Minority Views
[To accompany H.R. 1058]
The Committee on Energy and Commerce, to whom was referred
the bill (H.R. 1058) to establish a more uniform, transparent,
and modern process to authorize the construction, connection,
operation, and maintenance of international border-crossing
facilities for the import and export of oil and natural gas and
the transmission of electricity, having considered the same,
reports favorably thereon with an amendment and recommends that
the bill as amended do pass.
CONTENTS
Page
Purpose and Summary.............................................. 4
Background and Need for Legislation.............................. 4
Committee Action................................................. 7
Committee Votes.................................................. 8
Oversight Findings and Recommendations........................... 12
New Budget Authority, Entitlement Authority, and Tax Expenditures 12
Congressional Budget Office Estimate............................. 12
Federal Mandates Statement....................................... 12
Statement of General Performance Goals and Objectives............ 12
Duplication of Federal Programs.................................. 12
Related Committee and Subcommittee Hearings...................... 12
Committee Cost Estimate.......................................... 13
Earmark, Limited Tax Benefits, and Limited Tariff Benefits....... 13
Advisory Committee Statement..................................... 13
Applicability to Legislative Branch.............................. 13
Section-by-Section Analysis of the Legislation................... 14
Changes in Existing Law Made by the Bill, as Reported............ 15
Minority Views................................................... 16
The amendment is as follows:
Strike all after the enacting clause and insert the
following:
SECTION 1. SHORT TITLE.
This Act may be cited as the ``Promoting Cross-border Energy
Infrastructure Act''.
SEC. 2. STRENGTHENING NORTH AMERICAN ENERGY SECURITY.
(a) Authorization of Certain Energy Infrastructure Projects at an
International Boundary of the United States.--
(1) Authorization.--Except as provided in paragraph (3) and
subsection (e), no person may construct, connect, operate, or
maintain a border-crossing facility for the import or export of
oil or natural gas, or the transmission of electricity, across
an international border of the United States without obtaining
a certificate of crossing for the border-crossing facility
under this subsection.
(2) Certificate of crossing.--
(A) Requirement.--Not later than 120 days after final
action is taken, by the relevant official or agency
identified under subparagraph (B), under the National
Environmental Policy Act of 1969 (42 U.S.C. 4321 et
seq.) with respect to a border-crossing facility for
which a person requests a certificate of crossing under
this subsection, the relevant official or agency, in
consultation with appropriate Federal agencies, shall
issue a certificate of crossing for the border-crossing
facility unless the relevant official or agency finds
that the construction, connection, operation, or
maintenance of the border-crossing facility is not in
the public interest of the United States.
(B) Relevant official or agency.--The relevant
official or agency referred to in subparagraph (A) is--
(i) the Federal Energy Regulatory Commission
with respect to border-crossing facilities
consisting of oil or natural gas pipelines; and
(ii) the Secretary of Energy with respect to
border-crossing facilities consisting of
electric transmission facilities.
(C) Additional requirement for electric transmission
facilities.--In the case of a request for a certificate
of crossing for a border-crossing facility consisting
of an electric transmission facility, the Secretary of
Energy shall require, as a condition of issuing the
certificate of crossing under subparagraph (A), that
the border-crossing facility be constructed, connected,
operated, or maintained consistent with all applicable
policies and standards of--
(i) the Electric Reliability Organization and
the applicable regional entity; and
(ii) any Regional Transmission Organization
or Independent System Operator with operational
or functional control over the border-crossing
facility.
(3) Exclusions.--This subsection shall not apply to any
construction, connection, operation, or maintenance of a
border-crossing facility for the import or export of oil or
natural gas, or the transmission of electricity--
(A) if the border-crossing facility is operating for
such import, export, or transmission as of the date of
enactment of this Act;
(B) if a Presidential permit (or similar permit) for
the construction, connection, operation, or maintenance
has been issued pursuant to any provision of law or
Executive order; or
(C) if an application for a Presidential permit (or
similar permit) for the construction, connection,
operation, or maintenance is pending on the date of
enactment of this Act, until the earlier of--
(i) the date on which such application is
denied; or
(ii) two years after the date of enactment of
this Act, if such a permit has not been issued
by such date of enactment.
(4) Effect of other laws.--
(A) Application to projects.--Nothing in this
subsection or subsection (e) shall affect the
application of any other Federal statute to a project
for which a certificate of crossing for a border-
crossing facility is requested under this subsection.
(B) Natural gas act.--Nothing in this subsection or
subsection (e) shall affect the requirement to obtain
approval or authorization under sections 3 and 7 of the
Natural Gas Act for the siting, construction, or
operation of any facility to import or export natural
gas.
(C) Oil pipelines.--Nothing in this subsection or
subsection (e) shall affect the authority of the
Federal Energy Regulatory Commission with respect to
oil pipelines under section 60502 of title 49, United
States Code.
(b) Importation or Exportation of Natural Gas to Canada and Mexico.--
Section 3(c) of the Natural Gas Act (15 U.S.C. 717b(c)) is amended by
adding at the end the following: ``In the case of an application for
the importation of natural gas from, or the exportation of natural gas
to, Canada or Mexico, the Commission shall grant the application not
later than 30 days after the date on which the Commission receives the
complete application.''.
(c) Transmission of Electric Energy to Canada and Mexico.--
(1) Repeal of requirement to secure order.--Section 202(e) of
the Federal Power Act (16 U.S.C. 824a(e)) is repealed.
(2) Conforming amendments.--
(A) State regulations.--Section 202(f) of the Federal
Power Act (16 U.S.C. 824a(f)) is amended by striking
``insofar as such State regulation does not conflict
with the exercise of the Commission's powers under or
relating to subsection 202(e)''.
(B) Seasonal diversity electricity exchange.--Section
602(b) of the Public Utility Regulatory Policies Act of
1978 (16 U.S.C. 824a-4(b)) is amended by striking ``the
Commission has conducted hearings and made the findings
required under section 202(e) of the Federal Power
Act'' and all that follows through the period at the
end and inserting ``the Secretary has conducted
hearings and finds that the proposed transmission
facilities would not impair the sufficiency of electric
supply within the United States or would not impede or
tend to impede the coordination in the public interest
of facilities subject to the jurisdiction of the
Secretary.''.
(d) No Presidential Permit Required.--No Presidential permit (or
similar permit) shall be required pursuant to any provision of law or
Executive order for the construction, connection, operation, or
maintenance of an oil or natural gas pipeline or electric transmission
facility, or any border-crossing facility thereof.
(e) Modifications to Existing Projects.--No certificate of crossing
under subsection (a), or Presidential permit (or similar permit), shall
be required for a modification to--
(1) an oil or natural gas pipeline or electric transmission
facility that is operating for the import or export of oil or
natural gas or the transmission of electricity as of the date
of enactment of this Act;
(2) an oil or natural gas pipeline or electric transmission
facility for which a Presidential permit (or similar permit)
has been issued pursuant to any provision of law or Executive
order; or
(3) a border-crossing facility for which a certificate of
crossing has previously been issued under subsection (a).
(f) Prohibition on Revocation of Presidential Permits.--
Notwithstanding any other provision of law, the President may not
revoke a Presidential permit (or similar permit) issued pursuant to
Executive Order No. 13337 (3 U.S.C. 301 note), Executive Order No.
11423 (3 U.S.C. 301 note), Executive Order No. 12038 (43 Fed. Reg.
4957), Executive Order No. 10485 (18 Fed. Reg. 5397), or any other
Executive order for the construction, connection, operation, or
maintenance of an oil or natural gas pipeline or electric transmission
facility, or any border-crossing facility thereof, unless such
revocation is authorized by an Act of Congress.
(g) Effective Date; Rulemaking Deadlines.--
(1) Effective date.--Subsections (a) through (e), and the
amendments made by such subsections, shall take effect on the
date that is 1 year after the date of enactment of this Act.
(2) Rulemaking deadlines.--Each relevant official or agency
described in subsection (a)(2)(B) shall--
(A) not later than 180 days after the date of
enactment of this Act, publish in the Federal Register
notice of a proposed rulemaking to carry out the
applicable requirements of subsection (a); and
(B) not later than 1 year after the date of enactment
of this Act, publish in the Federal Register a final
rule to carry out the applicable requirements of
subsection (a).
(h) Definitions.--In this section:
(1) Border-crossing facility.--The term ``border-crossing
facility'' means the portion of an oil or natural gas pipeline
or electric transmission facility that is located at an
international boundary of the United States.
(2) Modification.--The term ``modification'' includes a
reversal of flow direction, change in ownership, change in flow
volume, addition or removal of an interconnection, or an
adjustment to maintain flow (such as a reduction or increase in
the number of pump or compressor stations).
(3) Natural gas.--The term ``natural gas'' has the meaning
given that term in section 2 of the Natural Gas Act (15 U.S.C.
717a).
(4) Oil.--The term ``oil'' means petroleum or a petroleum
product.
(5) Electric reliability organization; regional entity.--The
terms ``Electric Reliability Organization'' and ``regional
entity'' have the meanings given those terms in section 215 of
the Federal Power Act (16 U.S.C. 824o).
(6) Independent system operator; regional transmission
organization.--The terms ``Independent System Operator'' and
``Regional Transmission Organization'' have the meanings given
those terms in section 3 of the Federal Power Act (16 U.S.C.
796).
Purpose and Summary
H.R. 1058, the ``Promoting Cross-border Energy
Infrastructure Act,'' was introduced by Rep. Armstrong (R-ND)
on February 17, 2023. H.R. 1058 would establish a more uniform,
transparent, and modern process to authorize the construction,
connection, operation, and maintenance of international border-
crossing facilities for the import and export of oil and
natural gas and the transmission of electricity. H.R. 1058
would replace the existing Presidential Permit process that has
been established through Executive Order with a statutorily
directed process. Under the legislation, the Federal Energy
Regulatory Commission (FERC) would be authorized to review
applications for cross-border oil and natural gas pipelines,
and the Department of Energy (DOE) would be authorized to
review applications for cross-border electric transmission
facilities.
Background and Need for Legislation
Trade of oil, gas, and electricity among the United States,
Canada, and Mexico has resulted in one large, integrated North
American market. According to the Congressional Research
Service (CRS), the value of energy trade between the United
States and its North American neighbors exceeded $140 billion
in 2015, with $100 billion in U.S. energy imports and over $40
billion in exports.\1\ The expansion of cross-border energy
transportation infrastructure--pipelines for oil and natural
gas and transmission lines for electricity--is necessary to
enable increased energy trade. A number of new projects are
currently under construction or proposed to further expand
cross-border capacity, but they face considerable Federal
regulatory uncertainty.
---------------------------------------------------------------------------
\1\Congressional Research Service. Cross-Border Energy Trade in
North America: Present and Potential. January 30, 2017.
---------------------------------------------------------------------------
Congress has not asserted its authority to establish
procedures for permitting cross-border energy infrastructure.
In the absence of a statutorily directed process, agencies have
made decisions regarding cross-border energy infrastructure
within the context of their interpretations of a series of
Executive Orders dating back to the 1950's. Under these Orders,
the Secretary of State has the authority to issue Presidential
permits for cross-border liquids pipelines, the FERC for cross-
border natural gas pipelines, and the DOE for cross-border
electric transmission facilities.\2\
---------------------------------------------------------------------------
\2\The State Department makes permitting decisions based on
directives in Executive Order 11423 (E.O.), as amended by E.O. 13337.
FERC and DOE make permitting decisions in accordance with E.O. 10485,
as amended by E.O. 12038.
---------------------------------------------------------------------------
The U.S. currently has over 40 cross-border electric
transmission lines between the U.S. and Canada and the U.S. and
Mexico. These interconnections--the majority of which are
located at the Canadian border--have improved reliability, fuel
diversity, and efficiencies in system operations, particularly
for the New England, New York, and Midwest regions. Over the
last decade, the U.S. has experienced growing net electricity
imports from both Canada and Mexico, although Canada is by far
the greater trading partner. Future cross-border electricity
trade will be a function of both the development of future
generation capacity and the availability of cross-border
transmission infrastructure to move electric power. Under
current law, applications for new transmission projects will be
required to obtain a Presidential Permit and an export
authorization from the Secretary of Energy. There are currently
three pending export authorization applications and nine
pending Presidential Permit applications before DOE.\3\
---------------------------------------------------------------------------
\3\DOE, Grid Deployment Office, ``Pending Applications.''
---------------------------------------------------------------------------
There are over 50 operating cross-border natural gas
pipelines between the U.S. and Canada and the U.S. and
Mexico.\4\ Over the last five years, natural gas pipeline
capacity between the U.S. and Mexico has grown significantly.
According to the Energy Information Administration (EIA), U.S.
natural gas pipeline exports to Mexico in the summer of 2021
increased by 44% compared to the previous five-year monthly
average.\5\
---------------------------------------------------------------------------
\4\CRS Memorandum, ``Presidential Permitting of Border Crossing
Energy Facilities,'' at Table 1 (Aug. 16, 2013).
\5\https://www.eia.gov/todayinenergy/detail.php?id=48836
---------------------------------------------------------------------------
Under the current process to construct and operate a cross-
border natural gas pipeline, any person seeking to construct
and operate such facilities must obtain two, separate
authorizations from FERC for the facility and an authorization
from DOE to import or export natural gas. FERC authorization
under section 3 of the Natural Gas Act (NGA) is necessary for
siting, construction, or operation of facilities to import or
export natural gas. In addition, pursuant to Executive Order
10485 (September 3, 1954), as amended by Executive Order 12038
(February 3, 1978), a Presidential Permit also must be obtained
for the cross-border portion of the pipeline. Any person
seeking to import or export natural gas must also obtain a
separate authorization from DOE under section 3 of the NGA.\6\
For imports and exports to countries with which the U.S. has a
Free Trade Agreement, such as Canada and Mexico, DOE is
required to grant requests ``without modification or delay.''
---------------------------------------------------------------------------
\6\15 United States Code Sec. 717b.
---------------------------------------------------------------------------
Executive Order 12038 provides that, before a Presidential
Permit is issued, there must be a finding that the action is
consistent with the public interest. The criteria used for
determining if an application is consistent with the public
interest is identical to the criteria for approving
applications for the siting, construction, and operation of
import and export facilities under section 3 of the NGA.
For ``border facilities'' subject to Presidential Permit
and NGA section 3 review, discretion is given to FERC on a
project-by-project basis to determine the exact scope of the
project review, and therefore the exact parameters of the
Presidential Permit and section 3 application. FERC looks for a
physical feature on a project, such as a valve or meter on the
interior side of the U.S. border, as an endpoint for what may
be considered to lie within the Commission's jurisdiction and,
therefore, subject to its review procedures. From the physical
feature, the border crossing facilities would be construed to
extend to either the U.S./Canada or the U.S./Mexico border.
Crude oil trade between the U.S. and Canada is significant.
In 2019, crude oil imports to the U.S. from Canada averaged 3.8
million b/d, while the U.S. exported roughly 459,000 b/d to
Canada.\7\ In 2021, the U.S. imported over 212 million barrels
of crude oil from Mexico and exported over 1.6 million b/d of
refined petroleum products.\8\
---------------------------------------------------------------------------
\7\https://www.eia.gov/todayinenergy/detail.php?id=43995.
\8\https://www.trade.gov/country-commercial-guides/mexico-oil-and-
gas.
---------------------------------------------------------------------------
Under the current process to construct and operate an
international cross-border oil pipeline, any person seeking to
construct and operate such facilities must obtain a
Presidential Permit pursuant to Executive Order 13337 from the
Department of State. Under Executive Order 13337, the Secretary
of State is to approve cross-border oil pipelines that have
been determined to ``serve the national interest.'' Although
the Department of State will not necessarily evaluate the same
factors for each application for a Presidential Permit, its
evaluation considers such things as the environmental impacts
of the proposed project (associated closely with compliance
with the National Environmental Policy Act (NEPA)), the
stability of trading partners from whom the U.S. obtains crude
oil, the security of transport pathways for crude oil supplies
to the U.S., and the economic benefits to the U.S.
The Committee finds that cross-border permitting authority
should be explicitly granted by statute, as opposed to the
current framework created entirely by the Executive Branch. The
Committee is concerned by the inconsistent, ad hoc manner in
which Presidential Permit authority has been exercised among
the agencies to which it has been delegated by Executive Order.
This issue came into particular focus in the context of the
State Department's review of the Keystone XL pipeline proposal,
which originally applied for a Presidential Permit in 2008 and
did not receive approval until 2017, and subsequently had its
Presidential Permit revoked by President Biden in January 2021.
The Committee also finds that removing the Presidential Permit
authority from the executive branch will grant increased
regulatory certainty to cross-border facilities that have
already been issued a Presidential Permit.
The Committee finds that the statutorily directed process
for cross-border permitting embodied by H.R. 1058 would lead to
more objective and timely decisions, which in turn would create
jobs, strengthen our nation's energy security, and support
affordable and reliable energy for Americans.
H.R. 1058 would replace the Presidential Permit requirement
with a more transparent, efficient, and effective review
process. The legislation would require persons seeking to
construct, connect, operate, or maintain a border-crossing
facility for the import or export of oil or natural gas, or the
transmission of electricity, to obtain a Certificate of
Crossing. The term ``border-crossing facility,'' and thus what
may be considered jurisdictional for the purposes of the
Certificate of Crossing review, means the portion of the
pipeline or transmission facility that is located at an
international boundary. This description is consistent with
FERC's established procedures for review of Presidential Permit
and NGA section 3 applications. Under the legislation, the
relevant official would issue the certificate of crossing
unless it is found that the construction, connection,
operation, or maintenance of border facilities comprising the
cross-border segment is not in the public interest of the
United States. Consistent with FERC's existing procedures for
review of cross-border gas pipelines, the cross-border segment
of the border crossing facility would be identified as the
segment spanning from the international boundary to a physical
feature within close proximity, such as a valve or meter. The
legislation would have no effect on the requirement to obtain
approval or authorization under sections 3 and 7 of the NGA or
the authorities of FERC with respect to the siting of oil
pipelines upstream or downstream of a border crossing facility.
The legislation would also have no effect on any other Federal
statute that would apply to a project for which a Certificate
of Crossing is required, including any requirements of NEPA.
Committee Action
On January 31, 2023, the Committee on Energy and Commerce
held a full committee hearing on ``American Energy Expansion:
Strengthening Economic, Environmental, and National Security.''
The Committee received testimony from:
The Honorable Paul Dabbar, Former Under
Secretary of Energy; Distinguished Visiting Fellow,
Center on Global Enegry Policy, Columbia University;
CEO, Bohr Quantum Technology; and
Mr. Robert McNally, President, Rapidan
Energy Group; and
Ms. Donna Jackson, Director of Membership
Development, National Center for Public Policy
Research, Project 21; and
Dr. Ana Unruh Cohen, Former Majority Staff
Director, U.S. House Select Committee on the Climate
Crisis.
On February 7, 2023, the Subcommittees on Energy, Climate,
and Grid Security and Environment, Manufacturing, and Critical
Materials held a legislative hearing on 17 pieces of
legislation, including H.R. 1058. The Subcommittees received
testimony from:
The Honorable Mark Menezes, Former United
States Deputy Secretary of Energy, Principal at Global
Sustainable Energy Advisors, LLC, and Adjunct
Professor, Georgetown Law School; and
The Honorable Bernard McNamee, former
Commissioner at the Federal Energy Regulatory
Commission, Partner at McGuire Woods; and
Jeffrey Eshelman, President and CEO,
Independent Petroleum Association of America; and
Katie Sweeney, Executive Vice President and
COO, National Mining Association; and
Raul Garcia, Legislative Director for
Healthy Communities, Earthjustice; and
Tyson Slocum, Director of the Energy
Program, Public Citizen.
On February 28, 2023, the Subcommittee on Energy, Climate,
and Grid Security met in open markup session and forwarded H.R.
1058, as amended, to the full Committee by a recorded vote of
17 yeas and 10 nays. On March 9, 2023, the full Committee on
Energy and Commerce met in open markup session and ordered H.R.
1058 favorably reported to the House by a recorded vote of 28
yeas and 20 nays.
Committee Votes
Clause 3(b) of rule XIII requires the Committee to list the
record votes on the motion to report legislation and amendments
thereto. The following reflects the record votes taken during
the Committee consideration:
[GRAPHIC(S) NOT AVAILABLE IN TIFF FORMAT]
OVERSIGHT FINDINGS AND RECOMMENDATIONS
Pursuant to clause 2(b)(1) of rule X and clause 3(c)(1) of
rule XIII, the Committee held a hearing and made findings that
are reflected in this report.
NEW BUDGET AUTHORITY, ENTITLEMENT AUTHORITY, AND TAX EXPENDITURES
Pursuant to clause 3(c)(2) of rule XIII, the Committee
finds that H.R. 1058 would result in no new or increased budget
authority, entitlement authority, or tax expenditures or
revenues.
Congressional Budget Office Estimate
Pursuant to clause 3(c)(3) of rule XIII, at the time this
report was filed, the cost estimate prepared by the Director of
the Congressional Budget Office pursuant to section 402 of the
Congressional Budget Act of 1974 was not available.
FEDERAL MANDATES STATEMENT
The Committee adopts as its own the estimate of Federal
mandates prepared by the Director of the Congressional Budget
Office pursuant to section 423 of the Unfunded Mandates Reform
Act.
STATEMENT OF GENERAL PERFORMANCE GOALS AND OBJECTIVES
Pursuant to clause 3(c)(4) of rule XIII, the general
performance goal or objective of this legislation is to
establish coordinated procedures to authorize the construction,
connection, operation, and maintenance of international border-
crossing facilities for the import and export of oil and
natural gas and the transmission of electricity.
DUPLICATION OF FEDERAL PROGRAMS
Pursuant to clause 3(c)(5) of rule XIII, no provision of
H.R. 1058 is known to be duplicative of another Federal
program, including any program that was included in a report to
Congress pursuant to section 21 of Public Law 111-139 or the
most recent Catalog of Federal Domestic Assistance.
RELATED COMMITTEE AND SUBCOMMITTEE HEARINGS
Pursuant to clause 3(c)(6) of rule XIII,
(1) the following hearings were used to develop or consider
H.R. 1058:
On January 31, 2023, the Committee on Energy and Commerce
held an oversight hearing entitled, ``American Energy
Expansion: Strengthening Economic, Environmental, and National
Security.'' The Committee received testimony from:
The Honorable Paul Dabbar, Former Under
Secretary of Energy, Department of Energy;
Robert McNalley, President, Rapidan Energy
Group, LLC;
Donna Jackson, Director of Membership
Development--National Center for Public Policy
Research, Project 21; and
Ana Unruh Cohen, Former Majority Staff
Director, U.S. House Select Committee on the Climate
Crisis.
On February 16, 2023, the Subcommittee on Energy, Climate,
and Grid Security held a field hearing in Midland, Texas,
entitled, ``American Energy Expansion: Improving Local
Economies and Communities'' Way of Life.'' The Committee
received testimony from:
The Honorable Lori Blong, Mayor of Midland,
Texas, and President of Octane Energy;
Adrian Carrasco, Chairman Midland Hispanic
Chamber of Commerce, and President of Premier Energy
Services;
Steven Pruett, President and CEO, Elevation
Resources, and Chairman of the Board for Independent
Petroleum Association of America; and
Dr. Michael Zavada, Professor of Biology and
Geosciences, and Chair, Department of Geosciences at
The University of Texas--Permian Basin.
(2) The following related hearing was held:
On February 7, 2023, the Subcommittees on Energy, Climate,
and Grid Security and Environment, Manufacturing, and Critical
Materials held a joint hearing entitled, ``Unleashing American
Energy, Lowering Energy Costs, and Strengthening Supply
Chains,'' on 17 pieces of legislation, including H.R. 1058. The
Subcommittees received testimony from:
The Honorable Mark Menezes, Former United
States Deputy Secretary of Energy, Department of
Energy;
The Honorable Bernard McNamee, Former
Commissioner, Federal Energy Regulatory Commission;
Jeffrey Eshelman, II, President and Chief
Executive Officer, Independent Petroleum Association of
America;
Katie Sweeney, Executive Vice President and
Chief Operating Officer, National Mining Association;
Raul Garcia, Legislative Director for
Healthy Communities, Earthjustice; and
Tyson Slocum, Director of the Energy
Program, Public Citizen.
COMMITTEE COST ESTIMATE
Pursuant to clause 3(d)(1) of rule XIII, the Committee
adopts as its own the cost estimate prepared by the Director of
the Congressional Budget Office pursuant to section 402 of the
Congressional Budget Act of 1974. At the time this report was
filed, the estimate was not available.
EARMARK, LIMITED TAX BENEFITS, AND LIMITED TARIFF BENEFITS
Pursuant to clause 9(e), 9(f), and 9(g) of rule XXI, the
Committee finds that H.R. 1058 contains no earmarks, limited
tax benefits, or limited tariff benefits.
ADVISORY COMMITTEE STATEMENT
No advisory committees within the meaning of section 5(b)
of the Federal Advisory Committee Act were created by this
legislation.
APPLICABILITY TO LEGISLATIVE BRANCH
The Committee finds that the legislation does not relate to
the terms and conditions of employment or access to public
services or accommodations within the meaning of section
102(b)(3) of the Congressional Accountability Act.
SECTION-BY-SECTION ANALYSIS OF THE LEGISLATION
Section 1. Short title
This section provides the short title of ``Promoting Cross-
Border Energy Infrastructure Act.''
Section 2. Approval for border-crossing facilities
Section 2(a)(1) provides that no person may construct,
connect, operate, or maintain a border-crossing facility for
the import or export of oil or natural gas, or the transmission
of electricity, across an international border of the United
States without obtaining a certificate of crossing.
Section 2(a)(2) instructs relevant officials or agencies,
in consultation with appropriate Federal agencies, to issue a
certificate of crossing for a border-crossing facility within
120 days after final action is taken, unless the relevant
official or agency finds that the construction, connection,
operation, or maintenance of the border-crossing facility is
not in the public interest of the United States. The relevant
official or agency with respect to border-crossing facilities
consisting of oil or natural gas pipelines is the Federal
Energy Regulatory Commission. The relevant official or agency
with respect to electric transmission facilities is the
Secretary of Energy. This section also provides additional
requirements for electric transmission facilities.
Section 2(a)(3) instructs that subsection (a) shall not
apply to border-crossing facilities that are in operation on
the date of enactment of this Act if a permit as described in
subsection (d) has been issued, or if a permit as described in
subsection (d) is pending and meets certain requirements.
Section 2(a)(4) specifies that nothing in subsection (a) or
subsection (e) shall affect the application of any other
Federal statute to a project for which a certificate of
crossing for a border-crossing facility is requested; the
requirement to obtain approval or authorization under sections
3 and 7 of the NGA or the authority of the FERC with respect to
oil pipelines under section 60502 of title 49, United States
Code.
Section 2(b) amends section 3(c) of the NGA directing FERC
to grant an application for the importation of natural gas
from, or exportation of natural gas to, Canada and Mexico not
later than 30 days after the date on which the Commission
receives the complete application.
Section 2(c) repeals section 202(e) of the Federal Power
Act, eliminating the requirement to secure an order from FERC
to transmit electric energy from the United States to a foreign
country. This section also contains conforming amendments
related to State regulations and seasonal diversity electricity
exchange.
Section 2(d) specifies that no Presidential Permit or any
other Executive Order shall be necessary for the construction,
connection, operation, or maintenance of an oil or natural gas
pipeline or electric transmission facility, or any border-
crossing facility.
Section 2(e) directs that no certificate of crossing under
subsection (a) or permit described in subsection (d) shall be
required for a modification to an oil or natural gas pipeline
or electric transmission facility that is operating for the
import or export of energy as of the date of enactment of this
Act. Additionally, a certificate of crossing or a permit shall
not be required for a modification to an oil or natural gas
pipeline or electric transmission facility for which a permit
described in subsection (d) has been issued, or for which a
certificate of crossing has previously been issued under
subsection (a).
Section 2(f) specifies that the President may not revoke a
Presidential permit issued pursuant to a relevant Executive
Order for the construction, connection, operation, or
maintenance of an oil or natural gas pipeline or electric
transmission facility unless such revocation is authorized by
Congress.
Section 2(g) specifies that subsections (a) through (c)
shall take effect on the date that is one year after the date
of enactment of this Act. Each relevant official or agency
shall publish in the Federal Register a notice of a proposed
rulemaking to carry out the requirements of subsection (a)
within 180 days after the date of enactment of this Act. Not
later than one year after the date of enactment, the relevant
officials or agencies shall publish a final rule in the Federal
Register.
Section 2(h) provides definitions for terms used throughout
this section.
CHANGES IN EXISTING LAW MADE BY THE BILL, AS REPORTED
With respect to the requirement of clause 3(e) of rule XIII
of the Rules of the House of Representatives, changes in
existing law made by the bill, as reported, this section was
not made available to the Committee in time for the filing of
this report.
Minority Views
H.R. 1058 would substantially weaken the Federal review and
authorization process for cross-border crude oil, petroleum
product, and natural gas pipelines and electricity transmission
lines. The new process established by the bill effectively
exempts cross-border crude oil and petroleum product pipelines
from environmental reviews under the National Environmental
Policy Act (NEPA) by narrowing the scope of Federal
authorization to just the portion of the project crossing the
border--although the bill is unclear as to the actual scope of
its application. The new process created by the bill also
creates a presumption that cross-border energy infrastructure
projects are in the public interest, but forces the Department
of Energy (DOE) and the Federal Energy Regulatory Commission
(FERC) to weigh in on matters of foreign diplomacy and national
security and does not specify the agencies that DOE or FERC
must consult with before making a decision on national
interest.
The cumulative impact of these changes would be to allow
cross-border energy projects to be approved with less
environmental and public interest scrutiny than domestic energy
projects. Citizens and other interested parties would be left
with few avenues to request information or mitigating actions.
Currently, proposed crude oil, petroleum product, and
natural gas pipelines and electricity transmission lines that
cross international borders must obtain a Presidential permit
to do so.\1\ A series of executive orders have delegated the
powers to the Department of State (DOS) for crude oil and
petroleum product pipelines2, 3, 4, DOE for
electricity transmission lines\5\, and FERC for natural gas
pipelines.6, 7 Executive Order 13867 restructured
the process for granting Presidential permits for crude oil and
petroleum product pipelines and requires that DOS issue a
recommendation to the President with regards to if issuing the
permit would or would not serve the foreign policy interests of
the United States, but provides that ``any decision to issue,
deny, or amend a permit under this section shall be made solely
by the President''.\8\ The executive order delegating power to
DOE and FERC for cross-border electricity transmission lines
and natural gas pipelines explicitly allows those agencies to
issue Presidential permits.
---------------------------------------------------------------------------
\1\Congressional Research Service, Presidential Permits for Border
Crossing Energy Facilities (Aug. 1, 2017) (R43261).
\2\Exec. Order No. 11423, 33 Fed. Reg. 11741 (Aug. 16, 1968).
\3\Exec. Order No. 13337, 69 Fed. Reg. 25299 (May 5, 2004).
\4\Exec. Order No. 13867, 84 Fed. Reg. 15491 (Apr. 15, 2019).
\5\Exec. Order No. 10485, 18 Fed. Reg. 5397 (Sept. 3, 1953).
\6\Id.
\7\Department of Energy, Delegation Order No. S1-DEL-FERC-2006 to
the Federal Energy Regulatory Commission (May 16, 2006).
\8\Exec. Order No. 13867, 84 Fed. Reg. 15491 (Apr. 15, 2019).
---------------------------------------------------------------------------
The current process for crude oil and petroleum product
pipelines requires that DOS evaluate the pipeline in its
entirety when determining if a proposed pipeline serves the
foreign policy interests of the United States.\9\ This
determination about the entirety of the pipeline triggers an
environmental review under NEPA--and, as the decision covers
the entire pipeline (or at least its portion within the United
States), so must the environmental review. H.R. 1058 would gut
that requirement as it restricts DOE's review of the pipeline
to just the portion crossing the international border--meaning
that the agency's environmental review would be constrained to
just the infinitesimal sliver of the pipeline crossing the
border. As oil pipelines do not need to seek siting authority
from any Federal agency, this would rob the Federal government
of the only chance it has to conduct a comprehensive
environmental review of a cross-border crude oil or petroleum
product pipeline.
---------------------------------------------------------------------------
\9\Id.
---------------------------------------------------------------------------
A major flaw of the bill's is the fact that it circumvents
the process that is currently in place for DOS and the
Department of Defense (DOD) to weigh in on the national
security and foreign policy implications of cross-border energy
infrastructure. Executive Order 10485 requires that DOE or FERC
obtain favorable recommendations from both DOS and DOD for a
cross-border project before issuing a Presidential permit, and
if the agencies cannot come to agreement on whether or not a
permit should be issued, the decision is passed up to the
President.\10\ While section 2(a)(2)(A) of H.R. 1058 requires
that the relevant official or agency consult with ``the
appropriate Federal agencies,'' it neither defines which
Federal agencies are appropriate nor requires that the relevant
official or agency heed the conclusions of the appropriate
Federal agencies, potentially setting up a situation in which
DOE or FERC could approve a project over the foreign policy or
national security objections of DOS or DOD, requiring DOE and
FERC to become arbiters of foreign policy in addition to their
jurisdictions over energy policy.
---------------------------------------------------------------------------
\10\Exec. Order No. 10485, 18 Fed. Reg. 5397 (Sept. 3, 1953).
---------------------------------------------------------------------------
Additionally, section 2(g)(1) of H.R. 1058 is troublingly
vague--it is unclear if the term ``border-crossing facility''
consists of just the infinitesimal sliver of the pipeline that
physically straddles the border between the United States and a
foreign country, a span of dozens, hundreds, or thousands of
feet around that sliver, or the entirety of the pipeline. What
the definition is has major implications for environmental
reviews, as discussed above, and for FERC in general: currently
the commission has no experience in siting oil pipelines, and
the bill provides no resources for the commission to hire staff
to site cross-border oil pipelines. In its report, the majority
claims that ``the cross-border segment of the border-crossing
facility would be identified as the segment spanning from the
international boundary to a physical feature within close
proximity, such as a valve or meter.'' However, there is no
statutory language requiring this within the text of H.R. 1058.
The majority also claims in its report that ``the
legislation would also have no effect on any other Federal
statute that would apply to a project for which a Certificate
of Crossing is required, including any requirements of NEPA.''
Unfortunately, the only concrete piece of evidence indicates
that statement may not be the case. When nearly identical
legislation was considered on the House floor during the first
session of the 115th Congress, then-Rep. Gene Green (D-TX)
offered an amendment clarifying that nothing in the bill
affected the scope of reviews required pursuant to NEPA.\11\
The amendment was accepted by voice vote. However, when the
bill was re-introduced this Congress, the text of the bill was
effectively identical to the version that had been engrossed by
the House in the 115th Congress\12\, except that the language
relating to Rep. Green's amendment had been removed. An
identical amendment by Rep. Veasey was defeated on a recorded
vote in Full Committee markup, suggesting that the majority's
understanding is that the bill, as written, does affect the
scope of environmental reviews under NEPA.
---------------------------------------------------------------------------
\11\Congressional Record, H6019 (July 19, 2017).
\12\H.R. 2883, 115th Cong. (2017).
---------------------------------------------------------------------------
The bill is also contradictory and contains conflicting
deadlines. Section 2(a)(2)(A) of the bill requires that the
relevant official or agency grant a certificate within 120 days
after the agency takes a final action under NEPA (unless that
relevant official or agency finds that the facility is not in
the public interest of the United States). However, section
2(b) amends the Natural Gas Act (NGA) to require that FERC
grant an application to export natural gas to Canada or Mexico
within 30 days of receipt of the application--making no mention
of the time required to conduct an environmental review.
H.R. 1058 also guts the power of the Federal government to
put conditions on the export of electricity. Section 202(e) of
the Federal Power Act (FPA) requires FERC to grant the export
of electricity as long as such export does not impair the
domestic electricity supply of the United States, but allows
the Commission to add terms and conditions it deems appropriate
on to the application. Section 2(c)(1) of H.R. 1058 repeals
section 202(e) of the FPA and, under section 2(a)(2)(C) of the
bill, the only condition DOE is allowed to impose upon a cross-
border electricity line is that it conform with the policies
and standards of electricity reliability entities and any
relevant Independent System Operator or Regional Transmission
Organization. The removal of the 202(e) conditioning authority
could undermine FERC's mandate to ensure non-discriminatory
open access to the national grid, as operators of cross-border
transmission facilities could demand market participants pay
them discriminatory or onerous tariffs.
Sections 2(e) and 2(h)(2) effectively create an unlimited
right to expand existing cross-border facilities without having
to go through the already abbreviated process the bill creates.
Specifically, the fact that a ``change in flow volume'' through
a pipeline is defined as a modification that does not require
an additional certificate (and, by extension, does not require
an environmental review) is particularly egregious, as the
environmental, foreign policy, and national security impacts of
a drastic increase in volume of energy flowing through a cross-
border facility could dwarf the original impacts of the
facility with zero Federal oversight.
Sections 2(a)(3)(C) and 2(f) (which was added as an
amendment by Rep. Tim Walberg (R-MI) at Subcommittee markup) of
H.R. 1058 create a double standard, allowing projects that have
been denied a Presidential permit or kept waiting for two years
a second run at an authorization while prohibiting the
President from revoking permits that were previously issued.
On February 7, 2023, at a joint legislative hearing of the
Subcommittees on Energy, Climate, and Grid Security and
Environment, Manufacturing, and Critical Materials, the
Subcommittees heard testimony from Mr. Tyson Slocum, who
testified that H.R. 1058 would allow natural gas companies to
dodge the requirements of section 3 of the Natural Gas Act, and
more easily export natural gas to Mexico, where it would then
be re-exported abroad through an LNG terminal. He also
testified that increased LNG exports increased domestic natural
gas prices, meaning that H.R. 1058 would be likely to increase
the prices that American consumers pay for natural gas.\13\
---------------------------------------------------------------------------
\13\House Committee on Energy and Commerce, Testimony of Tyson
Slocum, Director of the Energy Program, Public Citizen, Hearing on
Unleashing American Energy, Lowering Energy Costs, and Strengthening
Supply Chains, 118th Cong. (Feb. 7, 2023).
---------------------------------------------------------------------------
During the Subcommittee and Full Committee markups of H.R.
1058, Democrats offered several amendments to the bill to
address their concerns. At the Subcommittee markup, the Ranking
Member of the Subcommittee on Energy, Climate, and Grid
Security, Rep. Diana DeGette (D-CO) offered an amendment that
would have flipped the presumption of public interest, and
required DOE and FERC to only grant certificates if the
agencies believed that a cross-border project was in the public
interest. At the Full Committee markup, Rep. Kathy Castor (D-
FL) offered an amendment that would have prevented the bill
from taking effect until DOE certified that it would not
increase crude oil, petroleum product, natural gas, or
electricity prices. Rep. Marc Veasey (D-TX) also offered an
amendment that affirmed that the bill did not affect the scope
of any environmental review required under NEPA--identical to
the amendment accepted by the full House on the floor in 2017.
All three amendments failed on a recorded vote.
For the reasons stated above, we dissent from the views
contained in the Committee's report.
Frank Pallone, Jr.,
Ranking Member, Committee on Energy and Commerce.
[all]