Background and Need for Legislation
The General Services Administration's (GSA's) Facilities
Standards for the Public Buildings Service, also known as the
``P100'' sets mandatory design standards and performance
criteria for GSA-owned buildings.\1\ The P100 is a mandatory
standard and applies to GSA-owned facilities regardless of
funding source.\2\ It applies to new construction, including
lease construction, repairs and alterations; historic
preservation; as well as customer-funded projects through
reimbursable work authorizations.\3\
---------------------------------------------------------------------------
\1\GSA, Facilities Standards (P100) Overview, (last updated Sept.
18, 2023), available at https://www.gsa.gov/real-estate/design-and-
construction/engineering/facilities-standards-for-the-public-buildings-
service.
\2\GSA, P100 Facilities Standards for the Public Buildings Service,
(Oct. 2021, with 2022 Addendum), available at https://www.gsa.gov/
system/files/P100%202022%20Addendum
%20Final_.pdf.
\3\Id.
---------------------------------------------------------------------------
The P100 sets requirements for all aspects of construction
and repairs and alterations, including health and safety,
sustainability, security, application of building codes and
building rating systems, space measurement and building
efficiency, building operations and maintenance, energy usage,
building systems, and materials. Therefore, the P-100 not only
impacts the quality of the projects but also the costs,
delivery timeline, competition and sourcing of construction
services and materials.\4\ For example, cost models in a 2016
National Institute of Building Sciences (NIBS) report indicated
that GSA repair and alteration projects cost roughly 15 to 25
percent more than for comparable private sector building
projects.\5\ Further the report showed that the higher costs
for GSA projects primarily included design and procurement
requirements specific to GSA's design standards.\6\
---------------------------------------------------------------------------
\4\Id.
\5\GAO, GAO-20-144, Federal Buildings: GSA Can Improve Its
Communication about and Assessment of Major Construction Projects,
(Dec. 2019), available at https://www.gao.gov/assets/710/706608.pdf.
\6\Id.
---------------------------------------------------------------------------
Given the impacts of the P100 building standards, H.R. 6317
would direct GSA to revise the process for updating and
changing the standards by ensuring more transparency, including
requiring a public comment period and publication of updates
and changes in the Federal Register and on the GSA website.
Hearings
For the purposes of rule XIII, clause 3(c)(6)(A) of the
118th Congress, the following hearing was used to develop or
consider H.R. 6317:
On July 13, 2023, the Subcommittee on Economic Development,
Public Buildings, and Emergency Management of the Committee on
Transportation and Infrastructure held a hearing entitled,
``When the Lights Are On but No One's Home: An Examination of
Federal Office Space Utilization.'' The hearing discussed
Federal real estate, including office space utilization. The
Subcommittee received testimony from Ms. Nina Albert,
Commissioner, Public Buildings Service, GSA; and Mr. David
Marroni, Acting Director, Physical Infrastructure, Government
Accountability Office (GAO).
LEGISLATIVE HISTORY AND CONSIDERATION
H.R. 6317 was introduced in the United States House of
Representatives on November 8, 2023, by Ms. Titus of Nevada and
referred to the Committee on Transportation and Infrastructure.
Within the Committee on Transportation and Infrastructure, H.R.
6317 was referred to the Subcommittee on Economic Development,
Public Buildings, and Emergency Management. The Subcommittee on
Economic Development, Public Buildings, and Emergency
Management was discharged from further consideration of H.R.
6317 on November 15, 2023.
The Committee considered H.R. 6317 on November 15, 2023,
and ordered the measure to be reported to the House with a
favorable recommendation, without amendment, by voice vote.
Committee Votes
Clause 3(b) of rule XIII of the Rules of the House of
Representatives requires each committee report to include the
total number of votes cast for and against on each record vote
on a motion to report and on any amendment offered to the
measure or matter, and the names of those members voting for
and against.
No recorded votes were requested during consideration of
H.R. 6317.
COMMITTEE OVERSIGHT FINDINGS AND RECOMMENDATIONS
With respect to the requirements of clause 3(c)(1) of rule
XIII of the Rules of the House of Representatives, the
Committee's oversight findings and recommendations are
reflected in this report.
NEW BUDGET AUTHORITY AND TAX EXPENDITURES
Clause 3(c)(2) of rule XIII of the Rules of the House of
Representatives does not apply where a cost estimate and
comparison prepared by the Director of the Congressional Budget
Office under section 402 of the Congressional Budget Act of
1974 has been timely submitted prior to the filing of the
report and is included in the report. Such a cost estimate is
included in this report.
CONGRESSIONAL BUDGET OFFICE COST ESTIMATE
With respect to the requirement of clause 3(c)(3) of rule
XIII of the Rules of the House of Representatives and section
402 of the Congressional Budget Act of 1974, the Committee has
received the enclosed cost estimate for H.R. 6317 from the
Director of the Congressional Budget Office:
H.R. 6317 would require the General Services Administration
(GSA) to amend its process for updating any guidance documents
that specify design standards or performance criteria for
federal buildings managed by GSA, including the P100 document.
(The P100 is GSA's main document detailing the mandatory
standards for its facilities.) Under the bill, GSA would be
required to accept public comment on any changes to those
guidance documents and publish a summary of the comments and
any changes to the documents in the federal register and on the
GSA website. H.R. 6317 also would require GSA to report to the
Congress on any revisions to its process for updating guidance
documents.
Using information from GSA, CBO estimates that the
administrative costs for accepting and reviewing public
comments related to updates of the P100 and reporting to the
Congress would total less than $500,000 over the 2024-2028
period. Any spending would be subject to the availability of
appropriated funds.
The CBO staff contact for this estimate is Mathew Pickford.
The estimate was reviewed by H. Samuel Papenfuss, Deputy
Director of Budget Analysis.
Phillip L. Swagel,
Director, Congressional Budget Office.
PERFORMANCE GOALS AND OBJECTIVES
With respect to the requirement of clause 3(c)(4) of rule
XIII of the Rules of the House of Representatives, the
performance goal and objective of this legislation is to direct
the Administrator of GSA to require GSA to revise the process
by which the Administrator of GSA updates or changes any P100
guidance document or other guidance document establishing
mandatory design standards and performance criteria for
federally owned buildings.
DUPLICATION OF FEDERAL PROGRAMS
Pursuant to clause 3(c)(5) of rule XIII of the Rules of the
House of Representatives, the Committee finds that no provision
of H.R. 6317 establishes or reauthorizes a program of the
Federal government known to be duplicative of another Federal
program, a program that was included in any report from the
Government Accountability Office to Congress pursuant to
section 21 of Public Law 111-139, or a program related to a
program identified in the most recent Catalog of Federal
Domestic Assistance.
CONGRESSIONAL EARMARKS, LIMITED TAX BENEFITS, AND LIMITED TARIFF
BENEFITS
In compliance with clause 9 of rule XXI of the Rules of the
House of Representatives, this bill, as reported, contains no
congressional earmarks, limited tax benefits, or limited tariff
benefits as defined in clause 9 (e), 9(f), or 9(g) of the rule
XXI.
FEDERAL MANDATES STATEMENT
The Committee adopts as its own the estimate of Federal
mandates prepared by the Director of the Congressional Budget
Office pursuant to section 423 of the Unfunded Mandates Reform
Act (Public Law 104-4).
PREEMPTION CLARIFICATION
Section 423 of the Congressional Budget Act of 1974
requires the report of any Committee on a bill or joint
resolution to include a statement on the extent to which the
bill or joint resolution is intended to preempt state, local,
or tribal law. The Committee finds that H.R. 6317 does not
preempt any state, local, or tribal law.
ADVISORY COMMITTEE STATEMENT
No advisory committees within the definition of Section
5(b) of the appendix to Title 5, United States Code, are
created by this legislation.
APPLICABILITY TO LEGISLATIVE BRANCH
The Committee finds that the legislation does not relate to
the terms and conditions of employment or access to public
services or accommodations within the meaning of section
102(b)(3) of the Congressional Accountability Act (Public Law
104-1).
SECTION-BY-SECTION ANALYSIS OF THE LEGISLATION
Section 1. Revision of design standards
This section requires GSA to revise the process by which
the Administrator of GSA updates or changes any P100 guidance
document or other guidance document establishing mandatory
design standards and performance criteria for Federally owned
buildings, not later than six months after the date of
enactment.
This section specifically requires the Administrator to
ensure the process includes a public comment period,
publication of updates in the Federal Register and on GSA's
website, and a summary of any comments received during the
comment period.
This section further requires GSA to submit a report to the
Committee on Transportation and Infrastructure of the House of
Representatives and Committee on Environment and Public Works
of the Senate describing the revisions made to the process.
CHANGES IN EXISTING LAW MADE BY THE BILL, AS REPORTED
As reported by the Committee, H.R. 6317 makes no changes in
existing law.