H. Rept. 118-834

HELP HOOVER DAM ACT

2024-12-10

Committees

Associated legislation

Text

Background and Need for Legislation

In 1928, the Boulder Canyon Project Act was signed into law to authorize the construction of Hoover Dam and other water projects along the Colorado River.\1\ This legislation appropriated $165 million for Arizona, California, and Nevada (collectively called the lower basin states) to build water projects with flood control as their primary purpose.\2\ Construction on the dam began in 1930, and the associated hydropower generators came online in 1937. Today, 40 million people rely on the Colorado River for water, and 1.3 million rely on it for electricity.\3\ --------------------------------------------------------------------------- \1\National Archives, Boulder Canyon Project Act (1928). https:// www.archives.gov/milestone-documents/boulder-canyon-project-act. \2\Id. \3\Id. --------------------------------------------------------------------------- In addition to the fees collected through power rates, the Department of Energy directs the Western Area Power Administration (WAPA) to collect $2 million annually from Hoover contractors to fund Post Retirement Benefits (PRBs) for WAPA and Bureau of Reclamation (Reclamation) federal employees to cover any gap in benefits from Department of Labor allocations.\4\ However, Congress provides annual appropriations for PRBs. To date, $45 million has been collected from ratepayers. --------------------------------------------------------------------------- \4\American Public Power Association, Groups Support Bill That Makes Funds Available for Hoover Dam Projects. https:// www.publicpower.org/periodical/article/groups-support-bill-makes-funds- available-hoover-dam-projects. --------------------------------------------------------------------------- H.R. 7776 would authorize the Reclamation to access the $45 million of ratepayer funding for the purpose of the operation, maintenance, and improvement of the Hoover Dam.\5\ Ms. Gail Bates, the Assistant Director of Hydropower for the Colorado River Commission of Nevada, recently said that there is $150 million in maintenance planned at the Hoover Dam over the next decade.\6\ H.R. 7776 has five Republican cosponsors and five Democrat cosponsors. --------------------------------------------------------------------------- \5\Congresswoman Lee, NV Congressional Delegation Lead Bipartisan Legislation to Recover Millions in Unused Funding for Hoover Dam. https://susielee.house.gov/media/press-releases/congresswoman-lee-nv- congressional-delegation-lead-bipartisan-legislation. \6\The Las Vegas Sun. ``Nevada lawmakers back bill that aims to free up Hoover Dam funding.'' March 30, 2024. https://lasvegassun.com/ news/2024/mar/30/nevada-lawmakers-back-bill-that-aims-to-free-up-fu/. ---------------------------------------------------------------------------

Committee Action

H.R. 7776 was introduced on March 21, 2024, by Rep. Susie Lee (D-NV). The bill was referred to the Committee on Natural Resources, and within the Committee to the Subcommittee on Water, Wildlife and Fisheries. On May 22, 2024, the Subcommittee on Water, Wildlife and Fisheries held a hearing on the bill. On June 12, 2024, the Committee on Natural Resources met to consider the bill. The Subcommittee on Water, Wildlife and Fisheries was discharged from further consideration of H.R. 7776 by unanimous consent. The bill was ordered favorably reported to the House of Representatives by unanimous consent.

Hearings

For the purposes of clause 3(c)(6) of House rule XIII, the following hearing was used to develop or consider this measure: hearing by the Subcommittee on Water, Wildlife and Fisheries held on May 22, 2024.

Section-by-Section Analysis

Section 1. Short title Establishes the short title of this act as the ``Help Hoover Dam Act.'' Section 2. Authorization to expend amounts Allows the Bureau of Reclamation to access stranded funds for the sole purpose of operations and maintenance costs at the Hoover Dam. Committee Oversight Findings and Recommendations Regarding clause 2(b)(1) of rule X and clause 3(c)(1) of rule XIII of the Rules of the House of Representatives, the Committee on Natural Resources' oversight findings and recommendations are reflected in the body of this report. Compliance With House Rule XIII and Congressional Budget Act 1. Cost of Legislation and the Congressional Budget Act. With respect to the requirements of clause 3(c)(2) and (3) of rule XIII of the Rules of the House of Representatives and sections 308(a) and 402 of the Congressional Budget Act of 1974, the Committee has received the following estimate for the bill from the Director of the Congressional Budget Office: [GRAPHIC(S) NOT AVAILABLE IN TIFF FORMAT] H.R. 7776 would allow the Department of the Interior (DOI) to use money from a particular account within the Colorado River Dam Fund to pay for operations, maintenance, and repairs of the Hoover Dam. Under current law, amounts collected from Hoover Dam project contractors are deposited into the fund and, excepting that one account, are available to be spent for those purposes. The bill would allow DOI to draw from that account for Hoover Dam projects. For this estimate, CBO assumes that the bill will be enacted before the end of calendar year 2024. Using information from the Office of Management and Budget, CBO estimates that $48 million currently in the fund would become available to DOI under the bill; CBO does not expect any additional deposits into that account. Based on historical spending patterns, CBO estimates that enacting the bill would cost $48 million over the 2025-2034 period. That spending would be classified as direct spending because the bill would allow those amounts to be spent without further appropriation. The costs of the legislation, detailed in Table 1, fall within budget function 300 (natural resources and environment). TABLE 1.--ESTIMATED INCREASES IN DIRECT SPENDING UNDER H.R. 7776 -------------------------------------------------------------------------------------------------------------------------------------------------------- By fiscal year, millions of dollars-- ------------------------------------------------------------------------------------------------- 2025- 2025- 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2029 2034 -------------------------------------------------------------------------------------------------------------------------------------------------------- Estimated Budget Authority............................ 48 0 0 0 0 0 0 0 0 0 48 48 Estimated Outlays..................................... 29 17 2 0 0 0 0 0 0 0 48 48 -------------------------------------------------------------------------------------------------------------------------------------------------------- The CBO staff contact for this estimate is Alaina Rhee. The estimate was reviewed by H. Samuel Papenfuss, Deputy Director of Budget Analysis. Phillip L. Swagel, Director, Congressional Budget Office. 2. General Performance Goals and Objectives. As required by clause 3(c)(4) of rule XIII, the general performance goal or objective of this bill is to amend the Boulder Canyon Project Act to authorize the Secretary of the Interior to expend amounts in the Colorado River Dam fund, and for other purposes. Earmark Statement This bill does not contain any Congressional earmarks, limited tax benefits, or limited tariff benefits as defined under clause 9(e), 9(f), and 9(g) of rule XXI of the Rules of the House of Representatives. Unfunded Mandates Reform Act Statement According to the Congressional Budget Office, H.R. 7776 contains no unfunded mandates as defined by the Unfunded Mandates Reform Act. Existing Programs Directed Rule Making. This bill does not contain any directed rule makings. Duplication of Existing Programs. This bill does not establish or reauthorize a program of the federal government known to be duplicative of another program. Such program was not included in any report from the Government Accountability Office to Congress pursuant to section 21 of Public Law 111-139 or identified in the most recent Catalog of Federal Domestic Assistance published pursuant to the Federal Program Information Act (Public Law 95-220, as amended by Public Law 98-169) as relating to other programs. Applicability to Legislative Branch The Committee finds that the legislation does not relate to the terms and conditions of employment or access to public services or accommodations within the meaning of section 102(b)(3) of the Congressional Accountability Act. Preemption of State, Local or Tribal Law Any preemptive effect of this bill over state, local, or tribal law is intended to be consistent with the bill's purposes and text and the Supremacy Clause of Article VI of the U.S. Constitution. Changes in Existing Law Made by the Bill, as Reported In compliance with clause 3(e) of rule XIII of the Rules of the House of Representatives, changes in existing law made by the bill, as reported, are shown as follows (new matter is printed in italics, and existing law in which no change is proposed is shown in roman): SECTION 2 OF THE ACT OF DECEMBER 21, 1928 AN ACT to provide for the construction of works for the protection and development of the Colorado River Basin, for the approval of the Colorado River compact, and for other purposes. Sec. 2. (a) There is hereby established a special fund, to be known as the ``Colorado River Dam fund'' (hereinafter referred to as the `` fund''), and to be available, as hereinafter provided, only for carrying out the provisions of this Act. All revenues received in carrying out the provisions of this Act shall be paid into and expenditures shall be made out of the fund, under the direction of the Secretary of the Interior. (b) The Secretary of the Treasury is authorized to advance to the fund, from time to time and within the appropriations therefor, such amounts as the secretary of the interior deems necessary for carrying out the provisions of this Act. Of this amount the sum of $25,000,000 shall be allocated to flood control and shall be repaid to the united states out of 62\1/2\ per centum of revenues, if any, in excess of the amount necessary to meet periodical payments during the period of amortization, as provided in section 4 of this Act. If said sum of $25,000,000 is not repaid in full during the period of amortization, then 62\1/2\ per centum of all net revenues shall be applied to payment of the remainder. Interest at the rate of 4 per centum per annum accruing during the year upon the amounts so advanced and remaining unpaid shall be paid annually out of the fund, except as herein otherwise provided. (c) Moneys in the fund advanced under subdivision (b) shall be available only for expenditures for construction and the payment of interest, during construction, upon the amounts so advanced. No expenditures out of the fund shall be made for operation and maintenance except from appropriations therefor. (d) The Secretary of the Treasury shall charge the fund as of June 30 in each year with such amount as may be necessary for the payment of interest on advances made under subdivision (b) at the rate of 4 per centum per annum accrued during the year upon the amounts so advanced and remaining unpaid, except that if the fund is insufficient to meet the payment of interest the Secretary of the Treasury may, in his discretion, defer any part of such payment, and the amount so deferred shall bear interest at the rate of 4 per centum per annum until paid. (e) The Secretary of the Interior shall certify to the Secretary of the Treasury, at the close of each fiscal year, the amount of money in the fund in excess of the amount necessary for construction, operation, and maintenance, and payment of interest. Upon receipt of each such certificate the Secretary of the Treasury is authorized and directed to charge the fund with the amount so certified as repayment of the advances made under subdivision (b), which amount shall be covered into the Treasury to the credit of miscellaneous receipts. (f) The Secretary of the Interior is authorized to expend moneys in the fund, including moneys in account XXXR5656P1, that were and hereafter are recovered on a non-reimbursable basis, for any authorized activity, including operations, maintenance, investigation and cleanup actions, and capital improvements, within the Boulder Canyon Project at Hoover Dam or on land used for the construction and operation of the Hoover Dam, subject to the review and approval of the Boulder Canyon Project contractors as identified in the Hoover Power Allocation Act of 2011 (Public Law 112-72). [all]