H. Rept. 119-193

HYDROPOWER LICENSING TRANSPARENCY ACT

2025-07-10

Committees

Associated legislation

Text

Purpose and Summary

H.R. 3657, the ``Hydropower Licensing Transparency Act'', was introduced by Representative Schrier (D-WA) on May 29, 2025. The legislation would require the Federal Energy Regulatory Commission to report periodically to Congress on the status of licensing and relicensing applications for hydropower dams.

Background and Need for Legislation

Hydropower is one of the world's oldest energy sources and continues to play an important role for our nation's energy supply, providing power to approximately 30 million homes and businesses across the United States.\1\ Additionally, hydropower accounts for 40 percent of the nation's black start capacity for grid recovery following a major disruption.\2\ --------------------------------------------------------------------------- \1\``The Path to Clean Energy.'' National Hydropower Association, June 6, 2025. https://www.hydro.org/. \2\Coleman, LeRoy, ``Black Start: Hydropower Is the Guardian of the Grid.'' National Hydropower Association, June 1, 2021 (last accessed July 10, 2025), https://www.hydro.org/ powerhouse/article/black-start-hydropower-is-the-guardian-of-the-grid/. --------------------------------------------------------------------------- Hydropower regulation, the oldest area of the Federal Energy Regulatory Commission's (FERC) jurisdiction, first began with the Federal Power Commission's regulation of non-federal hydroelectric generation in 1920. In 1977, Congress passed the Department of Energy (DOE) Organization Act, creating the FERC within the newly formed DOE to take over duties previously administered by the Federal Power Commission.\3\ This included the regulation of the construction and operation of non-federal hydropower projects. --------------------------------------------------------------------------- \3\42 U.S.C. 7101. --------------------------------------------------------------------------- Pursuant to Part I of the Federal Power Act,\4\ the FERC regulates over 1,600 non-federal hydropower projects at over 2,500 dams, representing about 57 gigawatts of hydropower capacity. In total, federal and non-federal hydropower capacity makes up approximately six percent of overall U.S. electric generation.\5\ --------------------------------------------------------------------------- \4\16 U.S.C. 791 et seq. \5\``U.S. Energy Information Administration, Independent Statistics and Analysis: Where Hydropower Is Generated,'' U.S. Energy Information Administration (EIA), last accessed July 8, 2025, https://www.eia.gov/ energyexplained/hydropower/where-hydropower-is-generated.php. --------------------------------------------------------------------------- The permitting of hydropower projects is essential to ensure projects comply with statutory requirements and address stakeholder priorities. Non-federal hydropower projects must be licensed by the FERC if they are located on a navigable waterway, occupy federal land, use surplus water or water power from a federal dam, or are located on non-navigable waters which Congress has jurisdiction under the Commerce Clause, involve post-1955 construction, and affect interstate or foreign commerce.\6\ --------------------------------------------------------------------------- \6\Polardino, Jennifer, ``Jurisdiction Determination,'' Federal Energy Regulatory Commission, July 8, 2020 (last accessed July 10, 2025), https://www.ferc.gov/industries-data/ hydropower/administration-and-compliance/jurisdiction-determination. --------------------------------------------------------------------------- For non-federal hydropower projects, the FERC serves as the lead agency for documentation required under the National Environmental Policy Act (NEPA). Over time, the regulatory structure has changed to include multiple permits and requirements by several bodies including, the FERC, the U.S. Army Corps of Engineers, land management agencies, resource agencies, and tribes.\7\ This regulatory morass has resulted in lengthy, complex, and opaque timelines. --------------------------------------------------------------------------- \7\Levine, Aaron, Brenda Pracheil, Taylor Curtis, Ligia Smith, Jesse Cruce, Matt Aldrovandi, Christa Breslford, et al. National Renewable Energy Laboratory, ``An examination of the hydropower licensing and Federal Authorization Process'', October 1, 2021, https:/ /doi.org/10.2172/1827895. --------------------------------------------------------------------------- FERC-issued hydropower licenses may be valid for a period of 30 to 50 years.\8\ However, 40 years is now the default license length for most projects under the Commission's jurisdiction.\9\ The average permitting length of an original license process spans from 5 to 7 years, and the average relicensing process takes 7 to 10 years.\10\ The average age of a hydropower facility in the United States is approximately 60 years old.\11\ Therefore, hundreds of projects, representing at least 16 gigawatts of power, will be required to go through the FERC's relicensing process in the next ten years. In fact, the FERC itself estimates that by 2034, over 400 projects, accounting for approximately 40 percent of the Commission's currently licensed projects and approximately 15 percent of currently licensed capacity, will begin the pre-filing stages of the relicensing process.\12\ Additionally, as energy demand is projected to grow substantially over the next decade, new projects will go through the original licensing process to bring new power generating dams online. --------------------------------------------------------------------------- \8\Id. \9\Id. \10\Id. \11\Id. \12\``Assuring Abundant, Reliable American Energy to Power Innovation'': Hearing Before the Subcommittee on Energy of the H. Comm. On Energy and Commerce 119th Cong., April 30, 2025, (statement of Terry Turpin, Director of the Office of Energy Projects, Federal Energy Regulatory Commission). --------------------------------------------------------------------------- H.R. 3657, introduced by Representative Kim Schrier (D-WA) and Representative Russ Fulcher (R-ID), would require an annual report from the FERC to Congress detailing the status of projects that have filed a notice of intent to go through the licensing and relicensing process. This legislation would better inform Congress regarding the status of applications, while highlighting obstacles to the efficient permitting and ultimate deployment of non-federal hydropower projects.

Committee Action

On April 30, 2025, the Subcommittee on Energy held a legislative hearing on 14 bills, including H.R. 3657. The Subcommittee received testimony from: Mike Goff, Acting Undersecretary of Energy, U.S. Department of Energy; David L. Morenoff, Acting General Counsel, Federal Energy Regulatory Commission; Terry Turpin, Director, Office of Energy Projects, Federal Energy Regulatory Commission; Jim Matheson, Chief Executive Officer, National Rural Electric Cooperative Association; Amy Andryszak, President & Chief Executive Officer, Interstate Natural Gas Association of America; Todd A. Snitchler, President & Chief Executive Officer, Electric Power Supply Association; and Kim Smaczniak, Partner, Roselle LLP. On June 5, 2025, the Subcommittee on Energy met in open markup session and forwarded H.R. 3657, without amendment, to the full Committee by a voice vote. On June 25, 2025, the full Committee on Energy and Commerce met in open markup session and ordered H.R. 3657, as amended, favorably reported to the House by a record vote of 47 yeas and 0 nays.

Committee Votes

Clause 3(b) of rule XIII requires the Committee to list the record votes on the motion to report legislation and amendments thereto. The following reflects the record votes taken during the Committee consideration: Oversight Findings and Recommendations Pursuant to clause 2(b)(1) of rule X and clause 3(c)(1) of rule XIII, the Committee held hearings and made findings that are reflected in this report. New Budget Authority, Entitlement Authority, and Tax Expenditures Pursuant to clause 3(c)(2) of rule XIII, the Committee finds that H.R. 3657 would result in no new or increased budget authority, entitlement authority, or tax expenditures or revenues.

Congressional Budget Office Estimate

Pursuant to clause 3(c)(3) of rule XIII, at the time this report was filed, the cost estimate prepared by the Director of the Congressional Budget Office pursuant to section 402 of the Congressional Budget Act of 1974 was not available. Federal Mandates Statement The Committee adopts as its own the estimate of Federal mandates prepared by the Director of the Congressional Budget Office pursuant to section 423 of the Unfunded Mandates Reform Act. Statement of General Performance Goals and Objectives Pursuant to clause 3(c)(4) of rule XIII, the general performance goal or objective of this legislation is to require FERC to report periodically to Congress on the status of licensing and relicensing applications for hydropower dams, in order to assess the availability of baseload generation and prevent premature retirements of baseload hydropower generation. Duplication of Federal Programs Pursuant to clause 3(c)(5) of rule XIII, no provision of H.R. 3657 is known to be duplicative of another Federal program, including any program that was included in a report to Congress pursuant to section 21 of Public Law 111-139 or the most recent Catalog of Federal Domestic Assistance. Related Committee and Subcommittee Hearings Pursuant to clause 3(c)(6) of rule XIII, the following related hearings were used to develop or consider H.R. 3657: On February 5, 2025, the Subcommittee on Energy held a hearing on H.R. 3657. The title of the hearing was ``Powering America's Future: Unleashing American Energy.'' The Subcommittee received testimony from: Amanda Eversole, Executive Vice President and Chief Advocacy Officer, American Petroleum Institute; Brigham McCown, Senior Fellow and Director, Initiative on American Energy Security, The Hudson Institute; Gary Arnold, Business Manager, Denver Pipefitters Local 208; and Tyler O'Connor, Partner, Crowell & Moring LLP. On March 5, 2025, the Subcommittee on Energy held a hearing on ``Scaling for Growth: Meeting the Demand for Reliable, Affordable Electricity.'' The Subcommittee received testimony from: Todd Brickhouse, CEO and General Manager, Basin Electric Power Cooperative; Asim Haque, Senior Vice President for Governmental and Member Services, PJM; Noel W. Black, Senior VP of Regulatory Affairs, Southern Company; and Tyler H. Norris, James B. Duke Fellow, Duke University. On March 25, 2025, the Subcommittee on Energy held a hearing on H.R. 3657. The title of the hearing was ``Keeping the Lights On: Examining the State of Regional Grid Reliability.'' The Subcommittee received testimony from: Gordon van Welie, President and Chief Executive Officer, ISO New England; Richard J. Dewey, President and Chief Executive Officer, New York Independent System Operator; Manu Asthana, President and Chief Executive Officer, PJM Interconnection LLC; Jennifer Curran, Senior Vice President for Planning and Operations, Midcontinent ISO; Lanny Nickell, Chief Operating Officer, Southwest Power Pool; Elliot Mainzer, President and Chief Executive Officer, California Independent System Operator; and Pablo Vegas, President and Chief Executive Officer, Electric Reliability Council of Texas, Inc. On April 9, 2025, the Committee on Energy and Commerce held a full committee hearing on H.R. 3657. The title of the hearing was ``The Energy Needs for Advancing American Technological Leadership.'' The Committee received testimony from: Eric Schmidt, Chair, Special Competitive Studies Project; Manish Bhatia, Executive Vice President of Global Operations, Micron Technology; Alexander Wang, Founder and Chief Executive Officer, Scale AI; and David Turk, Distinguished Visiting Fellow, Center on Global Energy Policy, Columbia University. On April 30, 2025, the Subcommittee on Energy held a legislative hearing on H.R. 3657. The title of the hearing was ``Assuring Abundant, Reliable American Energy to Power Innovation.'' The Subcommittee received testimony from: Mike Goff, Acting Undersecretary of Energy, U.S. Department of Energy; David L. Morenoff, Acting General Counsel, Federal Energy Regulatory Commission; Terry Turpin, Director, Office of Energy Projects, Federal Energy Regulatory Commission; Jim Matheson, Chief Executive Officer, National Rural Electric Cooperative Association; Amy Andryszak, President and Chief Executive Officer, Interstate Natural Gas Association of America; Todd A. Snitchler, President and Chief Executive Officer, Electric Power Supply Association; and Kim Smaczniak, Partner, Roselle LLP. Committee Cost Estimate Pursuant to clause 3(d)(1) of rule XIII, the Committee adopts as its own the cost estimate prepared by the Director of the Congressional Budget Office pursuant to section 402 of the Congressional Budget Act of 1974. At the time this report was filed, the estimate was not available. Earmark, Limited Tax Benefits, and Limited Tariff Benefits Pursuant to clause 9(e), 9(f), and 9(g) of rule XXI, the Committee finds that H.R. 3657 contains no earmarks, limited tax benefits, or limited tariff benefits. Advisory Committee Statement No advisory committees within the meaning of section 5(b) of the Federal Advisory Committee Act were created by this legislation. Applicability to Legislative Branch The Committee finds that the legislation does not relate to the terms and conditions of employment or access to public services or accommodations within the meaning of section 102(b)(3) of the Congressional Accountability Act. Section-by-Section Analysis of the Legislation Section 1. Short title This section provides the short title of ``Hydropower Relicensing Transparency Act.'' Section 2. Annual licensing status report This section amends the Federal Power Act by requiring an annual report from the Commission to Congress on the status of certain hydropower licenses under sections 15(b)(1) and 4(e) of the Federal Power Act. The report shall include: the date a notice of intent was provided to the Commission; any assigned docket number; whether an application has been filed; information regarding the status of such application; any upcoming proceeding related to the new license; any ongoing or completed actions required of the Commissions, other agencies, or the licensee. The information in the report is required to be disaggregated based on license type. Changes in Existing Law Made by the Bill, as Reported In compliance with clause 3(e) of rule XIII of the Rules of the House of Representatives, changes in existing law made by the bill, as reported, are shown as follows (new matter is printed in italics and existing law in which no change is proposed is shown in roman): FEDERAL POWER ACT PART I * * * * * * * SEC. 37. ANNUAL LICENSING STATUS REPORT. (a) In General.--Not later than 180 days after the date of enactment of this section, and annually thereafter, the Commission shall submit to Congress a report on the status of-- (1) the licensing process for each new license, and for each subsequent license for which sections 14 and 15 have been waived, for which the existing licensee has notified the Commission under section 15(b)(1) at least 3 years prior to submission of the report that such existing licensee intends to file an application for such new license or subsequent license, but such new license or subsequent license has not yet been issued under section 15; and (2) the licensing process for each original license under section 4(e) for which a citizen, association, corporation, State, Indian Tribe, or municipality has notified the Commission, pursuant to applicable regulations, at least 3 years prior to submission of the report that such citizen, association, corporation, State, Indian Tribe, or municipality intends to file an application for such original license, but such original license has not yet been issued under section 4(e). (b) Inclusions.--Each report submitted under subsection (a) shall include, with respect to the licensing process for each new license and subsequent license described in such subsection and the licensing process for each original license described in such subsection-- (1) the date the notice of intent described in such subsection was provided to the Commission; (2) any docket number assigned with respect to such licensing process; (3) whether any application for such new license, such subsequent license, or such original license has been filed; (4) information regarding the status of any such application, including the date the Commission anticipates it will issue such original license, such subsequent license, or such new license; (5) the date of any upcoming proceeding or other meeting related to such original license, such subsequent license, or such new license; and (6) a description of any ongoing or completed actions required of the existing licensee, citizen, association, corporation, State, Indian Tribe, municipality, the Commission, the fish and wildlife agencies referred to in section 15(b), and any other agencies. (c) Disaggregation of Information by License Type.--The information included in each report submitted under subsection (a) shall be disaggregated by whether the information relates to a new license, or a subsequent license, issued under section 15 or an original license issued under section 4(e). * * * * * * *