Background and Need for Legislation
Deploying broadband technologies and closing the digital
divide for rural and Tribal communities means installing a
significant portion of communications infrastructure on federal
land.\1\ The Department of the Interior (DOI), through the
Bureau of Land Management (BLM), and the U.S. Forest Service
(USFS), process the majority of applications and communications
use authorizations to install communications facilities on
federal property.\2\ Communications use authorizations are
requests for easements, rights-of-way, leases, or other
authorizations ``to locate or modify a transmitting device,
support structure, or other communications facility'' on public
lands.\3\
---------------------------------------------------------------------------
\1\``Special Uses--Communications Uses,'' U.S. Department of
Agriculture, U.S. Forest Service, https://www.fs.usda.gov/managing-
land/special-uses/communications-uses. Streamlining Federal Siting
Working Group Final Report, FCC Broadband Deployment Advisory
Committee, January 24, 2018, https://www.fcc.gov/sites/default/files/
bdac-federalsiting-01232018.pdf.
\2\``Broadband Deployment: Agencies Should Take Steps to Better
Meet Deadline for Processing Permits,'' U.S. Government Accountability
Office, April 10, 2024, https://www.gao.gov/products/gao-24-106157#.
\3\Id.
---------------------------------------------------------------------------
Although BLM and USFS face a statutory requirement to grant
or deny these applications within 270 days, this deadline is
often missed.\4\ The U.S. Government Accountability Office
(GAO) recently reported roughly half of the communications use
applications submitted to BLM and USFS from fiscal years 2018
to 2022 either exceeded the 270-day deadline or lacked data
sufficient to reveal whether the deadline had been met.\5\ As a
result, broadband developers report that fiber deployment in
rural areas takes an average of five to ten years to
complete.\6\ These regulatory hurdles raise the costs of
broadband development plans and bring delay and uncertainty to
them, dissuading many would-be providers from even applying in
the first place.\7\ Without lowering these obstacles, the
``digital divide'' and its detrimental consequences will
persist.
---------------------------------------------------------------------------
\4\Id.
\5\Id.
\6\Linda Hardesty, ``Whoa--the fiber permitting process could crush
digital divide dreams,'' Fierce Network, December 9, 2021, https://
www.fierce-network.com/broadband/whoa-fiber-
permitting-process-could-crush-digital-divide-dreams.
\7\Id.
---------------------------------------------------------------------------
H.R. 1681 is one of several Republican-led solutions that
would expedite broadband deployment on federal lands.\8\ The
legislation would require the Assistant Secretary of Commerce
for Communications and Information (Assistant Secretary), in
their capacity as head of the National Telecommunications and
Information Administration, to create an interagency ``strike
force'' that would assist BLM and USFS in reviewing requests
for communications use authorizations. Crucially, the bill
would require the two agencies, at each organizational unit, to
prioritize their review of such requests. The five-member
strike force would consist of the Assistant Secretary, the
heads of BLM and USFS, and a designee of each the Secretary of
Agriculture and the Secretary of the Interior, respectively.
Once established, the strike force would periodically convene
to ensure BLM and USFS are prioritizing the review of requests
for communications use authorizations, establish ``objective
and reasonable'' goals for those reviews, and hold the agencies
accountable for meeting such goals.
---------------------------------------------------------------------------
\8\``E&C Advances Seven Bills to Close the Digital Divide and
Improve American Leadership in Wireless Communications,'' U.S. House
Committee on Energy and Commerce, May 24, 2023, https://
energycommerce.house.gov/posts/e-and-c-advances-seven-bills-to-close-
the-digital-divide-and-improve-american-leadership-in-wireless-
communications.
---------------------------------------------------------------------------
Committee Action
H.R. 1681 was introduced on February 27, 2025, by
Representative Gabe Evans (R-CO). The bill was referred to the
Committee on Natural Resources. The bill was also referred to
the Committee on Energy and Commerce and the Committee on
Agriculture. On April 9, 2025, the Committee on Natural
Resources met to consider the bill. The bill was then ordered
favorably reported to the House of Representatives by unanimous
consent.
Hearings
For the purposes of clause 3(c)(6) of House rule XIII, the
following hearing was used to develop or consider this measure:
hearing in the 118th Congress by the Subcommittee on Federal
Lands held on July 24, 2024.
Section-by-Section Analysis
Section 1. Short title
Names the legislation the ``Expediting Federal Broadband
Deployment Reviews Act.''
Section 2. Establishment of interagency strike force
Section 2 directs the Assistant Secretary of Commerce for
Communications and Information to establish, not later than 180
days after the bill's enactment, an interagency strike force to
ensure BLM and USFS prioritize reviewing requests for
communications use authorizations. This section specifies the
strike force shall consist of the Assistant Secretary, the
heads of the BLM and USFS, and separate designees of the
Secretary of Agriculture and the Secretary of the Interior,
respectively. Section 2 tasks the strike force with making
periodic calls to ensure BLM and USFS prioritize reviewing
requests for communications use authorizations, establishing
objective and reasonable goals for those reviews, and holding
the agencies accountable for meeting such goals. Finally,
Section 2 requires the Assistant Secretary to submit to
Congress, not later than 270 days after the bill's enactment, a
report on the effectiveness of the strike force in ensuring BLM
and USFS prioritize the review of requests for communications
use authorizations.
COMMITTEE OVERSIGHT FINDINGS AND RECOMMENDATIONS
Regarding clause 2(b)(1) of rule X and clause 3(c)(1) of
rule XIII of the Rules of the House of Representatives, the
Committee on Natural Resources' oversight findings and
recommendations are reflected in the body of this report.
COMPLIANCE WITH HOUSE RULE XIII AND
CONGRESSIONAL BUDGET ACT
1. Cost of Legislation and the Congressional Budget Act.
With respect to the requirements of clause 3(c)(2) and (3) of
rule XIII of the Rules of the House of Representatives and
sections 308(a) and 402 of the Congressional Budget Act of
1974, the Committee has received the following estimate for the
bill from the Director of the Congressional Budget Office:
H.R. 1681 would require the National Telecommunications and
Information Administration (NTIA) to establish an interagency
strike force to help prioritize the review of communications
use authorizations by the Bureau of Land Management (BLM) and
the Forest Service. Communications use authorizations are
requests for the placement and operation of a communications
facility on federal land. That group would establish goals for
reviewing communications use authorizations and monitor each
agency to ensure goals are met. The NTIA also would be required
to report to the Congress on the effectiveness of the strike
force.
Using information from the affected agencies, CBO estimates
that it would cost $9 million over the 2025-2030 period to
establish and administer the interagency group, as well as
write the report; any related spending would be subject to the
availability of appropriated funds. That amount would support
12 employees each year across the three affected agencies at an
average cost of $150,000 per employee in 2025, with increases
in later years to account for anticipated inflation.
The CBO staff contact for this estimate is Margot Berman.
The estimate was reviewed by H. Samuel Papenfuss, Deputy
Director of Budget Analysis.
Phillip L. Swagel,
Director, Congressional Budget Office.
2. General Performance Goals and Objectives. As required by
clause 3(c)(4) of rule XIII, the general performance goal or
objective of this bill is to require the Assistant Secretary of
Commerce for Communications and Information to establish an
interagency strike force to ensure that certain Federal land
management agencies, including the organizational units of such
agencies, prioritize the review of requests for communications
use authorizations, and for other purposes.
EARMARK STATEMENT
This bill does not contain any Congressional earmarks,
limited tax benefits, or limited tariff benefits as defined
under clause 9(e), 9(f), and 9(g) of rule XXI of the Rules of
the House of Representatives.
UNFUNDED MANDATES REFORM ACT STATEMENT
According to the Congressional Budget Office, H.R. 1681
contains no unfunded mandates as defined by the Unfunded
Mandates Reform Act.
EXISTING PROGRAMS
Directed Rule Making. This bill does not contain any
directed rule makings.
Duplication of Existing Programs. This bill does not
establish or reauthorize a program of the federal government
known to be duplicative of another program. Such program was
not included in any report from the Government Accountability
Office to Congress pursuant to section 21 of Public Law 111-139
or identified in the most recent Catalog of Federal Domestic
Assistance published pursuant to the Federal Program
Information Act (Public Law 95-220, as amended by Public Law
98-169) as relating to other programs.
APPLICABILITY TO LEGISLATIVE BRANCH
The Committee finds that the legislation does not relate to
the terms and conditions of employment or access to public
services or accommodations within the meaning of section
102(b)(3) of the Congressional Accountability Act.
PREEMPTION OF STATE, LOCAL OR TRIBAL LAW
Any preemptive effect of this bill over state, local, or
tribal law is intended to be consistent with the bill's
purposes and text and the Supremacy Clause of Article VI of the
U.S. Constitution.
CHANGES IN EXISTING LAW
As ordered reported by the Committee on Natural Resources,
H.R. 1681 would make no changes in existing law.
[all]