Background
VA manages significant acquisition programs to procure
services, supplies, technology, and systems critical to
delivering timely and high-quality care, benefits, and services
to eligible veterans and other beneficiaries. The Committee
bill would redefine ``major acquisition program'' to focus
oversight on high-cost initiatives (defined as those with life-
cycle costs exceeding $1,000,000,000 or annual costs exceeding
$200,000,000), addressing concerns about cost overruns and
delays in programs like the Electronic Health Record
Modernization (EHRM).
Committee Bill
The Committee bill would establish the Office of
Acquisition under an Assistant Secretary, with Program
Executive Officers and Deputy Assistant Secretaries to
centralize oversight. It would further add provisions for
independent analysis and requirements development to enhance
efficiency and accountability, complementing VA's ongoing
acquisition reforms.
Section 3: Department of Veterans Affairs Major Acquisition Program
Managers
Major VA programs have faced delays and failures due to
weak early oversight and leadership. GAO reviewed VA's major
acquisition programs and found that nearly all (approximately
90 percent) did not use the department's official Acquisition
Program Management Framework (in place since 2017), which is
designed to enforce early oversight, including setting
baselines for costs, schedules, and performance. Instead, these
programs relied on ad-hoc, program-specific approaches that
``vary widely in robustness.''\1\ This section would require VA
to appoint level-three certified project managers for all major
programs under the Assistant Secretary for Acquisition. These
managers will set firm baselines for costs and schedules,
ensure compliance, and manage risks, helping to avoid past
problems.
---------------------------------------------------------------------------
\1\U.S. Government Accountability Office, GAO-22-105195, VA
Acquisition Management: Action Needed to Ensure Success of New
Oversight Framework (August 2022).
---------------------------------------------------------------------------
Background
Section 4 of the Committee bill would require unification
within one year--with a 90-day congressional plan--to eliminate
silos, streamline decision-making, and have a consolidated
model.
VA's three main administrations--the Veterans Health
Administration, the Veterans Benefits Administration, and the
National Cemetery Administration--have separate acquisition,
procurement, and logistics operations, leading to repeated
contracts, mismatched systems, and yearly waste. To address
that, the Committee bill orders full consolidation under the
Assistant Secretary for Acquisition within one year, including
a plan and briefing to Congress within 90 days. This will
reduce duplication, improve decision-making, and create a
single system for better operations, oversight, and cost
control.
Committee Bill
The Committee bill would mandate organizational
consolidation of acquisition, procurement, and logistics
activities under the Assistant Secretary for Acquisition within
one year, with a plan and briefing to Congress within 90 days.
Section 5: Independent Verification and Validation (IV&V) of Major
Acquisition Programs of Department of Veterans Affairs
VA program launches have missed early problems with
usability, causing safety issues and restarts, due to reliance
on contractor self-reports. The Committee bill would require VA
to hire IV&V contractors for major programs within 120 days. It
would further stipulate that contractors have at least three
health-sector contracts, good past performance, and no
conflicts. Costs would be shared across VA units for neutral
reviews of technical aspects like usability and integration.
Background
To harmonize the improvements needed with 38 USC 8171,
8172, 8173 the definitions for ``major information technology
project'' from 8171 and ``major acquisition program'' were
removed.
Committee Bill
The Committee bill makes conforming amendments, striking
section 8171(5) and (6) and section 8172 of title 38. Section
10 would strike paragraphs (5) and (6) in 8171 but kept the
definitions still needed for 8173, 8174, 8175. All of 8172 was
stricken but moved the project manager qualifications into this
bill.
Congressional Budget Office Cost Estimate
In accordance with paragraph 11(a) of rule XXVI of the
Standing Rules of the Senate and section 402 of the
Congressional Budget Act of 1974, the Committee provides the
following cost estimate, prepared by the Congressional Budget
Office:
[GRAPHIC(S) NOT AVAILABLE IN TIFF FORMAT]
S. 1591 would make changes to acquisition and contracting
processes used by the Department of Veterans Affairs (VA).
Specifically, the bill would:
Establish a new office to evaluate the cost
of major acquisition programs;
Require several studies and reports on how
VA acquires products and services;
Reorganize VA's current acquisition
workforce; and
Establish new rules for vendors that test VA
programs, such as those dealing with information
technology.
In total, implementing S. 1591 would cost $24 million over
the 2026-2030 period, CBO estimates. Such spending would be
subject to the availability of appropriated funds.
The costs of the legislation, detailed in Table 1, fall
within budget function 700 (veterans benefits and services).
Table 1.--Estimated Increases in Spending Subject to Appropriation Under S. 1591
----------------------------------------------------------------------------------------------------------------
By fiscal year, millions of dollars--
-------------------------------------------------------
2026 2027 2028 2029 2030 2026-2030
----------------------------------------------------------------------------------------------------------------
Cost Assessment Office:
Estimated Authorization............................. 2 5 5 5 5 22
Estimated Outlays................................... 2 5 5 5 5 22
Studies and Reports:
Estimated Authorization............................. 1 1 * * * 2
Estimated Outlays................................... * 1 1 * * 2
Total Changes:
Estimated Authorization............................. 2 3 3 5 5 24
Estimated Outlays................................... 1 3 4 5 5 24
----------------------------------------------------------------------------------------------------------------
* = between zero and $500,000.
Cost assessment office. S. 1591 would establish a new
Director of Cost Assessment and Program Evaluation. The
director would lead a team responsible for estimating the cost
of new major acquisition programs and evaluating the
effectiveness of existing ones. Using information on similar
offices at other agencies, CBO estimates that VA would
eventually require 25 full-time equivalent employees to perform
the office's duties. Those employees would receive an average
annual compensation of about $200,000. As a result,
establishing the new office would cost $22 million over the
2026-2030 period, CBO estimates.
Studies and reports. The bill would require VA to contract
with the Department of Defense's Acquisition Research Center to
conduct a study of VA's acquisition processes. Using
information from VA, CBO estimates that satisfying that
requirement would cost $1 million. The bill also would require
four other studies and reports. Using information on the cost
of similar efforts, CBO estimates that satisfying those
requirements would cost $1 million. In total, the bill's study
and reporting requirements would cost $2 million over the 2026-
2030 period, CBO estimates.
Acquisition reorganization. S. 1591 would reorganize VA's
existing acquisition workforce and processes under a new
Assistant Secretary for Acquisition. VA currently employs
people who would fill positions under the reorganization and
meet the bill's requirements for acquisition processes (such as
appointing managers for major programs). Thus, CBO estimates
that any associated costs would be less than $500,000.
Program testing. The bill would direct VA to contract for
independent verification and validation (IV&V) services,
including for testing information technology systems to ensure
they function properly and meet VA's requirements. Any such
contract must ensure that the vendor has experience performing
IV&V services at other agencies and has no conflict of interest
that would prevent independent testing. VA currently contracts
for IV&V services for major acquisition programs. CBO estimates
that the cost of modifying those contracts to meet the bill's
requirements would be less than $500,000.
The CBO staff contact for this estimate is Logan Smith. The
estimate was reviewed by Christina Hawley Anthony, Deputy
Director of Budget Analysis.
Phillip L. Swagel,
Director, Congressional Budget Office.
Regulatory Impact Statement
In compliance with paragraph 11(b) of rule XXVI of the
Standing Rules of the Senate, the Committee on Veterans'
Affairs has made an evaluation of the regulatory impact that
would be incurred in carrying out the Committee bill. The
Committee finds that the Committee bill would not entail any
regulation of individuals or businesses, result in any impact
on the personal privacy of any individuals, and that the
paperwork resulting from enactment would be minimal.
Tabulation of Votes Cast in Committee
In compliance with paragraph 7(b) of rule XXVI of the
Standing Rules of the Senate, the following is a tabulation of
votes cast by members of the Committee on Veterans' Affairs at
its July 30, 2025, meeting.
During this meeting, Chairman Moran called up 23 bills,
including S. 1591, to be considered en bloc. The bills were
reported favorably by voice vote en bloc.
Agency Report
On May 21, 2025, Thomas O'Toole, M.D., Acting Assistant
Under Secretary for Health for Clinical Services, Veterans
Health Administration, U.S. Department of Veterans Affairs,
appeared before the Committee and submitted testimony on S.
1591. An excerpt from that testimony is reprinted below:
statement of thomas o'toole, m.d., acting assistant under secretary for
health for clinical services, veterans health administration (vha),
department of veterans affairs before the senate committee on veterans'
affairs
acquisition reform and cost assessment act of 2025 (s. 1591)
This bill includes nine total sections, with section 1
providing a short title and table of contents.
Section 2(a) would add new subchapter VII, ``Acquisition
Organization, Cost Assessment, and Program Evaluation,'' to
chapter 81 of title 38, U.S.C. The new subchapter would include
section 8181, ``Definitions,'' which would add definitions for
the terms ``major acquisition program'' and ``non-major
acquisition program'' that would apply throughout the
subchapter. Section 2(b) would amend 38 U.S.C. Sec. 308 to
increase the number of Assistant Secretaries from seven to
eight, including the addition of an Assistant Secretary for
``Acquisition and innovation''.
Section 2(c) would add a new section 8182, ``Acquisition
organization,'' to title 38, U.S.C., which would direct the
Secretary to designate an Assistant Secretary for Acquisition
and Innovation, who would also be the Chief Acquisition Officer
(CAO). The Assistant Secretary would be the head of the Office
of Acquisition and Innovation, and major program offices would
align under the Office. The budget for the Office would be
established in VA's budget justification materials submitted to
Congress. The Secretary would appoint three Deputy Assistant
Secretaries (DAS), who would report to the Assistant Secretary
for Acquisition and Innovation--a DAS for Logistics, a DAS for
Innovation, and a DAS for Procurement. The DAS for Logistics
would be responsible for the administration of logistics and
supply chain operations. The DAS for Innovation would be
responsible for all research development, testing, and
innovation development organizations, including the VHA
Innovation Ecosystem. The DAS for Procurement would be
responsible for all VA procurement and contracting
organizations.
VA supports the intent of this section, subject to amendments and
the availability of appropriations
VA supports the intent of this section, subject to
amendments, because it enhances the focus on and coordination
of acquisition and innovation activities, ensuring they align
with Presidential priorities to streamline processes, improve
efficiency, and foster a more innovative approach to acquiring
and developing capabilities. This new role and organization
better support and reflect the CAO's responsibilities and the
increasing complexity of VA's acquisition needs. The CAO serves
as the primary advisor to the Secretary for all major
acquisitions, manages 17,000 acquisition professionals, and is
responsible for providing oversight of approximately $100
billion in VA's major acquisition programs. VA believes
additional amendments are needed to give effect to the intent
of this section, particularly with revising the dollar value
for major/non-major acquisition programs to align with the
definition of ``Major Information Technology Project'' in 38
U.S.C. Sec. 8171(5) (as added by the Department of Veterans
Affairs Information Technology Reform Act of 2022 (section 403
of the Joseph Maxwell Cleland and Robert Joseph Dole Memorial
Veterans Benefits and Health Care Improvement Act of 2022; P.L.
117-328, Div. U)). VA also recommends adding a DAS for
Acquisition, Program Management, and Performance, who would
report to the Assistant Secretary for Acquisition and
Innovation. This additional DAS role would focus on the
critical aspects of VA's ``Big A'' acquisitions. This role
would transcend mere procurement, placing a strong emphasis on
lifecycle management that is intricately structured around
vital elements: requirements planning, programming and
budgeting, policy innovation, performance standards,
governance, and enhancing the capabilities of the acquisition
workforce. This comprehensive approach would ensure that our
major acquisitions are both effective and forward-thinking,
paving the way for successful outcomes.
VA does not have a cost estimate for this section.
Section 3 would add a new section 8183, ``Major acquisition
program managers.'' The new section would direct the Deputy
Secretary to appoint a manager to administer a major
acquisition program not later than 30 days after the Secretary
approves commencement of the program. Each appointed manager
would report to the Assistant Secretary for Acquisition and
Innovation and be responsible for developing a ``program
baseline.'' The program baseline would include a description of
each acquisition phase; requirements for advancing the program;
and estimates for cost, schedule, and performance for the
lifecycle of the program. The manager would be responsible for
ensuring that the program is in compliance with such
requirements, securing funding, adopting standardized
processes, and ensuring personnel responsible for estimating
the budget for the program are able to raise concerns prior to
the establishment of the program baseline. The manager would be
responsible for ensuring that: the program complies with cost
accounting standards as applicable; the program has a qualified
workforce; and the program has adequate technology and
production capacity prior to commencing if the program is
related to manufacturing.
The manager would be required to submit a certification,
within 90 days of establishing the program baseline, stating
that alternative requirements were considered prior to
establishing the program baseline. The certification would be
submitted to the program decision authority (the Assistant
Secretary for Acquisition and Innovation). The Secretary would
ensure that the program management offices for the major
acquisition programs are independent of VBA, VHA, and the
National Cemetery Administration (NCA), and other staff offices
by reporting directly to the Assistant Secretary for
Acquisition and Innovation. The manager would be required to
notify the program decision authority within 30 days of the
conclusion of an acquisition phase of a major acquisition
program. The manager would not be allowed to proceed to a
subsequent acquisition phase without the authorization of the
program decision authority.
VA supports the intent of this section, subject to amendments
VA supports the intent of this section, subject to minor
amendments, as VA has taken action to establish a policy that
major acquisition programs require certified program managers
and teams appointed by the Deputy Secretary to ensure efficient
planning, execution, and oversight of VA's most complex and
high-stakes programs. VA also seeks to ensure that Assistant
Secretary for Acquisition and Innovation would align and seek
input from other senior functional areas regarding statutory
requirements for program oversight.
VA does not have a cost estimate for this section.
Section 4 would transfer all contracting officers and
acquisition centers to the Office of Acquisition and
Innovation. All activities related to the administration of
logistics and supply chain operation would be consolidated
under the DAS for Logistics.
VA supports the intent of this section
VA does not have a cost estimate for this section.
Section 5 would require the Secretary to enter into one or
more contracts for the independent verification and validation
(IV&V) of a major acquisition program or major information
technology project. To be awarded a contract, the CAO would
have to determine that the entity performs or has performed,
within a 3-year period as prime contractor, IV&V or systems
engineering and technical advisory support of major acquisition
programs or defense systems. The entity, including its
subsidiaries, subcontractors, and investments, would be
precluded from receiving an award if it was performing or had
performed within a 3-year period a covered contract for the
project or system involved or for VA. If requested by Congress,
contracting officers would be required to submit an
organizational conflict of interest mitigation plan submitted
by the entity within 30 days from the request. VA would send a
copy of the IV&V to Congress not later than 30 days after it
was performed. The Chief Financial Officer would need to
ensure, to the extent practicable, that each organizational
subdivision that enters into a contract for IV&V proportionally
contributes to the funding of each contract.
VA supports the intent of this section, subject to amendments
VA supports the intent of this section, subject to
amendments. With the exclusive mandate for IV&V by external
contractors, the Department would need to carefully review
existing IV&V and testing-related contracts for compliance
while ensuring continuity. This shift may unintentionally
exclude experienced VA contractors who lack the required DoD-
related contract experience; therefore, VA believes refining
the proposed legislative language for clarity and proactively
addressing these exclusions would be crucial to mitigating
operational disruptions. To preserve operational integrity and
effectiveness, leveraging both governmental expertise and
external contractor support in IV&V processes is vital, and
adhering to industry standards such as IEEE Std. 1012 while
maintaining flexibility in IV&V implementation will ensure
comprehensive oversight without compromising quality.
VA does not have a cost estimate for this section.
Section 6 would add a new section 8184, ``Cost assessment
and program evaluation.'' This new section would establish a
Director of Cost Assessment and Program Evaluation (CAPE) who
would report directly to the Secretary. The CAPE Director would
provide independent analysis and advice to the Secretary and
other senior VA officials on matters assigned to the Director
pursuant to this section and to 38 U.S.C. Sec. 303. Proposed
section 8184(c) would establish two Deputy Directors within the
CAPE Office, one for Cost Assessment and one for Program
Evaluation. Proposed section 8184(d) would define the
responsibilities of the CAPE Director. The Secretary would have
to ensure that the Director promptly received the results of
all cost estimates and cost analyses conducted by VBA, VHA,
NCA, or staff offices and all studies conducted by the
Administration, in connection with such cost estimates and cost
analyses for major acquisition programs and major automated
information system programs of the Administrations. The
Director also would have to have timely access to any records
and data in the Department. Proposed section 8184(h) and
section 6(b) of the bill would define VA's annual reporting
requirements. Finally, section 6(b) would define reporting
requirements on the monitoring of operating and support costs
for major acquisition programs.
VA does not support this section
While VA agrees with the intent behind establishing a CAPE
Director function to enhance oversight, VA does not support
this section. VA does not believe that establishing the
function and roles in law is necessary. VA seeks the
flexibility to develop and expand existing capabilities within
the Office of Management without the additional constraints
prescribed in this section.
VA does not have a cost estimate for this section.
Section 7 would add two new sections, 8185 and 8186, titled
``Other transaction authority'' and ``Advance market
commitments for technologies or services for provision of
health care,'' respectively. Proposed section 8185 would
establish another transaction authority (OTA) that would permit
VA to enter into transactions with non-traditional contractors
to perform certain types of research or innovation development
activities. The authority could also be exercised by the Deputy
Assistant Secretary for Innovation for activities that align
with the mission of the VHA Innovation Ecosystem, provided
certain requirements are met. The criteria include research
that is not duplicative, a determination by the senior
procurement executive that the research is appropriate, that
the transaction will not exceed $5 million to include all
options (unless a determination is made to exceed such limits),
and other details and limitations. It also would specify notice
and reporting requirements to Congress, require VA prescribe
regulations to carry out the section, and lim