Volume 47 · 1416
Public Law 72–154
To extend the times for commencing and completing the construction of a bridge across the Mississippi River between New Orleans and Gretna, Louisiana.
Approved March 1, 1933
Statutory text
AN ACT
To extend the times for commencing and completing the construction of a bridge across the Mississippi River between New Orleans and Gretna, Louisiana.
Be it enacted by the Senate and House of Representatives of the United States of America in Congress assembled,
That the times for
Mississippi River.
Time extended for bridging, between New Orleans and Gretna, La.
commencing and completing the construction of a bridge across the Mississippi River between New Orleans and Gretna, Louisiana, authorized to be built by George A. Hero, and Allen S. Hackett,
Vol. 44, p. 1270; Vol. 45, pp. 193, 1229; Vol. 46, p. 551, amended.
their successors and assigns, by Act of Congress approved March 2, 1927, heretofore extended by Acts of Congress approved March 6, 1928, February 19, 1929, and June 10, 1930, are hereby further extended one and three years, respectively, from March 2, 1933.
Sec. 2.
The right to alter, amend, or repeal this Act is hereby expressly reserved.
Approved, March 1, 1933.