Skip to content

Volume 48 · 1407

Private Law 73–634

For the relief of Carleton-Mace Engineering Corporation.

Approved June 18, 1934

Statutory text

AN ACT

For the relief of Carleton-Mace Engineering Corporation.

Be it enacted by the Senate and House of Representatives of the United States of America in Congress assembled,

That the Comptroller

Carleton-Mace Engineering Corporation.

Claim for extra cost on contract to bo settled.

General of the United States be, and he is hereby, authorized and directed to adjust and settle the claim of Carleton-Mace Engineering Corporation, of Boston, Massachusetts, on account of the extra cost of installing fire-protection system at the naval ammunition depot, Hingham, Massachusetts, under contract numbered 3808-B, which extra cost was occasioned by an embargo placed on freight by the United States Railroad Administration, thereby preventing the completion of the work under the above contract before cold weather set in, and to allow in full and final settlement of said claim such amount, not exceeding $32,726.14, as the Comptroller General may find from the facts and the evidence submitted to him to be the actual amount of the extra cost occasioned by the said embargo. There is hereby appropriated, out of any money in the Treasury not otherwise appropriated, the sum of $32,726.14, or so

Appropriation.

much thereof as may be necessary, to pay the amount herein authorized to be allowed.

Approved, June 18, 1934.

Parsed from the official Statutes at Large USLM XML in 48.xml