Volume 52 · 1300
Private Law 75–177
Conferring jurisdiction upon the United States District Court for the Eastern District of Virginia to hear, determine, and render judgment upon the claim of the Tidewater Construction Corporation.
Approved April 26, 1938
Statutory text
AN ACT
Conferring jurisdiction upon the United States District Court for the Eastern District of Virginia to hear, determine, and render judgment upon the claim of the Tidewater Construction Corporation.
Be it enacted by the Senate and House of Representatives of the United States of America in Congress assembled,
That the claim
Tidewater Construction Corporation.
Jurisdiction conferred upon district court to hear, etc., claim of.
of Tidewater Construction Corporation against the United States for damages alleged to have been sustained by Tidewater Construction Corporation on June 4, 1936, by reason of the steamship Daniel Webster, then owned by the United States, and in tow of the tug Hawk, also owned by the United States, colliding with and doing damage to certain portions of the fender piling and other parts of the James River Bridge near Newport News, Virginia, which the said Tidewater Construction Corporation was then engaged in repairing, may be sued for by the said Tidewater Constructon 1 1 So in original.Corporation in the United States District Court for the Eastern District of Virginia, and that said court shall have jurisdiction to hear and determine such suit and to enter a judgment and decree for such damages and costs, if any, as shall be found to be due against the United States in favor of the said Tidewater Construction Corporation upon the same principles and measures of liability as in like cases as if said
suit were brought under the twentieth paragraph of section 24 of the Judicial Code, as amended, and with the same rights of appeal:
Provisos.
Notice to Attorney General.
Provided, That such notice of the suit shall be given to the Attorney General of the United States as may be provided for by order of the said court, and it shall be the duty of the Attorney General to cause the United States attorney in such district to appear and defend said
Commencement of suit.
United States: Provided further, That said suit shall be brought and commenced within four months from the date of the passage of this
Limitation on amount of judgment.
Act: And provided further, That the judgment, if any, shall not exceed the sum of $3,900.
Approved, April 26, 1938.