Volume 62 · 336
Public Law 80–415
Authorizing modifications in the repayment contracts with the Lower Yellowstone Irrigation District Numbered 1 and the Lower Yellowstone Irrigation District Numbered 2.
Approved June 4, 1948
Statutory text
AN ACT
Authorizing modifications in the repayment contracts with the Lower Yellowstone Irrigation District Numbered 1 and the Lower Yellowstone Irrigation District Numbered 2.
Be it enacted by the Senate and House of Representatives of the United States of America in Congress assembled,
That the Secretary of the Interior, pursuant to section 8 of the Act of August 4, 1939 (53 Stat. 1187), is authorized (a) to enter into appropriate amendatory repayment contracts with Lower Yellowstone Irrigation District Numbered 1 and Lower Yellowstone Irrigation District Numbered 2 for the purpose of effecting changes, modifications, and financial adjustments in the existing district repayment contracts and (b) to make appropriate adjustment of project accounts, all consistent with the provisions of this Act.
Sec. 2.
Changes in repayment contracts.
With respect to the Lower Yellowstone Irrigation District Numbered 1:
Payment of construction charges against one thousand three hundred and forty and four one-hundredths acres of lands classified
Temporarily unproductive land.
under the Act of May 25, 1926, as productive and found to be possessed of insufficient productive power to be continued in a paying class shall be suspended until the Secretary of the Interior shall declare them to be possessed of sufficient productive power properly to be placed in the paying class, whereupon payment of construction charges against such areas shall be resumed. While said lands are so classified as temporarily unproductive, and the construction charges against them are suspended, water for irrigation purposes may be furnished upon payment of the usual operation and maintenance charges or such other charges as may be fixed by the Secretary of the Interior, the advance payment of which may be required in the discretion of the said Secretary. Should said lands temporarily classed as unproductive, or any of them in the future, be found by the Secretary of the Interior to be permanently unproductive, the charges against them shall be charged off as a permanent loss to the reclamation fund;
(b) Permanently unproductive land.44 Stat. 640.
The charges in the amount of $12,166 against two hundred and twenty and thirty-six one-hundredths acres of lands classified in a paying class under the Act of May 25, 1926, and found to be permanently unproductive shall be deducted from the contractual obligation of said Lower Yellowstone Irrigation District Numbered 1;
(c) Contractual obligation.
The contractual obligation of Lower Yellowstone Irrigation District Numbered 1 shall, by reason of a finding that four hundred and fifty-two and ninety-six one-hundredths acres of lands previously classed as permanently unproductive, possess sufficient productive power properly to be placed in a paying class, be increased in the sum of $25,008; and
(d) Construction charges.
The construction charges against four hundred and sixty-two and eighty-seven one-hundredths acres of lands included in drain and lateral right-of-way and found to be excluded from the irrigable area of the project shall be included in the principal obligation of the district, but said lands are to be relieved of future assessment by the district.
Sec. 3.
With respect to the Lower Yellowstone Irrigation District Numbered 2:
(a) Temporarily unproductive land.44 Stat. 640.
Payment of construction charges against six hundred and sixty two and ninety one-hundredths acres of lands classified under the Act of May 25, 1926, as productive and found to be possessed of insufficient productive power to be continued in a paying class shall be suspended until the Secretary of the Interior shall declare them to be possessed of sufficient productive power properly to be placed in the paying class, whereupon payment of construction charges against such areas shall be resumed. While said lands are so classified as temporarily unproductive, and the construction charges against them are suspended, water for irrigation purposes may be furnished upon payment of the usual operation and maintenance charges or such other charges as may be fixed by the Secretary of the Interior, the advance payment of which may be required in the discretion of the said Secretary. Should said lands temporarily classed as unproductive, or any of them in the future, be found by the Secretary of the Interior to be permanently unproductive, the charges against them shall be charged off as a permanent loss to the Reclamation Fund;
(b) Permanently unproductive land.44 Stat. 640.
The charges in the amount of $911 against sixteen and fifty one-hundredths acres of lands classified in a paying class under the Act of May 25, 1926. and found to be permanently unproductive shall be deducted from the contractual obligation of said Lower Yellowstone Irrigation District Numbered 2;
(c) Contractual obligation.
The contractual obligation of Lower Yellowstone Irrigation District Numbered 2 shall, by reason of a finding that one hundred and eighty-two and twenty-two one-hundredths acres of lands previously classed as permanently unproductive, possess sufficient productive power properly to be placed in a paying class, be increased in the sum of $10,060; and
(d) Construction charges.
The construction charges against four hundred and thirty-one and thirty-eight one-hundredths acres of lands included in drain and lateral right-of-way and found to be excluded from the irrigable area of the project shall be included in the principal obligation of the district, but said lands shall be relieved of future assessment by the district.
Sec. 4.
The contractual modifications provided for in this Act shall be effective, as to Lower Yellowstone Irrigation District Numbered
Effective dates.
1, as of September 19, 1945, and, as to Lower Yellowstone Irrigation District Numbered 2, as of October 31, 1945.
Approved June 4, 1948.