Volume 79 · 134
Public Law 89–42
Authorizing additional appropriations for prosecution of projects in certain comprehensive river basin plans for flood control, navigation, and other purposes.
Approved June 18, 1965
Statutory text
AN ACT
Authorizing additional appropriations for prosecution of projects in certain comprehensive river basin plans for flood control, navigation, and other purposes.
Be it enacted by the Senate and House of Representatives of the United States of America in Congress assembled,
That,
in addition to previous authorizations, there is hereby authorized to be appropriated for the prosecution of the comprehensive plan of development of each river basin under the jurisdiction of the Secretary of the Army referred to in the first column below, which was basically authorized by the Act referred to by date of enactment in the second column below, an amount not to exceed that shown opposite such river basin in the third column below:
| Basin | Act of Congress | Amount |
|---|---|---|
| Alabama-Coosa | March 2, 1945 | $38,000,000 |
| Arkansas River | June 28, 1888 | 290,000,000 |
| Brazos River | September 3, 1954 | 14,000,000 |
| Central and Southern Florida | June 30, 1948 | 30,000,000 |
| Columbia River | June 28, 1938 | 223,000,000 |
| Lower Mississippi | May 15, 1928 | 53,000,000 |
| Missouri River | June 28, 1938 | 118,000,000 |
| Ohio River | June 22, 1938 | 89,000,000 |
| Ouachita River | May 17, 1950 | 11,000,000 |
| Upper Mississippi River | June 28, 1938 | 27,000,000 |
| West Branch Susquehanna River | September 3, 1954 | 17,000,000 |
The total amount authorized to be appropriated by this section shall not exceed $908,000,000.
Sec. 2.
In addition to previous authorizations, the completion of the Great Lakes to Hudson River Waterway, New York, project, approved in the River and Harbor Act of August 30, 1935, as amended,
is hereby authorized at an estimated cost of $5,000,000.
Sec. 3.
In addition to previous authorizations, the completion of the comprehensive plan for flood control and other purposes in the Los Angeles River Basin, approved by the Flood Control Act of August 18, 1941, as amended and supplemented, is hereby authorized
at an estimated cost of $31,000,000.
Approved June 18, 1965.