Statutory text
Project Authorization Required.—
The Secretary of Defense may carry out such military construction projects for energy resilience, energy security, and energy conservation as are authorized by law, using funds appropriated or otherwise made available for that purpose.
Submission of Project Proposals.—
As part of the Department of Defense Form 1391 submitted to the appropriate committees of Congress for a military construction project covered by subsection (a), the Secretary of Defense shall include the following information:
The project title.
The location of the project.
A brief description of the scope of work.
The original project cost estimate and the current working cost estimate, if different.
Such other information as the Secretary considers appropriate.
In the case of a military construction project for energy conservation, the Secretary also shall include the following information:
The original expected savings-to-investment ratio and simple payback estimates and measurement and verification cost estimate.
The most current expected savings-to-investment ratio and simple payback estimates and measurement and verification plan and costs.
A brief description of the measurement and verification plan and planned funding source.
In the case of a military construction project for energy resilience or energy security, the Secretary also shall include the rationale for how the project would enhance mission assurance, support mission critical functions, and address known vulnerabilities.
Alternative Funding Source.—
In addition to the authority under section 2805(c) of this title, in carrying out a military construction project for energy resilience, energy security, or energy conservation under this section, the Secretary concerned may use amounts available for operation and maintenance for the military department concerned if the Secretary concerned submits to the congressional defense committees a notification of the decision to carry out the project using such amounts and includes in the notification—
the current estimate of the cost of the project;
the source of funds for the project; and
a certification that deferring the project pending the availability of funds appropriated for or otherwise made available for military construction would be inconsistent with the timely assurance of energy resilience, energy security, or energy conservation for one or more critical national security functions.
A project carried out under this section using amounts under paragraph (1) may be carried out only after the end of the seven-day period beginning on the date on which a copy of the notification described in paragraph (1) is provided in an electronic medium pursuant to section 480 of this title.
The maximum aggregate amount that the Secretary concerned may obligate from amounts available to the military department concerned for operation and maintenance in any fiscal year for projects under the authority of this subsection is $100,000,000.
Relation to Certain Other Authorities.—
A project under this section may include—
activities related to a utility system authorized under subsections (h), (j), and (k) of section 2688 or section 2913 of this title, notwithstanding that the United States does not own the utility system covered by the project; and
energy-related activities included as a separate requirement in an energy savings performance contract (as defined in section 804(3) of the National Energy Conservation Policy Act (42 U.S.C. 8287c(3))).
Incorporation of Cybersecurity Supply Chain Risk Management Tools and Methods.—
The Secretary of Defense shall incorporate into covered projects cybersecurity supply chain risk management tools and solutions to provide continuous analysis, monitoring, and mitigation of cyber vulnerabilities.
In carrying out the requirements of paragraph (1), the Secretary of Defense shall consider, to the maximum extent practicable, the following:
The adoption of commercially available cybersecurity supply chain risk management tools and solutions.
The inclusion of existing databases on cyber vulnerabilities when selecting such tools and solutions.
The need for such tools and methods to provide continuous analysis, monitoring, and mitigation of cyber vulnerabilities in covered projects.
Beginning with fiscal year 2026, documentation for any new requirements for cybersecurity supply chain risk management in annual guidance for covered projects that is submitted along with the annual budget request of the President submitted pursuant to section 1105 of title 31.
In this subsection, the term “covered project” means a project connected to a Department of Defense Information Network for which funds are made available under this section.
Application to Military Construction Projects.—
This section shall apply to military construction projects covered by subsection (a) for which a Department of Defense Form 1391 is submitted to the appropriate committees of Congress in connection with the budget of the Department of Defense for fiscal year 2023 and thereafter.
Legislative history
Reconstructed from this section’s Code source credit and amendment notes, resolved against the local Statutes at Large. Editorial notes are evidence, not the law that made the change.
Military Construction Authorization Act for Fiscal Year 2007
Pub. L. 109–364 div. B title XXVIII § 2851(a)(1) · 120 Stat. 2083
Enacted · 10 U.S.C. § 2914
Added Pub. L. 109–364, div. B, title XXVIII, § 2851(a)(1), Oct. 17, 2006, 120 Stat. 2493
Source evidence
Code source credit
Added Pub. L. 109–364, div. B, title XXVIII, § 2851(a)(1), Oct. 17, 2006, 120 Stat. 2493Enacted provision · exact public law section
(1) Reorganization of section 2865 of title 10.— Title 10, United States Code, is amended by inserting after chapter 172 the following new chapter: “CHAPTER 173— ENERGY SECURITY “Subchapter “I. Energy Security Activities “II. Energy-Related Procurement “III. General Provisions “SUBCHAPTER I— ENERGY SECURITY ACTIVITIES “Sec. “ 2911. Energy performance goals and plan for Department of Defense. “ 2912. Availability and use of energy cost savings. “ 2913. Energy savings contracts and activities. “ 2914. Energy conservation construction projects. “2915. New construction: use of renewable forms of energy and energy efficient products. “2916. Sale of electricity from alternate energy and cogeneration production facilities. “2917. Development of geothermal energy on military lands. “2918. Fuel sources for heating systems; prohibition on converting certain heating facilities. “§ 2911. Energy performance goals and plan for Department of Defense “(a) Energy Performance Goals.— (1) The Secretary of Defense shall submit to the congressional defense committees the energy performance goals for the Department of Defense regarding transportation systems, support systems, utilities, and infrastructure and facilities. “(2) Deadline. The energy performance goals shall be submitted annually not later than the date on which the President submits to Congress the budget for the next fiscal year under section 1105 of title 31 and cover that fiscal year as well as the next five, l0, and 20 years. The Secretary shall identify changes to the energy performance goals since the previous submission. “(b) Energy Performance Plan.— The Secretary of Defense shall develop, and update as necessary, a comprehensive plan to help achieve the energy performance goals for the Department of Defense. “(c) Special Considerations.— For the purpose of developing and implementing the energy performance goals and energy performance plan, the Secretary of Defense shall consider at a minimum the following: “(1) Opportunities to reduce the current rate of consumption of energy. “(2) Opportunities to reduce the future demand and the requirements for the use of energy. “(3) Opportunities to implement conservation measures to improve the efficient use of energy. “(4) Opportunities to pursue alternative energy initiatives, including the use of alternative fuels in military vehicles and equipment. “(5) Cost effectiveness, cost savings, and net present value of alternatives. “(6) The value of diversification of types and sources of energy used. “(7) The value of economies-of-scale associated with fewer energy types used. “(8) The value of the use of renewable energy sources. “(9) The potential for an action to serve as an incentive for members of the armed forces and civilian personnel to reduce energy consumption or adopt an improved energy performance measure. “(d) Selection of Energy Conservation Measures.— (1) For the purpose of implementing the energy performance plan, the Secretary of Defense shall provide that the selection of energy conservation measures, including energy efficient maintenance, shall be limited to those measures that— “(A) are readily available; “(B) demonstrate an economic return on the investment; “(C) are consistent with the energy performance goals and energy performance plan for the Department; and “(D) are supported by the special considerations specified in subsection (c). “(2) In this subsection, the term ‘energy efficient maintenance’ includes— “(A) the repair of military vehicles, equipment, or facility and infrastructure systems, such as lighting, heating, or cooling equipment or systems, or industrial processes, by replacement with technology that— “(i) will achieve energy savings over the life-cycle of the equipment or system being repaired; and “(ii) will meet the same end needs as the equipment or system being repaired; and “(B) improvements in an operation or maintenance process, such as improved training or improved controls, that result in energy savings. “§ 2912. Availability and use of energy cost savings “(a) Availability.— An amount of the funds appropriated to the Department of Defense for a fiscal year that is equal to the amount of energy cost savings realized by the Department, including financial benefits resulting from shared energy savings contracts entered into under section 2913 of this title, shall remain available for obligation under subsection (b) until expended, without additional authorization or appropriation. “(b) Use.— The Secretary of Defense shall provide that the amount that remains available for obligation under subsection (a) and the funds made available under section 2916(b)(2) of this title shall be used as follows: “(1) One-half of the amount shall be used for the implementation of additional energy conservation measures at buildings, facilities, or installations of the Department of Defense or related to vehicles and equipment of the Department, which are designated, in accordance with regulations prescribed by the Secretary of Defense, by the head of the department, agency, or instrumentality that realized the savings referred to in subsection (a). “(2) One-half of the amount shall be used at the installation at which the savings were realized, as determined by the commanding officer of such installation consistent with applicable law and regulations, for— “(A) improvements to existing military family housing units; “(B) any unspecified minor construction project that will enhance the quality of life of personnel; or “(C) any morale, welfare, or recreation facility or service. “(c) Treatment of Certain Financial Incentives.— Financial incentives received from gas or electric utilities under section 2913 of this title shall be credited to an appropriation designated by the Secretary of Defense. Amounts so credited shall be merged with the appropriation to which credited and shall be available for the same purposes and the same period as the appropriation with which merged. “(d) Congressional Notification.— The Secretary of Defense shall include in the budget material submitted to Congress in connection with the submission of the budget for a fiscal year pursuant to section 1105 of title 31 a separate statement of the amounts available for obligation under this section in that fiscal year. “§ 2913. Energy savings contracts and activities “(a) Shared Energy Savings Contracts.— (1) The Secretary of Defense shall develop a simplified method of contracting for shared energy savings contract services that will accelerate the use of these contracts with respect to military installations and will reduce the administrative effort and cost on the part of the Department of Defense as well as the private sector. “(2) In carrying out paragraph (1), the Secretary of Defense may— “(A) request statements of qualifications (as prescribed by the Secretary of Defense), including financial and performance information, from firms engaged in providing shared energy savings contracting; “(B) designate from the statements received, with an update at least annually, those firms that are presumptively qualified to provide shared energy savings services; “(C) select at least three firms from the qualifying list to conduct discussions concerning a particular proposed project, including requesting a technical and price proposal from such selected firms for such project; and “(D) select from such firms the most qualified firm to provide shared energy savings services pursuant to a contractual arrangement that the Secretary determines is fair and reasonable, taking into account the estimated value of the services to be rendered and the scope and nature of the project. “(3) In carrying out paragraph (1), the Secretary may also provide for the direct negotiation, by departments, agencies, and instrumentalities of the Department of Defense, of contracts with shared energy savings contractors that have been selected competitively and approved by any gas or electric utility serving the department, agency, or instrumentality concerned. “(b) Participation in Gas or Electric Utility Programs.— The Secretary of Defense shall permit and encourage each military department, Defense Agency, and other instrumentality of the Department of Defense to participate in programs conducted by any gas or electric utility for the management of energy demand or for energy conservation. “(c) Acceptance of Financial Incentive, Goods, or Services.— The Secretary of Defense may authorize any military installation to accept any financial incentive, goods, or services generally available from a gas or electric utility, to adopt technologies and practices that the Secretary determines are in the interests of the United States and consistent with the energy performance goals for the Department of Defense. “(d) Agreements With Gas or Electric Utilities.— (1) The Secretary of Defense may authorize the Secretary of a military department having jurisdiction over a military installation to enter into agreements with gas or electric utilities to design and implement cost-effective demand and conservation incentive programs (including energy management services, facilities alterations, and the installation and maintenance of energy saving devices and technologies by the utilities) to address the requirements and circumstances of the installation. “(2) If an agreement under this subsection provides for a utility to advance financing costs for the design or implementation of a program referred to in that paragraph to be repaid by the United States, the cost of such advance may be recovered by the utility under terms no less favorable than those applicable to its most favored customer. “(3) Subject to the availability of appropriations, repayment of costs advanced under paragraph (2) shall be made from funds available to a military department for the purchase of utility services. “(4) An agreement under this subsection shall provide that title to any energy-saving device or technology installed at a military installation pursuant to the agreement vest in the United States. Such title may vest at such time during the term of the agreement, or upon expiration of the agreement, as determined to be in the best interests of the United States. “§ 2914. Energy conservation construction projects “(a) Projects Authorized.— The Secretary of Defense may carry out a military construction project for energy conservation, not previously authorized, using funds appropriated or otherwise made available for that purpose. “(b) Congressional Notification.— When a decision is made to carry out a project under this section, the Secretary of Defense shall notify in writing the appropriate committees of Congress of that decision. The project may then be carried out only after the end of the 21-day period beginning on the date the notification is received by such committees or, if earlier, the end of the 14-day period beginning on the date on which a copy of the notification is provided in an electronic medium pursuant to section 480 of this title. “SUBCHAPTER II— ENERGY-RELATED PROCUREMENT “Sec. “2922. Liquid fuels and natural gas: contracts for storage, handling, or distribution. “2922a. Contracts for energy or fuel for military installations. “2922b. Procurement of energy systems using renewable forms of energy. “2922c. Procurement of gasohol as motor vehicle fuel. “2922d. Procurement of fuel derived from coal, oil shale, and tar sands. “2922e. Acquisition of certain fuel sources: authority to waive contract procedures; acquisition by exchange; sales authority. “2922f. Preference for energy efficient electric equipment. “SUBCHAPTER III— GENERAL PROVISIONS “Sec. “2925. Annual report. “§ 2925. Annual report “(a) Report Required.— As part of the annual submission of the energy performance goals for the Department of Defense under section 2911 of this title, the Secretary of Defense shall submit a report containing the following: “(1) A description of the progress made to achieve the goals of the Energy Policy Act of 2005 (Public Law 109–58) and the energy performance goals for the Department of Defense during the preceding fiscal year. “(2) A description of the actions taken to implement the energy performance plan in effect under section 2911 of this title and carry out this chapter during the preceding fiscal year. “(3) A description of the energy savings realized from such actions. “(4) An estimate of the types and quantities of energy consumed by the Department of Defense and members of the armed forces and civilian personnel residing or working on military installations during the preceding fiscal year, including a breakdown of energy consumption by user groups and types of energy, energy costs, and the quantities of renewable energy produced or procured by the Department. “(5) A description of the types and amount of financial incentives received under section 2913 of this title during the preceding fiscal year and the appropriation account or accounts to which the incentives were credited. “(b) Initial Report.— In the first report required under this section, the Secretary of Defense shall include the following: “(1) Such recommendations for changes to this chapter as the Secretary considers appropriate to improve energy performance. “(2) A description of how responsibility over energy performance is distributed within the Department of Defense and a discussion on whether such responsibilities should be consolidated within a single entity. “(3) A discussion of the manner in which the Secretary intends to balance the considerations specified in subsection (c) of section 2911 of this title in developing and implementing the energy performance goals and energy performance plan. “(4) A discussion of the extent to which non-direct energy costs are considered in making research and development, procurement, and construction decisions.” .Military Construction Authorization Act for Fiscal Year 2017
Pub. L. 114–328 § 2805(a)(1)(A) · 130 Stat. 2000
Inserted · 10 U.S.C. § 2914
Pub. L. 114–328, § 2805(a)(1)(A), inserted “resiliency and” before “conservation construction projects” in section catchline. Text quoted in directory language of amendment was editorially conformed to the style of the catchline
Source evidence
Code amendment note
Pub. L. 114–328, § 2805(a)(1)(A), inserted “resiliency and” before “conservation construction projects” in section catchline. Text quoted in directory language of amendment was editorially conformed to the style of the catchline.Enacted provision · exact public law section
(A) in the section heading, by inserting “resiliency and” before “conservation construction projects”; andEffective date note
Pub. L. 114–328, div. B, title XXVIII, § 2805(b)(1)(B), Dec. 23, 2016, 130 Stat. 2714, provided that: “The amendment made by subparagraph (A) [amending this section] shall apply with respect to notifications provided during fiscal year 2017 or any succeeding fiscal year.”Military Construction Authorization Act for Fiscal Year 2017
Pub. L. 114–328 § 2805(a)(1)(B) · 130 Stat. 2000
Substituted · 10 U.S.C. § 2914(a)
Pub. L. 114–328, § 2805(a)(1)(B), substituted “military construction project for energy resiliency, energy security, or energy conservation” for “military construction project for energy conservation”
Source evidence
Code amendment note
Subsec. (a). Pub. L. 114–328, § 2805(a)(1)(B), substituted “military construction project for energy resiliency, energy security, or energy conservation” for “military construction project for energy conservation”.Enacted provision · exact public law section
(B) in subsection (a), by striking “military construction project for energy conservation” and inserting “military construction project for energy resiliency, energy security, or energy conservation”.Effective date note
Pub. L. 114–328, div. B, title XXVIII, § 2805(b)(1)(B), Dec. 23, 2016, 130 Stat. 2714, provided that: “The amendment made by subparagraph (A) [amending this section] shall apply with respect to notifications provided during fiscal year 2017 or any succeeding fiscal year.”Military Construction Authorization Act for Fiscal Year 2017
Pub. L. 114–328 § 2805(b)(1)(A) · 130 Stat. 2000
Amended · 10 U.S.C. § 2914(b)
Pub. L. 114–328, § 2805(b)(1)(A), designated existing provisions as par. (1)
Added · 10 U.S.C. § 2914(b)
Pub. L. 114–328, § 2805(b)(1)(A), added par. (2)
Source evidence
Code amendment note
Subsec. (b). Pub. L. 114–328, § 2805(b)(1)(A), designated existing provisions as par. (1) and added par. (2).Enacted provision · exact public law section
(A) Contents.— Section 2914(b) of title 10, United States Code, is amended— (i) by striking “When a decision” and inserting “(1) When a decision”; and (ii) by adding at the end the following new paragraph: “(2) The Secretary of Defense shall include in each notification submitted under paragraph (1) the following information: “(A) In the case of a military construction project for energy conservation, the justification and current cost estimate for the project, the expected savings-to-investment ratio, simple payback estimates, and the project’s measurement and verification cost estimate. “(B) In the case of a military construction project for energy resiliency or energy security, the rationale for how the project would enhance mission assurance, support mission critical functions, and address known vulnerabilities.” .Effective date note
Pub. L. 114–328, div. B, title XXVIII, § 2805(b)(1)(B), Dec. 23, 2016, 130 Stat. 2714, provided that: “The amendment made by subparagraph (A) [amending this section] shall apply with respect to notifications provided during fiscal year 2017 or any succeeding fiscal year.”Military Construction Authorization Act for Fiscal Year 2017
Pub. L. 114–328 § 2805(b)(2) · 130 Stat. 2000
Added · 10 U.S.C. § 2914(c)
Pub. L. 114–328, § 2805(b)(2), added subsec. (c)
Source evidence
Code amendment note
Subsec. (c). Pub. L. 114–328, § 2805(b)(2), added subsec. (c).Enacted provision · exact public law section
(2) Annual report.— Section 2914 of such title is amended by adding at the end the following new subsection: “(c) Annual Report.— Not later than 90 days after the end of each fiscal year (beginning with fiscal year 2017), the Secretary of Defense shall submit to the appropriate committees of Congress a report on the status of the planned and active projects carried out under this section (including completed projects), and shall include in the report with respect to each such project the following information: “(1) The title, location, a brief description of the scope of work, the original project cost estimate, and the current working cost estimate. “(2) In the case of a military construction project for energy conservation— “(A) the original expected savings-to-investment ratio and simple payback estimates and measurement and verification cost estimate; “(B) the most current expected savings-to-investment ratio and simple payback estimates and measurement and verification plan and costs; and “(C) a brief description of the measurement and verification plan and planned funding source. “(3) In the case of a military construction project for energy resiliency or energy security, the rationale for how the project would enhance mission assurance, support mission critical functions, and address known vulnerabilities. “(4) Such other information as the Secretary considers appropriate.” .Effective date note
Pub. L. 114–328, div. B, title XXVIII, § 2805(b)(1)(B), Dec. 23, 2016, 130 Stat. 2714, provided that: “The amendment made by subparagraph (A) [amending this section] shall apply with respect to notifications provided during fiscal year 2017 or any succeeding fiscal year.”Military Construction Authorization Act for Fiscal Year 2018
Pub. L. 115–91 § 2831(c)(1) · 131 Stat. 1283
Substituted · 10 U.S.C. § 2914
Pub. L. 115–91, § 2831(c)(1), substituted “energy resilience” for “energy resiliency” wherever appearing in text
Source evidence
Code amendment note
Pub. L. 115–91, § 2831(c)(1), substituted “energy resilience” for “energy resiliency” wherever appearing in text.Enacted provision · exact public law section
(1) in section 2914, by striking “energy resiliency” each place it appears and inserting “energy resilience”;Military Construction Authorization Act for Fiscal Year 2018
Pub. L. 115–91 § 2801(e)(1) · 131 Stat. 1283
Struck · 10 U.S.C. § 2914(b)(1)
Pub. L. 115–91, § 2801(e)(1), struck out “in writing” after “shall notify” and “or, if earlier, the end of the 14-day period beginning on the date on which a copy of the notification is provided” after “received by such committees”
Substituted · 10 U.S.C. § 2914(b)(1)
Pub. L. 115–91, § 2801(e)(1), substituted “14-day period” for “21-day period”
Source evidence
Code amendment note
Subsec. (b)(1). Pub. L. 115–91, § 2801(e)(1), struck out “in writing” after “shall notify” and “or, if earlier, the end of the 14-day period beginning on the date on which a copy of the notification is provided” after “received by such committees” and substituted “14-day period” for “21-day period”.Enacted provision · exact public law section
(1) Section 2914(b)(1) is amended— (A) by striking “in writing”; (B) by striking “21-day period” and inserting “14-day period”; and (C) by striking “or, if earlier, the end of the 14-day period beginning on the date on which a copy of the notification is provided”.John S. McCain National Defense Authorization Act for Fiscal Year 2019
Pub. L. 115–232 div. A title X § 1081(a)(29) · 132 Stat. 1636
Substituted · 10 U.S.C. § 2914
Pub. L. 115–232 substituted “resilience” for “resiliency” in section catchline
Source evidence
Code amendment note
Pub. L. 115–232 substituted “resilience” for “resiliency” in section catchline.Enacted provision · exact public law section
(29) The heading of section 2914 is amended to read as follows: “§ 2914. Energy resilience and conservation construction projects” .Military Construction Authorization Act for Fiscal Year 2021
Pub. L. 116–283 § 2805(a) · 134 Stat. 3388
Amended · 10 U.S.C. § 2914
Pub. L. 116–283, § 2805(a), amended section generally. Prior to amendment, section related to energy resilience and conservation construction projects
Source evidence
Code amendment note
Pub. L. 116–283, § 2805(a), amended section generally. Prior to amendment, section related to energy resilience and conservation construction projects.Enacted provision · exact public law section
(a) Replacement of Notice and Wait Authority.— Section 2914 of title 10, United States Code, is amended to read as follows: “§ 2914. Military construction projects for energy resilience, energy security, and energy conservation “(a) Project Authorization Required.— The Secretary of Defense may carry out such military construction projects for energy resilience, energy security, and energy conservation as are authorized by law, using funds appropriated or otherwise made available for that purpose. “(b) Submission of Project Proposals.— (1) As part of the Department of Defense Form 1391 submitted to the appropriate committees of Congress for a military construction project covered by subsection (a), the Secretary of Defense shall include the following information: “(A) The project title. “(B) The location of the project. “(C) A brief description of the scope of work. “(D) The original project cost estimate and the current working cost estimate, if different. “(E) Such other information as the Secretary considers appropriate. “(2) In the case of a military construction project for energy conservation, the Secretary also shall include the following information: “(A) The original expected savings-to-investment ratio and simple payback estimates and measurement and verification cost estimate. “(B) The most current expected savings-to-investment ratio and simple payback estimates and measurement and verification plan and costs. “(C) A brief description of the measurement and verification plan and planned funding source. “(3) In the case of a military construction project for energy resilience or energy security, the Secretary also shall include the rationale for how the project would enhance mission assurance, support mission critical functions, and address known vulnerabilities. “(c) Application to Military Construction Projects.— This section shall apply to military construction projects covered by subsection (a) for which a Department of Defense Form 1391 is submitted to the appropriate committees of Congress in connection with the budget of the Department of Defense for fiscal year 2023 and thereafter.” .Military Construction Authorization Act for Fiscal Year 2021
Pub. L. 116–283 § 2823(b) · 134 Stat. 3388
Added · 10 U.S.C. § 2914(c); 10 U.S.C. § 2914(d)
Pub. L. 116–283, § 2823(b), added subsec. (c)
Redesignated · 10 U.S.C. § 2914(c); 10 U.S.C. § 2914(d)
Pub. L. 116–283, § 2823(b), redesignated former subsec. (c) as (d)
Target inherited from the preceding amendment note.
Source evidence
Code amendment note
Pub. L. 116–283, § 2823(b), added subsec. (c) and redesignated former subsec. (c) as (d).Enacted provision · exact public law section
(b) Availability of ERCIP Funds for Privatized Utility System Activities.— Section 2914 of title 10, United States Code, as amended by section 2805, is further amended— (1) by redesignating subsection (c) as subsection (d); and (2) by inserting after subsection (b) the following new subsection (c): “(c) Relation to Certain Other Authorities.— A project under this section may include— “(1) activities related to a utility system authorized under subsections (h), (j), and (k) of section 2688 or section 2913 of this title, notwithstanding that the United States does not own the utility system covered by the project; and “(2) energy-related activities included as a separate requirement in an energy savings performance contract (as defined in section 804(3) of the National Energy Conservation Policy Act (42 U.S.C. 8287c(3))).” .National Defense Authorization Act for Fiscal Year 2022
Pub. L. 117–81 div. B title XXVIII § 2804 · 135 Stat. 1541
Added · 10 U.S.C. § 2914(c); 10 U.S.C. § 2914(d)
Pub. L. 117–81 added subsec. (c)
Redesignated · 10 U.S.C. § 2914(c); 10 U.S.C. § 2914(d)
Pub. L. 117–81 redesignated former subsec. (c) as (d). Former subsec. (d) redesignated (e)
Source evidence
Code amendment note
Subsecs. (c), (d). Pub. L. 117–81 added subsec. (c) and redesignated former subsec. (c) as (d). Former subsec. (d) redesignated (e).Enacted provision · exact public law section
SEC. 2804. USE OF AMOUNTS AVAILABLE FOR OPERATION AND MAINTENANCE IN CARRYING OUT MILITARY CONSTRUCTION PROJECTS FOR ENERGY RESILIENCE, ENERGY SECURITY, OR ENERGY CONSERVATION. Section 2914 of title 10, United States Code, is amended— (1) by redesignating subsections (c) and (d) as subsections (d) and (e), respectively; and (2) by inserting after subsection (b) the following new subsection (c): “(c) Alternative Funding Source.— (1) In addition to the authority under section 2805(c) of this title, in carrying out a military construction project for energy resilience, energy security, or energy conservation under this section, the Secretary concerned may use amounts available for operation and maintenance for the military department concerned if the Secretary concerned submits to the congressional defense committees a notification of the decision to carry out the project using such amounts and includes in the notification— “(A) the current estimate of the cost of the project; “(B) the source of funds for the project; and “(C) a certification that deferring the project pending the availability of funds appropriated for or otherwise made available for military construction would be inconsistent with the timely assurance of energy resilience, energy security, or energy conservation for one or more critical national security functions. “(2) A project carried out under this section using amounts under paragraph (1) may be carried out only after the end of the seven-day period beginning on the date on which a copy of the notification described in paragraph (1) is provided in an electronic medium pursuant to section 480 of this title. “(3) The maximum aggregate amount that the Secretary concerned may obligate from amounts available to the military department concerned for operation and maintenance in any fiscal year for projects under the authority of this subsection is $100,000,000.” .National Defense Authorization Act for Fiscal Year 2022
Pub. L. 117–81 § 2804(1) · 135 Stat. 1541
Redesignated · 10 U.S.C. § 2914(e)
Pub. L. 117–81, § 2804(1), redesignated subsec. (d) as (e)
Source evidence
Code amendment note
Subsec. (e). Pub. L. 117–81, § 2804(1), redesignated subsec. (d) as (e).Enacted provision · exact public law section
(1) by redesignating subsections (c) and (d) as subsections (d) and (e), respectively; andNational Defense Authorization Act for Fiscal Year 2024
Pub. L. 118–31 div. B title XXVIII § 2809 · 137 Stat. 136
Added · 10 U.S.C. § 2914(e); 10 U.S.C. § 2914(f)
Pub. L. 118–31 added subsec. (e)
Redesignated · 10 U.S.C. § 2914(e); 10 U.S.C. § 2914(f)
Pub. L. 118–31 redesignated former subsec. (e) as (f)
Source evidence
Code amendment note
Subsecs. (e), (f). Pub. L. 118–31 added subsec. (e) and redesignated former subsec. (e) as (f).Enacted provision · exact public law section
SEC. 2809. INCORPORATION OF CYBERSECURITY SUPPLY CHAIN RISK MANAGEMENT TOOLS AND METHODS. Section 2914 of title 10, United States Code, is amended— (1) by redesignating subsection (e) as subsection (f); and (2) by inserting after subsection (d) the following new subsection: “(e) Incorporation of Cybersecurity Supply Chain Risk Management Tools and Methods.— (1) The Secretary of Defense shall incorporate into covered projects cybersecurity supply chain risk management tools and solutions to provide continuous analysis, monitoring, and mitigation of cyber vulnerabilities. “(2) In carrying out the requirements of paragraph (1), the Secretary of Defense shall consider, to the maximum extent practicable, the following: “(A) The adoption of commercially available cybersecurity supply chain risk management tools and solutions. “(B) The inclusion of existing databases on cyber vulnerabilities when selecting such tools and solutions. “(C) The need for such tools and methods to provide continuous analysis, monitoring, and mitigation of cyber vulnerabilities in covered projects. “(D) Beginning with fiscal year 2026, documentation for any new requirements for cybersecurity supply chain risk management in annual guidance for covered projects that is submitted along with the annual budget request of the President submitted pursuant to section 1105 of title 31. “(3) In this subsection, the term ‘covered project’ means a project connected to a Department of Defense Information Network for which funds are made available under this section.” .
18 of 18 references resolved to an enrolled provision
Editorial Notes
Amendments2016–2023 · 5 rounds
2023
Subsecs. (e), (f). Pub. L. 118–31 added subsec. (e) and redesignated former subsec. (e) as (f).
2021
Pub. L. 116–283, § 2805(a), amended section generally. Prior to amendment, section related to energy resilience and conservation construction projects.
Subsecs. (c), (d). Pub. L. 117–81 added subsec. (c) and redesignated former subsec. (c) as (d). Former subsec. (d) redesignated (e).
Pub. L. 116–283, § 2823(b), added subsec. (c) and redesignated former subsec. (c) as (d).
Subsec. (e). Pub. L. 117–81, § 2804(1), redesignated subsec. (d) as (e).
2018
Pub. L. 115–232 substituted “resilience” for “resiliency” in section catchline.
2017
Pub. L. 115–91, § 2831(c)(1), substituted “energy resilience” for “energy resiliency” wherever appearing in text.
Subsec. (b)(1). Pub. L. 115–91, § 2801(e)(1), struck out “in writing” after “shall notify” and “or, if earlier, the end of the 14-day period beginning on the date on which a copy of the notification is provided” after “received by such committees” and substituted “14-day period” for “21-day period”.
2016
Pub. L. 114–328, § 2805(a)(1)(A), inserted “resiliency and” before “conservation construction projects” in section catchline. Text quoted in directory language of amendment was editorially conformed to the style of the catchline.
Subsec. (a). Pub. L. 114–328, § 2805(a)(1)(B), substituted “military construction project for energy resiliency, energy security, or energy conservation” for “military construction project for energy conservation”.
Subsec. (b). Pub. L. 114–328, § 2805(b)(1)(A), designated existing provisions as par. (1) and added par. (2).
Subsec. (c). Pub. L. 114–328, § 2805(b)(2), added subsec. (c).
Statutory Notes and Related Subsidiaries
Effective Date of 2016 Amendment
Pub. L. 114–328, div. B, title XXVIII, § 2805(b)(1)(B), , 130 Stat. 2714, provided that: “The amendment made by subparagraph (A) [amending this section] shall apply with respect to notifications provided during fiscal year 2017 or any succeeding fiscal year.”
Credits
2006–2023 · 7 acts
- 2006Added Pub. L. 109–364, div. B, title XXVIII, § 2851(a)(1), , 120 Stat. 2493
- 2016amended Pub. L. 114–328, div. B, title XXVIII, § 2805(a)(1), (b)(1)(A), (2), , 130 Stat. 2713, 2714
- 2017Pub. L. 115–91, div. B, title XXVIII, §§ 2801(e)(1), 2831(c)(1), , 131 Stat. 1845, 1857
- 2018Pub. L. 115–232, div. A, title X, § 1081(a)(29), , 132 Stat. 1985
- 2021Pub. L. 116–283, div. B, title XXVIII, §§ 2805(a), 2823(b), , 134 Stat. 4321, 4333
- 2021Pub. L. 117–81, div. B, title XXVIII, § 2804, , 135 Stat. 2188
- 2023Pub. L. 118–31, div. B, title XXVIII, § 2809, , 137 Stat. 746.
Show as published
(Added Pub. L. 109–364, div. B, title XXVIII, § 2851(a)(1), , 120 Stat. 2493; amended Pub. L. 114–328, div. B, title XXVIII, § 2805(a)(1), (b)(1)(A), (2), , 130 Stat. 2713, 2714; Pub. L. 115–91, div. B, title XXVIII, §§ 2801(e)(1), 2831(c)(1), , 131 Stat. 1845, 1857; Pub. L. 115–232, div. A, title X, § 1081(a)(29), , 132 Stat. 1985; Pub. L. 116–283, div. B, title XXVIII, §§ 2805(a), 2823(b), , 134 Stat. 4321, 4333; Pub. L. 117–81, div. B, title XXVIII, § 2804, , 135 Stat. 2188; Pub. L. 118–31, div. B, title XXVIII, § 2809, , 137 Stat. 746.)