§ 6312. Independent acquisition project reviews of capital assets acquisition projects

Statutory text

(a)

Reviews.—

The appropriate head shall ensure that an independent entity conducts reviews of each capital assets acquisition project as the project moves toward the approval of each of critical decision 0, critical decision 1, and critical decision 2 in the acquisition process.

(b)

Pre-critical Decision 1 Reviews.—

In addition to any other matters, with respect to each review of a capital assets acquisition project under subsection (a) that has not reached critical decision 1 approval in the acquisition process, such review shall include—

(1)

a review using best practices of the analysis of alternatives for the project; and

(2)

identification of any deficiencies in such analysis of alternatives for the appropriate head to address.

(c)

Independent Entities.—

The appropriate head shall ensure that each review of a capital assets acquisition project under subsection (a) is conducted by an independent entity with the appropriate expertise with respect to the project and the stage in the acquisition process of the project.

(d)

Definitions.—

In this section:

(1)

The term “acquisition process” means the acquisition process for a project, as defined in Department of Energy Order 413.3B (relating to project management and project management for the acquisition of capital assets), or a successor order.

(2)

The term “appropriate head” means—

(A)

the Administrator, with respect to capital assets acquisition projects of the Administration; and

(B)

the Assistant Secretary of Energy for Environmental Management, with respect to capital assets acquisition projects of the Office of Environmental Management.

(3)

The term “capital assets acquisition project” means a project—

(A)

the total project cost of which is more than $500,000,000; and

(B)

that is covered by Department of Energy Order 413.3B, or a successor order, for the acquisition of capital assets for atomic energy defense activities.

Legislative history

Reconstructed from this section’s Code source credit and amendment notes, resolved against the local Statutes at Large. Editorial notes are evidence, not the law that made the change.

  1. Pub. L. 119–60 div. C title XXXI § 3111(a) · 139 Stat. 1439

    Enacted · 10 U.S.C. § 6312

    (Added Pub. L. 119–60, div. C, title XXXI, § 3111(a), Dec. 18, 2025, 139 Stat. 1439.)

    Unresolved: Pub. L. 119–60 was not found in the local Statutes at Large index.

    Source evidence

    Code source credit
    (Added Pub. L. 119–60, div. C, title XXXI, § 3111(a), Dec. 18, 2025, 139 Stat. 1439.)

0 of 1 references resolved to an enrolled provision · 1 unresolved

Editorial Notes

Prior Provisions

Provisions similar to those in this section were contained in section 2773 of Title 50, War and National Defense, prior to repeal by Pub. L. 119–60, § 3111(b)(1).

Credits

(Added Pub. L. 119–60, div. C, title XXXI, § 3111(a), , 139 Stat. 1439.)