§ 824s. Transmission infrastructure investment

Statutory text

(a)

Rulemaking requirement

Not later than 1 year after , the Commission shall establish, by rule, incentive-based (including performance-based) rate treatments for the transmission of electric energy in interstate commerce by public utilities for the purpose of benefitting consumers by ensuring reliability and reducing the cost of delivered power by reducing transmission congestion.

(b)

Contents

The rule shall—

(1)

promote reliable and economically efficient transmission and generation of electricity by promoting capital investment in the enlargement, improvement, maintenance, and operation of all facilities for the transmission of electric energy in interstate commerce, regardless of the ownership of the facilities;

(2)

provide a return on equity that attracts new investment in transmission facilities (including related transmission technologies);

(3)

encourage deployment of transmission technologies and other measures to increase the capacity and efficiency of existing transmission facilities and improve the operation of the facilities; and

(4)

allow recovery of—

(A)

all prudently incurred costs necessary to comply with mandatory reliability standards issued pursuant to section 824o of this title; and

(B)

all prudently incurred costs related to transmission infrastructure development pursuant to section 824p of this title.

(c)

Incentives

In the rule issued under this section, the Commission shall, to the extent within its jurisdiction, provide for incentives to each transmitting utility or electric utility that joins a Transmission Organization. The Commission shall ensure that any costs recoverable pursuant to this subsection may be recovered by such utility through the transmission rates charged by such utility or through the transmission rates charged by the Transmission Organization that provides transmission service to such utility.

(d)

Just and reasonable rates

All rates approved under the rules adopted pursuant to this section, including any revisions to the rules, are subject to the requirements of sections 824d and 824e of this title that all rates, charges, terms, and conditions be just and reasonable and not unduly discriminatory or preferential.

Legislative history

Reconstructed from this section’s Code source credit and amendment notes, resolved against the local Statutes at Large. Editorial notes are evidence, not the law that made the change.

  1. Electricity Modernization Act of 2005

    Pub. L. 109–58 title XII § 1241 · 119 Stat. 594

    Enacted · 16 U.S.C. § 824s

    (June 10, 1920, ch. 285, pt. II, § 219, as added Pub. L. 109–58, title XII, § 1241, Aug. 8, 2005, 119 Stat. 961.)

    Source evidence

    Code source credit
    (June 10, 1920, ch. 285, pt. II, § 219, as added Pub. L. 109–58, title XII, § 1241, Aug. 8, 2005, 119 Stat. 961.)

    Enacted provision · exact public law section
    SEC. 1241. TRANSMISSION INFRASTRUCTURE INVESTMENT.   Part II of the Federal Power Act (16 U.S.C. 824 et seq.) is amended by adding at the end the following: “SEC. 219. TRANSMISSION INFRASTRUCTURE INVESTMENT. “(a) Rulemaking Requirement.— Not later than 1 year after the date of enactment of this section, the Commission shall establish, by rule, incentive-based (including performance-based) rate treatments for the transmission of electric energy in interstate commerce by public utilities for the purpose of benefitting consumers by ensuring reliability and reducing the cost of delivered power by reducing transmission congestion. “(b) Contents.— The rule shall— “(1) promote reliable and economically efficient transmission and generation of electricity by promoting capital investment in the enlargement, improvement, maintenance, and operation of all facilities for the transmission of electric energy in interstate commerce, regardless of the ownership of the facilities; “(2) provide a return on equity that attracts new investment in transmission facilities (including related transmission technologies); “(3) encourage deployment of transmission technologies and other measures to increase the capacity and efficiency of existing transmission facilities and improve the operation of the facilities; and “(4) allow recovery of— “(A) all prudently incurred costs necessary to comply with mandatory reliability standards issued pursuant to section 215; and “(B) all prudently incurred costs related to transmission infrastructure development pursuant to section 216. “(c) Incentives.— In the rule issued under this section, the Commission shall, to the extent within its jurisdiction, provide for incentives to each transmitting utility or electric utility that joins a Transmission Organization. The Commission shall ensure that any costs recoverable pursuant to this subsection may be recovered by such utility through the transmission rates charged by such utility or through the transmission rates charged by the Transmission Organization that provides transmission service to such utility. “(d) Just and Reasonable Rates.— All rates approved under the rules adopted pursuant to this section, including any revisions to the rules, are subject to the requirements of sections 205 and 206 that all rates, charges, terms, and conditions be just and reasonable and not unduly discriminatory or preferential.” .

1 of 1 references resolved to an enrolled provision

Credits

(June 10, 1920, ch. 285, pt. II, § 219, as added Pub. L. 109–58, title XII, § 1241, , 119 Stat. 961.)

Parsed from the official OLRC USLM XML in data/usc_all/usc16.xml · release point 119-108 · OLRC build 2026-07-16

USLM identifier /us/usc/t16/s824s