§ 838c. Acquisition by condemnation of transmission facilities

Statutory text

(a)

Approval by Congress; exceptions

Unless specifically authorized by Act of Congress, the Administrator shall not expend funds made available under this chapter, other than funds specifically appropriated by the Congress for such purpose, to acquire any operating transmission facility by condemnation: Provided, That this provision shall not restrict the acquisition of the right to cross such a facility by condemnation.

(b)

Notice of request for approval for construction or condemnation to contracting or interconnected entities in Pacific Northwest

At least sixty days prior to the time a request for approval or authority under this section or section 838b of this title is sent to Congress, the Administrator shall give notice of such request to entities in the Pacific Northwest with which the Administrator has power sales or exchange contracts or transmission contracts or which have a transmission interconnection with the Federal transmission system.

Legislative history

Reconstructed from this section’s Code source credit and amendment notes, resolved against the local Statutes at Large. Editorial notes are evidence, not the law that made the change.

  1. Federal Columbia River Transmission System Act

    Pub. L. 93–454 § 5 · 88 Stat. 1376

    Enacted · 16 U.S.C. § 838c

    (Pub. L. 93–454, § 5, Oct. 18, 1974, 88 Stat. 1377.)

    Source evidence

    Code source credit
    (Pub. L. 93–454, § 5, Oct. 18, 1974, 88 Stat. 1377.)

    Enacted provision · exact public law section
    Sec. 5. (a) Unless specifically authorized by Act of Congress, the 16 USC 838c. Administrator shall not expend funds made available under this Act, other than funds specifically appropriated by the Congress for such purpose, to acquire any operating transmission facility by condemnation: Provided, That this provision shall not restrict the acquisition of the right to cross such a facility by condemnation. (b) At least sixty days prior to the time a request for approval or authority under section 4 or 5 of this Act is sent to Congress, the Administrator shall give notice of such request to entities in the Pacific Northwest with which the Administrator has power sales or exchange contracts or transmission contracts or which have a transmission interconnection with the Federal transmission system.

1 of 1 references resolved to an enrolled provision

Statutory Notes and Related Subsidiaries

Transfer of Functions

Functions of Secretary of the Interior with respect to Bonneville Power Administration transferred to Secretary of Energy by section 7152(a)(1)(D), (2) of Title 42, The Public Health and Welfare, with Bonneville Power Administration to be preserved as a distinct organizational entity within Department of Energy and headed by an Administrator.

Credits

(Pub. L. 93–454, § 5, , 88 Stat. 1377.)

Parsed from the official OLRC USLM XML in data/usc_all/usc16.xml · release point 119-108 · OLRC build 2026-07-16