§ 3552. Protests by interested parties concerning procurement actions

Statutory text

(a)

A protest concerning an alleged violation of a procurement statute or regulation shall be decided by the Comptroller General if filed in accordance with this subchapter.

(b)
(1)

In the case of an agency tender official who is an interested party under section 3551(2)(B) of this title, the official may file a protest in connection with the public-private competition for which the official is an interested party. At the request of a majority of the employees of the Federal agency who are engaged in the performance of the activity or function subject to such public-private competition, the official shall file a protest in connection with such public-private competition unless the official determines that there is no reasonable basis for the protest.

(2)

The determination of an agency tender official under paragraph (1) whether or not to file a protest is not subject to administrative or judicial review. An agency tender official shall provide written notification to Congress whenever the official makes a determination under paragraph (1) that there is no reasonable basis for a protest.

Legislative history

Reconstructed from this section’s Code source credit and amendment notes, resolved against the local Statutes at Large. Editorial notes are evidence, not the law that made the change.

  1. Competition in Contracting Act of 1984

    Pub. L. 98–369 div. B title VII § 2741(a) · 98 Stat. 494

    Enacted · 31 U.S.C. § 3552

    Added Pub. L. 98–369, div. B, title VII, § 2741(a), July 18, 1984, 98 Stat. 1199

    Source evidence

    Code source credit
    Added Pub. L. 98–369, div. B, title VII, § 2741(a), July 18, 1984, 98 Stat. 1199

    Enacted provision · exact public law section
    (a) Chapter 35 of title 31, United States Code, is amended by adding at the end thereof the following new subchapter: “SUBCHAPTER V— PROCUREMENT PROTEST SYSTEM “§ 3551. Definitions “In this subchapter— “(1) ‘protest’ means a written objection by an interested party to a solicitation by an executive agency for bids or proposals for a proposed contract for the procurement of property or services or a written objection by an interested party to a proposed award or the award of such a contract; “(2) ‘interested party’, with respect to a contract or proposed contract described in paragraph (1), means an actual or prospective bidder or offeror whose direct economic interest would be affected by the award of the contract or by failure to award the contract; and “(3) ‘Federal agency’ has the meaning given such term by section 3 of the Federal Property and Administrative Services Act of 1949 (40 U.S.C. 472). “§ 3552. Protests by interested parties concerning procurement actions “A protest concerning an alleged violation of a procurement statute or regulation shall be decided by the Comptroller General if filed in accordance with this subchapter. An interested party who has filed a protest under section 111(h) of the Federal Property and Administrative Services Act of 1949 (40 U.S.C. 759(h)) with respect to a procurement or proposed procurement may not file a protest with respect to Ante, p. 1182. that procurement under this subchapter. “§3553. Review of protests; effect on contracts pending decision “(a) Under procedures prescribed under section 3555 of this title, the Comptroller General shall decide a protest submitted to the Comptroller General by an interested party. “(b) (1) Within one working day of the receipt of a protest, the Comptroller General shall notify the Federal agency involved of the protest. “(2) Except as provided in paragraph (3) of this subsection, a Federal agency receiving a notice of a protested procurement under paragraph (1) of this subsection shall submit to the Comptroller General a complete report (including all relevant documents) on the protested procurement— “(A) within 25 working days from the date of the agency’s receipt of that notice; “(B) if the Comptroller General, upon a showing by the Federal agency, determines (and states the reasons in writing) that the specific circumstances of the protest require a longer period, within the longer period determined by the Comptroller General; or “(C) in a case determined by the Comptroller General to be suitable for the express option under section 3554(a)(2) of this title, within 10 working days from the date of the Federal agency’s receipt of that determination. “(3) A Federal agency need not submit a report to the Comptroller General pursuant to paragraph (2) of this subsection if the agency is sooner notified by the Comptroller General that the protest concerned has been dismissed under section 3554(a)(3) of this title. “(c) (1) Except as provided in paragraph (2) of this subsection, a contract may not be awarded in any procurement after the Federal agency has received notice of a protest with respect to such procurement from the Comptroller General and while the protest is pending. “(2) The head of the procuring activity responsible for award of a contract may authorize the award of the contract (notwithstanding a protest of which the Federal agency has notice under this section)— “(A) upon a written finding that urgent and compelling circumstances which significantly affect interests of the United States will not permit waiting for the decision of the Comptroller General under this subchapter; and “(B) after the Comptroller General is advised of that finding. “(3) A finding may not be made under paragraph (2)(A) of this subsection unless the award of the contract is otherwise likely to occur within 30 days thereafter. “(d) (1) If a Federal agency receives notice of a protest under this section after the contract has been awarded but within 10 days of the date of the contract award, the Federal agency (E)(cept as provided under paragraph (2)) shall, upon receipt of that notice, immediately direct the contractor to cease performance under the contract and to suspend any related activities that may result in additional obligations being incurred by the United States under that contract. Performance of the contract may not be resumed while the protest is pending. “(2) The head of the procuring activity responsible for award of a contract may authorize the performance of the contract (notwithstanding a protest of which the Federal agency has notice under this section)— “(A) upon a written finding— “(i) that performance of the contract is in the best interests of the United States; or “(ii) that urgent and compelling circumstances that significantly affect interests of the United States will not permit waiting for the decision of the Comptroller General concerning the protest; and “(B) after the Comptroller General is notified of that finding. “(e) The authority of the head of the procuring activity to make findings and to authorize the award and performance of contracts under subsections (c) and (d) of this section may not be delegated. “(f) Within such deadlines as the Comptroller General prescribes, upon request each Federal agency shall provide to an interested party any document relevant to a protested procurement action (including the report required by subsection (b)(2) of this section) that would not give that party a competitive advantage and that the party is otherwise authorized by law to receive. “§ 3554. Decisions on protests “(a) (1) To the maximum extent practicable, the Comptroller General shall provide for the inexpensive and expeditious resolution of protests under this subchapter. Except as provided under paragraph (2) of this subsection, the Comptroller General shall issue a final decision concerning a protest within 90 working days from the date the protest is submitted to the Comptroller General unless the Comptroller General determines and states in writing the reasons that the specific circumstances of the protest require a longer period. “(2) The Comptroller General shall, by regulation prescribed pursuant to section 3555 of this title, establish an express option for Post, p. 1202. deciding those protests which the Comptroller General determines suitable for resolution within 45 calendar days from the date the protest is submitted. “(3) The Comptroller General may dismiss a protest that the Comptroller General determines is frivolous or which, on its face, does not state a valid basis for protest. “(b) (1) With respect to a solicitation for a contract, or a proposed award or the award of a contract, protested under this subchapter, the Comptroller General may determine whether the solicitation, proposed award, or award complies with statute and regulation. If the Comptroller General determines that the solicitation, proposed award, or award does not comply with a statute or regulation, the Comptroller General shall recommend that the Federal agency— “(A) refrain from exercising any of its options under the contract; “(B) recompete the contract immediately; “(C) issue a new solicitation; “(D) terminate the contract; “(E) award a contract consistent with the requirements of such statute and regulation; “(F) implement any combination of recommendations under clauses (A), (B), (C), (D), and (E); or “(G) implement such other recommendations as the Comptroller General determines to be necessary in order to promote compliance with procurement statutes and regulations. “(2) If the head of the procuring activity responsible for a contract makes a finding under section 3553(d)(2)(A)(i) of this title, the Comp- Ante, p. 1200. troller General shall make recommendations under this subsection without regard to any cost or disruption from terminating, recompeting, or reawarding the contract. “(c) (1) If the Comptroller General determines that a solicitation for a contract or a proposed award cr the award of a contract does not comply with a statute or regulation, the Comptroller General may declare an appropriate interested party to be entitled to the costs of— “(A) filing and pursuing the protest, including reasonable attorneys’ fees; and “(B) bid and proposal preparation. “(2) Monetary awards to which a party is declared to be entitled under paragraph (1) of this subsection shall be paid promptly by the Federal agency concerned out of funds available to or for the use of the Federal agency for the procurement of property and services. “(d) Each decision of the Comptroller General under this subchapter shall be signed by the Comptroller General or a designee for that purpose. A copy of the decision shall be made available to the interested parties, the head of the procuring activity responsible for the solicitation, proposed award, or award of the contract, and the senior procurement executive of the Federal agency involved. “(e) (1) The head of the procuring activity responsible for the solicitation, proposed award, or award of the contract shall report to the Comptroller General, if the Federal agency has not fully implemented those recommendations within 60 days of receipt of the Comptroller General’s recommendations under subsection (b) of this section. “(2) Not later than January 31 of each year, the Comptroller General shall transmit to Congress a report describing each instance in which a Federal agency did not fully implement the Comptroller General’s recommendations during the preceding fiscal year. “§ 3555. Regulations; authority of Comptroller General to verify assertions “(a) Not later than January 15, 1985, the Comptroller General shall prescribe such procedures as may be necessary to the expeditious decision of protests under this subchapter, including procedures for accelerated resolution of protests under the express option Ante, p. 1201. authorized by section 3554(a)(2) of this title. Such procedures shall provide that the protest process may not be delayed by the failure of a party to make a filing within the time provided for the filing. “(b) The Comptroller General may use any authority available 31 USC 701 et seq. under chapter 7 of this title and this chapter to verify assertions made by parties in protests under this subchapter. “§ 3556. Nonexclusivity of remedies; matters included in agency record “This subchapter does not give the Comptroller General exclusive jurisdiction over protests, and nothing contained in this subchapter shall affect the right of any interested party to file a protest with the contracting agency or to file an action in a district court of the United States or the United States Claims Court. In any such action based on a procurement or proposed procurement with respect to which a protest has been filed under this subchapter, the reports Ante, p. 1200. required by sections 3553(b)(2) and 3554(e)(1) of this title with respect to such procurement or proposed procurement and any decision or recommendation of the Comptroller General under this subchapter with respect to such procurement or proposed procurement shall be considered to be part of the agency record subject to review.”.

  2. Pub. L. 103–272 § 4(f)(1)(L) · 108 Stat. 745

    1. Amended · 31 U.S.C. § 3552

      Pub. L. 103–272 and Pub. L. 103–355 amended section identically

    2. Substituted · 31 U.S.C. § 3552

      Pub. L. 103–272 and Pub. L. 103–355 substituting “section 111(f)” for “section 111(h)”

    3. Substituted · 31 U.S.C. § 3552

      Pub. L. 103–272 and Pub. L. 103–355 substituting “759(f)” for “759(h)”

    Source evidence

    Code amendment note
    Pub. L. 103–272 and Pub. L. 103–355 amended section identically, substituting “section 111(f)” for “section 111(h)” and “759(f)” for “759(h)”.

    Enacted provision · exact public law section
    (L) In section 3552, strike “section 111(h)” and “(40 U.S.C. 759(h))” and substitute “section 111(f)” and “(40 U.S.C. 759(f))”, respectively.

  3. National Defense Authorization Act for Fiscal Year 1996

    Pub. L. 104–106 div. E title LVI § 5603 · 110 Stat. 186

    Struck · 31 U.S.C. § 3552

    Pub. L. 104–106 struck out at end “An interested party who has filed a protest under section 111(f) of the Federal Property and Administrative Services Act of 1949 (40 U.S.C. 759(f)) with respect to a procurement or proposed procurement may not file a protest with respect to that procurement under this subchapter.”

    Source evidence

    Code amendment note
    Pub. L. 104–106 struck out at end “An interested party who has filed a protest under section 111(f) of the Federal Property and Administrative Services Act of 1949 (40 U.S.C. 759(f)) with respect to a procurement or proposed procurement may not file a protest with respect to that procurement under this subchapter.”

    Enacted provision · exact public law section
    SEC. 5603. AMENDMENT TO TITLE 31, UNITED STATES CODE. Section 3552 of title 31, United States Code, is amended by striking out the second sentence.

  4. Ronald W. Reagan National Defense Authorization Act for Fiscal Year 2005

    Pub. L. 108–375 div. A title III § 326(b) · 118 Stat. 1811

    1. Amended · 31 U.S.C. § 3552

      Pub. L. 108–375 designated existing provisions as subsec. (a)

    2. Added · 31 U.S.C. § 3552

      Pub. L. 108–375 added subsec. (b)

    Source evidence

    Code amendment note
    Pub. L. 108–375 designated existing provisions as subsec. (a) and added subsec. (b).

    Enacted provision · exact public law section
    (b) Filing of Protest on Behalf of Federal Employees.— Section 3552 of such title is amended— (1) by inserting “(a)” before “A protest”; and (2) by adding at the end the following new subsection: “(b) (1) In the case of an agency tender official who is an interested party under section 3551(2)(B) of this title, the official may file a protest in connection with the public-private competition for which the official is an interested party. At the request of a majority of the employees of the Federal agency who are engaged in the performance of the activity or function subject to such public-private competition, the official shall file a protest in connection with such public-private competition unless the official determines that there is no reasonable basis for the protest. “(2) The determination of an agency tender official under paragraph (1) whether or not to file a protest is not subject to administrative or judicial review. An agency tender official shall provide written notification to Congress whenever the official makes a determination under paragraph (1) that there is no reasonable basis for a protest.” .

    Effective date note
    Amendment by Pub. L. 108–375 applicable to protests filed under this subchapter that relate to studies initiated under Office of Management and Budget Circular A–76 on or after the end of the 90-day period beginning on Oct. 28, 2004, see section 326(d) of Pub. L. 108–375, set out as a note under section 3551 of this title.

7 of 7 references resolved to an enrolled provision

Editorial Notes

Amendments1994–2004 · 3 rounds

2004

Pub. L. 108–375 designated existing provisions as subsec. (a) and added subsec. (b).

1996

Pub. L. 104–106 struck out at end “An interested party who has filed a protest under section 111(f) of the Federal Property and Administrative Services Act of 1949 (40 U.S.C. 759(f)) with respect to a procurement or proposed procurement may not file a protest with respect to that procurement under this subchapter.”

1994

Pub. L. 103–272 and Pub. L. 103–355 amended section identically, substituting “section 111(f)” for “section 111(h)” and “759(f)” for “759(h)”.

Statutory Notes and Related Subsidiaries

Effective Date of 2004 Amendment

Amendment by Pub. L. 108–375 applicable to protests filed under this subchapter that relate to studies initiated under Office of Management and Budget Circular A–76 on or after the end of the 90-day period beginning on , see section 326(d) of Pub. L. 108–375, set out as a note under section 3551 of this title.

Effective Date of 1996 Amendment

Amendment by Pub. L. 104–106 effective 180 days after , see section 5701 of Pub. L. 104–106, div. E, title LVII, , 110 Stat. 702.

Effective Date of 1994 Amendment

For effective date and applicability of amendment by Pub. L. 103–355, see section 10001 of Pub. L. 103–355, set out as a note under section 8752 of Title 10, Armed Forces.

Effective Date

Section applicable with respect to any protest filed after , see section 2751(b) of Pub. L. 98–369, set out as a note under section 4751 of Title 10, Armed Forces.

Construction of 2004 Amendment

Amendment by Pub. L. 108–375 not to be construed to authorize the use of a protest under this subchapter with regard to a decision made by an agency tender official, see section 326(e) of Pub. L. 108–375, set out as a note under section 3551 of this title.

Credits

1984–2004 · 5 acts
  1. 1984Added Pub. L. 98–369, div. B, title VII, § 2741(a), , 98 Stat. 1199
  2. 1994amended Pub. L. 103–272, § 4(f)(1)(L), , 108 Stat. 1362
  3. 1994Pub. L. 103–355, title X, § 10005(d), , 108 Stat. 3408
  4. 1996Pub. L. 104–106, div. E, title LVI, § 5603, , 110 Stat. 700
  5. 2004Pub. L. 108–375, div. A, title III, § 326(b), , 118 Stat. 1848.
Show as published

(Added Pub. L. 98–369, div. B, title VII, § 2741(a), , 98 Stat. 1199; amended Pub. L. 103–272, § 4(f)(1)(L), , 108 Stat. 1362; Pub. L. 103–355, title X, § 10005(d), , 108 Stat. 3408; Pub. L. 104–106, div. E, title LVI, § 5603, , 110 Stat. 700; Pub. L. 108–375, div. A, title III, § 326(b), , 118 Stat. 1848.)

Parsed from the official OLRC USLM XML in data/usc_all/usc31.xml · release point 119-108 · OLRC build 2026-09-16

USLM identifier /us/usc/t31/s3552