Title 33 — Navigation and Navigable Waters
Chapter 40 — Oil Pollution
§ 2717. Litigation, jurisdiction, and venue
Statutory text
Review of regulations
Review of any regulation promulgated under this Act may be had upon application by any interested person only in the Circuit Court of Appeals of the United States for the District of Columbia. Any such application shall be made within 90 days from the date of promulgation of such regulations. Any matter with respect to which review could have been obtained under this subsection shall not be subject to judicial review in any civil or criminal proceeding for enforcement or to obtain damages or recovery of response costs.
Jurisdiction
Except as provided in subsections (a) and (c), the United States district courts shall have exclusive original jurisdiction over all controversies arising under this Act, without regard to the citizenship of the parties or the amount in controversy. Venue shall lie in any district in which the discharge or injury or damages occurred, or in which the defendant resides, may be found, has its principal office, or has appointed an agent for service of process. For the purposes of this section, the Fund shall reside in the District of Columbia.
State court jurisdiction
A State trial court of competent jurisdiction over claims for removal costs or damages, as defined under this Act, may consider claims under this Act or State law and any final judgment of such court (when no longer subject to ordinary forms of review) shall be recognized, valid, and enforceable for all purposes of this Act.
Assessment and collection of tax
The provisions of subsections (a), (b), and (c) shall not apply to any controversy or other matter resulting from the assessment or collection of any tax, or to the review of any regulation promulgated under title 26.
Savings provision
Nothing in this subchapter shall apply to any cause of action or right of recovery arising from any incident which occurred prior to . Such claims shall be adjudicated pursuant to the law applicable on the date of the incident.
Period of limitations
Damages
Except as provided in paragraphs (3) and (4), an action for damages under this Act shall be barred unless the action is brought within 3 years after—
the date on which the loss and the connection of the loss with the discharge in question are reasonably discoverable with the exercise of due care, or
in the case of natural resource damages under section 2702(b)(2)(A) of this title, the date of completion of the natural resources damage assessment under section 2706(c) of this title.
Removal costs
An action for recovery of removal costs referred to in section 2702(b)(1) of this title must be commenced within 3 years after completion of the removal action. In any such action described in this subsection, the court shall enter a declaratory judgment on liability for removal costs or damages that will be binding on any subsequent action or actions to recover further removal costs or damages. Except as otherwise provided in this paragraph, an action may be commenced under this subchapter for recovery of removal costs at any time after such costs have been incurred.
Contribution
No action for contribution for any removal costs or damages may be commenced more than 3 years after—
the date of judgment in any action under this Act for recovery of such costs or damages, or
the date of entry of a judicially approved settlement with respect to such costs or damages.
Subrogation
No action based on rights subrogated pursuant to this Act by reason of payment of a claim may be commenced under this Act more than 3 years after the date of payment of such claim.
Commencement
The time limitations contained herein shall not begin to run—
against a minor until the earlier of the date when such minor reaches 18 years of age or the date on which a legal representative is duly appointed for such minor, or
against an incompetent person until the earlier of the date on which such incompetent’s incompetency ends or the date on which a legal representative is duly appointed for such incompetent.
Timing of review
Before the date of completion of a removal action, no person may bring an action under this Act, section 1321 of this title, or chapter 7 of title 5 challenging any decision relating to such removal action that is made by an on-scene coordinator appointed under the National Contingency Plan.
Legislative history
Reconstructed from this section’s Code source credit and amendment notes, resolved against the local Statutes at Large. Editorial notes are evidence, not the law that made the change.
Oil Pollution Act of 1990
Pub. L. 101–380 title I § 1017 · 104 Stat. 484
Enacted · 33 U.S.C. § 2717
Pub. L. 101–380, title I, § 1017, Aug. 18, 1990, 104 Stat. 504
Source evidence
Code source credit
Pub. L. 101–380, title I, § 1017, Aug. 18, 1990, 104 Stat. 504Enacted provision · exact public law section
SEC. 1017. LITIGATION. JURISDICTION, AND VENUE. (a) Review of Regulations.— Review of any regulation promulgated under this Act may be had upon application by any interested person only in the Circuit Court of Appeals of the United States for the District of Columbia. Any such application shall be made within 90 days from the date of promulgation of such regulations. Any matter with respect to which review could have been obtained under this subsection shall not be subject to judicial review in any civil or criminal proceeding for enforcement or to obtain damages or recovery of response costs. (b) Jurisdiction.— Except as provided in subsections (a) and (c), the United States district courts shall have exclusive original jurisdiction over all controversies arising under this Act, without regard to the citizenship of the parties or the amount in controversy. Venue shall lie in any district in which the discharge or injury or damages occurred, or in which the defendant resides, may be found, has its principal office, or has appointed an agent for service of process. For the purposes of this section, the Fund shall reside in the District of Columbia. (c) State Court Jurisdiction.— A State trial court of competent jurisdiction over claims for removal costs or damages, as defined under this Act, may consider claims under this Act or State law and any final judgment of such court (when no longer subject to ordinary forms of review) shall be recognized, valid, and enforceable for all purposes of this Act. (d) Assessment and Collection of Tax.— The provisions of subsections (a), (b), and (c) shall not apply to any controversy or other matter resulting from the assessment or collection of any tax, or to the review of any regulation promulgated under the Internal Revenue Code of 1986. (e) Savings Provision.— Nothing in this title shall apply to any cause of action or right of recovery arising from any incident which occurred prior to the date of enactment of this title. Such claims shall be adjudicated pursuant to the law applicable on the date of the incident. (f) Period of Limitations.— (1) Damages.— Except as provided in paragraphs (3) and (4), an action for damages under this Act shall be barred unless the action is brought within 3 years after— (A) the date on which the loss and the connection of the loss with the discharge in question are reasonably discoverable with the exercise of due care, or (B) in the case of natural resource damages under section l002(b)(2)(A), the date of completion of the natural resources damage assessment under section 1006(c). (2) Removal costs.— An action for recovery of removal costs referred to in section 1002(b)(1) must be commenced within 3 years after completion of the removal action. In any such action described in this subsection, the court shall enter a declaratory judgment on liability for removal costs or damages that will be binding on any subsequent action or actions to recover further removal costs or damages. Except as otherwise provided in this paragraph, an action may be commenced under this title for recovery of removal costs at any time after such costs have been incurred. (3) Contribution.— No action for contribution for any removal costs or damages may be commenced more than 3 years after— (A) the date of judgment in any action under this Act for recovery of such costs or damages, or (B) the date of entry of a judicially approved settlement with respect to such costs or damages. (4) Subrogation.— No action based on rights subrogated pursuant to this Act by reason of payment of a claim may be commenced under this Act more than 3 years after the date of payment of such claim. (5) Commencement.— The time limitations contained herein shall not begin to run— (A) against a minor until the earlier of the date when such minor reaches 18 years of age or the date on which a legal representative is duly appointed for such minor, or (B) against an incompetent person until the earlier of the date on which such incompetent’s incompetency ends or the date on which a legal representative is duly appointed for such incompetent.Pub. L. 119–60 div. G title LXXIV § 7403 · 139 Stat. 1784
Added · 33 U.S.C. § 2717(g)
Pub. L. 119–60 added subsec. (g)
Unresolved: Pub. L. 119–60 was not found in the local Statutes at Large index.
Source evidence
Code amendment note
Subsec. (g). Pub. L. 119–60 added subsec. (g).
1 of 2 references resolved to an enrolled provision · 1 unresolved
Editorial Notes
References in Text
This Act, referred to in text, is Pub. L. 101–380, , 104 Stat. 484, known as the Oil Pollution Act of 1990, which is classified principally to this chapter. For complete classification of this Act to the Code, see Short Title note set out under section 2701 of this title and Tables.
Amendments
2025—Subsec. (g). Pub. L. 119–60 added subsec. (g).
Credits
1990–2025 · 2 acts
- 1990Pub. L. 101–380, title I, § 1017, , 104 Stat. 504
- 2025Pub. L. 119–60, div. G, title LXXIV, § 7403, , 139 Stat. 1784.
Show as published
(Pub. L. 101–380, title I, § 1017, , 104 Stat. 504; Pub. L. 119–60, div. G, title LXXIV, § 7403, , 139 Stat. 1784.)