Title 42 — The Public Health and Welfare
Part A–1 · Chapter 162 — Energy Infrastructure
§ 18715b. Interregional and offshore wind electricity transmission planning, modeling, and analysis
Statutory text
Appropriation
In addition to amounts otherwise available, there is appropriated to the Secretary for fiscal year 2022, out of any money in the Treasury not otherwise appropriated, $100,000,000, to remain available through , to carry out this section.
Use of funds
The Secretary shall use amounts made available under subsection (a)—
to pay expenses associated with convening relevant stakeholders to address the development of interregional electricity transmission and transmission of electricity that is generated by offshore wind; and
to conduct planning, modeling, and analysis regarding interregional electricity transmission and transmission of electricity that is generated by offshore wind, taking into account the local, regional, and national economic, reliability, resilience, security, public policy, and environmental benefits of interregional electricity transmission and transmission of electricity that is generated by offshore wind, including planning, modeling, and analysis, as the Secretary determines appropriate, pertaining to—
clean energy integration into the electric grid, including the identification of renewable energy zones;
the effects of changes in weather due to climate change on the reliability and resilience of the electric grid;
cost allocation methodologies that facilitate the expansion of the bulk power system;
the benefits of coordination between generator interconnection processes and transmission planning processes;
the effect of increased electrification on the electric grid;
power flow modeling;
the benefits of increased interconnections or interties between or among the Western Interconnection, the Eastern Interconnection, the Electric Reliability Council of Texas, and other interconnections, as applicable;
the cooptimization of transmission and generation, including variable energy resources, energy storage, and demand-side management;
the opportunities for use of nontransmission alternatives, energy storage, and grid-enhancing technologies;
economic development opportunities for communities arising from development of interregional electricity transmission and transmission of electricity that is generated by offshore wind;
evaluation of existing rights-of-way and the need for additional transmission corridors; and
a planned national transmission grid, which would include a networked transmission system to optimize the existing grid for interconnection of offshore wind farms.
Legislative history
Reconstructed from this section’s Code source credit and amendment notes, resolved against the local Statutes at Large. Editorial notes are evidence, not the law that made the change.
Pub. L. 117–169 title V § 50153 · 136 Stat. 1818
Enacted · 42 U.S.C. § 18715b
(Pub. L. 117–169, title V, § 50153, Aug. 16, 2022, 136 Stat. 2048.)
Source evidence
Code source credit
(Pub. L. 117–169, title V, § 50153, Aug. 16, 2022, 136 Stat. 2048.)Enacted provision · exact public law section
SEC. 50153. INTERREGIONAL AND OFFSHORE WIND ELECTRICITY TRANSMISSION PLANNING, MODELING, AND ANALYSIS. (a) Appropriation.— In addition to amounts otherwise available, there is appropriated to the Secretary for fiscal year 2022, out of any money in the Treasury not otherwise appropriated, $100,000,000, to remain available through September 30, 2031, to carry out this section. (b) Use of Funds.— The Secretary shall use amounts made available under subsection (a)— (1) to pay expenses associated with convening relevant stakeholders to address the development of interregional electricity transmission and transmission of electricity that is generated by offshore wind; and (2) to conduct planning, modeling, and analysis regarding interregional electricity transmission and transmission of electricity that is generated by offshore wind, taking into account the local, regional, and national economic, reliability, resilience, security, public policy, and environmental benefits of interregional electricity transmission and transmission of electricity that is generated by offshore wind, including planning, modeling, and analysis, as the Secretary determines appropriate, pertaining to— (A) clean energy integration into the electric grid, including the identification of renewable energy zones; (B) the effects of changes in weather due to climate change on the reliability and resilience of the electric grid; (C) cost allocation methodologies that facilitate the expansion of the bulk power system; (D) the benefits of coordination between generator interconnection processes and transmission planning processes; (E) the effect of increased electrification on the electric grid; (F) power flow modeling; (G) the benefits of increased interconnections or interties between or among the Western Interconnection, the Eastern Interconnection, the Electric Reliability Council of Texas, and other interconnections, as applicable; (H) the cooptimization of transmission and generation, including variable energy resources, energy storage, and demand-side management; (I) the opportunities for use of nontransmission alternatives, energy storage, and grid-enhancing technologies; (J) economic development opportunities for communities arising from development of interregional electricity transmission and transmission of electricity that is generated by offshore wind; (K) evaluation of existing rights-of-way and the need for additional transmission corridors; and (L) a planned national transmission grid, which would include a networked transmission system to optimize the existing grid for interconnection of offshore wind farms.
1 of 1 references resolved to an enrolled provision
Editorial Notes
Codification
Section was enacted as part of Pub. L. 117–169, and not as part of div. D of Pub. L. 117–58, which enacted this chapter.
Statutory Notes and Related Subsidiaries
Definition of “Secretary”
“Secretary” means the Secretary of Energy, see section 50111 of Pub. L. 117–169, set out as a note under section 17113b of this title.