Title 42 — The Public Health and Welfare
Part E · Chapter 162 — Energy Infrastructure
§ 18842. Model guidance for combined heat and power systems and waste heat to power systems
Statutory text
Definitions
In this section:
Additional services
The term “additional services” means the provision of supplementary power, backup or standby power, maintenance power, or interruptible power to an electric consumer by an electric utility.
Waste heat to power system
The term “waste heat to power system” means a system that generates electricity through the recovery of waste energy.
Other terms
Purpa
The terms “electric consumer”, “electric utility”, “interconnection service”, “nonregulated electric utility”, and “State regulatory authority” have the meanings given those terms in the Public Utility Regulatory Policies Act of 1978 (16 U.S.C. 2601 et seq.), within the meaning of title I of that Act (16 U.S.C. 2611 et seq.).
EPCA
The terms “combined heat and power system” and “waste energy” have the meanings given those terms in section 6341 of this title.
Review
In general
Not later than 180 days after , the Secretary, in consultation with the Federal Energy Regulatory Commission and other appropriate entities, shall review existing rules and procedures relating to interconnection service and additional services throughout the United States for electric generation with nameplate capacity up to 150 megawatts connecting at either distribution or transmission voltage levels to identify barriers to the deployment of combined heat and power systems and waste heat to power systems.
Inclusion
The review under this subsection shall include a review of existing rules and procedures relating to—
determining and assigning costs of interconnection service and additional services; and
ensuring adequate cost recovery by an electric utility for interconnection service and additional services.
Model guidance
In general
Not later than 18 months after , the Secretary, in consultation with the Federal Energy Regulatory Commission and other appropriate entities, shall issue model guidance for interconnection service and additional services for consideration by State regulatory authorities and nonregulated electric utilities to reduce the barriers identified under subsection (b)(1).
Current best practices
The model guidance issued under this subsection shall reflect, to the maximum extent practicable, current best practices to encourage the deployment of combined heat and power systems and waste heat to power systems while ensuring the safety and reliability of the interconnected units and the distribution and transmission networks to which the units connect, including—
relevant current standards developed by the Institute of Electrical and Electronic Engineers; and
model codes and rules adopted by—
States; or
associations of State regulatory agencies.
Factors for consideration
In establishing the model guidance under this subsection, the Secretary shall take into consideration—
the appropriateness of using standards or procedures for interconnection service that vary based on unit size, fuel type, or other relevant characteristics;
the appropriateness of establishing fast-track procedures for interconnection service;
the value of consistency with Federal interconnection rules established by the Federal Energy Regulatory Commission as of ;
the best practices used to model outage assumptions and contingencies to determine fees or rates for additional services;
the appropriate duration, magnitude, or usage of demand charge ratchets;
potential alternative arrangements with respect to the procurement of additional services, including—
contracts tailored to individual electric consumers for additional services;
procurement of additional services by an electric utility from a competitive market; and
waivers of fees or rates for additional services for small electric consumers; and
outcomes such as increased electric reliability, fuel diversification, enhanced power quality, and reduced electric losses that may result from increased use of combined heat and power systems and waste heat to power systems.
Legislative history
Reconstructed from this section’s Code source credit and amendment notes, resolved against the local Statutes at Large. Editorial notes are evidence, not the law that made the change.
Infrastructure Investment and Jobs Act
Pub. L. 117–58 div. D title V § 40556 · 135 Stat. 429
Enacted · 42 U.S.C. § 18842
(Pub. L. 117–58, div. D, title V, § 40556, Nov. 15, 2021, 135 Stat. 1078.)
Source evidence
Code source credit
(Pub. L. 117–58, div. D, title V, § 40556, Nov. 15, 2021, 135 Stat. 1078.)Enacted provision · exact public law section
SEC. 40556. MODEL GUIDANCE FOR COMBINED HEAT AND POWER SYSTEMS AND WASTE HEAT TO POWER SYSTEMS. (a) Definitions.— In this section: (1) Additional services.— The term “additional services” means the provision of supplementary power, backup or standby power, maintenance power, or interruptible power to an electric consumer by an electric utility. (2) Waste heat to power system.— The term “waste heat to power system” means a system that generates electricity through the recovery of waste energy. (3) Other terms.— (A) Purpa.— The terms “electric consumer”, “electric utility”, “interconnection service”, “nonregulated electric utility”, and “State regulatory authority” have the meanings given those terms in the Public Utility Regulatory Policies Act of 1978 (16 U.S.C. 2601 et seq.), within the meaning of title I of that Act (16 U.S.C. 2611 et seq.). (B) Epca.— The terms “combined heat and power system” and “waste energy” have the meanings given those terms in section 371 of the Energy Policy and Conservation Act (42 U.S.C. 6341). (b) Review.— (1) In general.— Not later than 180 days after the date of enactment of this Act, the Secretary, in consultation with the Federal Energy Regulatory Commission and other appropriate entities, shall review existing rules and procedures relating to interconnection service and additional services throughout the United States for electric generation with nameplate capacity up to 150 megawatts connecting at either distribution or transmission voltage levels to identify barriers to the deployment of combined heat and power systems and waste heat to power systems. (2) Inclusion.— The review under this subsection shall include a review of existing rules and procedures relating to— (A) Determination. determining and assigning costs of interconnection service and additional services; and (B) ensuring adequate cost recovery by an electric utility for interconnection service and additional services. (c) Model Guidance.— (1) In general.— Not later than 18 months after the date of enactment of this Act, the Secretary, in consultation with the Federal Energy Regulatory Commission and other appropriate entities, shall issue model guidance for interconnection service and additional services for consideration by State regulatory authorities and nonregulated electric utilities to reduce the barriers identified under subsection (b)(1). (2) Current best practices.— The model guidance issued under this subsection shall reflect, to the maximum extent practicable, current best practices to encourage the deployment of combined heat and power systems and waste heat to power systems while ensuring the safety and reliability of the interconnected units and the distribution and transmission networks to which the units connect, including— (A) relevant current standards developed by the Institute of Electrical and Electronic Engineers; and (B) model codes and rules adopted by— (i) States; or (ii) associations of State regulatory agencies. (3) Factors for consideration.— In establishing the model guidance under this subsection, the Secretary shall take into consideration— (A) the appropriateness of using standards or procedures for interconnection service that vary based on unit size, fuel type, or other relevant characteristics; (B) the appropriateness of establishing fast-track procedures for interconnection service; (C) the value of consistency with Federal interconnection rules established by the Federal Energy Regulatory Commission as of the date of enactment of this Act; (D) the best practices used to model outage assumptions and contingencies to determine fees or rates for additional services; (E) the appropriate duration, magnitude, or usage of demand charge ratchets; (F) potential alternative arrangements with respect to the procurement of additional services, including— (i) contracts tailored to individual electric consumers for additional services; (ii) procurement of additional services by an electric utility from a competitive market; and (iii) waivers of fees or rates for additional services for small electric consumers; and (G) outcomes such as increased electric reliability, fuel diversification, enhanced power quality, and reduced electric losses that may result from increased use of combined heat and power systems and waste heat to power systems.
1 of 1 references resolved to an enrolled provision
Editorial Notes
References in Text
The Public Utility Regulatory Policies Act of 1978, referred to in subsec. (a)(3)(A), is Pub. L. 95–617, , 92 Stat. 3117. Title I (§ 101 et seq.) of the Act enacted subchapters I to IV of chapter 46 (§ 2611 et seq.) of Title 16, Conservation, and section 6808 of this title, and amended sections 6802 to 6807 of this title. For complete classification of this Act to the Code, see Short Title note set out under section 2601 of Title 16 and Tables.
Statutory Notes and Related Subsidiaries
Wage Rate Requirements
For provisions relating to rates of wages to be paid to laborers and mechanics on projects for construction, alteration, or repair work funded under div. D or an amendment by div. D of Pub. L. 117–58, including authority of Secretary of Labor, see section 18851 of this title.
Credits
(Pub. L. 117–58, div. D, title V, § 40556, , 135 Stat. 1078.)