Skip to content

Title 42 — The Public Health and Welfare

Chapter 23 — Development and Control of Atomic Energy

§ 2239. Hearings and judicial review

Statutory text

(a)
(1)
(A)

In any proceeding under this chapter, for the granting, suspending, revoking, or amending of any license or construction permit, or application to transfer control, and in any proceeding for the issuance or modification of rules and regulations dealing with the activities of licensees, and in any proceeding for the payment of compensation, an award or royalties under sections 1 2183, 2187, 2236(c) or 2238 of this title, the Commission shall grant a hearing upon the request of any person whose interest may be affected by the proceeding, and shall admit any such person as a party to such proceeding. The Commission shall hold a hearing after thirty days’ notice and publication once in the Federal Register, on each application under section 2133 or 2134(b) of this title for a construction permit for a facility, and on any application under section 2134(c) of this title for a construction permit for a testing facility. In cases where such a construction permit has been issued following the holding of such a hearing, the Commission may, in the absence of a request therefor by any person whose interest may be affected, issue an operating license or an amendment to a construction permit or an amendment to an operating license without a hearing, but upon thirty days’ notice and publication once in the Federal Register of its intent to do so. The Commission may dispense with such thirty days’ notice and publication with respect to any application for an amendment to a construction permit or an amendment to an operating license upon a determination by the Commission that the amendment involves no significant hazards consideration.

(B)
(i)

Not less than 180 days before the date scheduled for initial loading of fuel into a plant by a licensee that has been issued a combined construction permit and operating license under section 2235(b) of this title, the Commission shall publish in the Federal Register notice of intended operation. That notice shall provide that any person whose interest may be affected by operation of the plant, may within 60 days request the Commission to hold a hearing on whether the facility as constructed complies, or on completion will comply, with the acceptance criteria of the license.

(ii)

A request for hearing under clause (i) shall show, prima facie, that one or more of the acceptance criteria in the combined license have not been, or will not be met, and the specific operational consequences of nonconformance that would be contrary to providing reasonable assurance of adequate protection of the public health and safety.

(iii)

After receiving a request for a hearing under clause (i), the Commission expeditiously shall either deny or grant the request. If the request is granted, the Commission shall determine, after considering petitioners’ prima facie showing and any answers thereto, whether during a period of interim operation, there will be reasonable assurance of adequate protection of the public health and safety. If the Commission determines that there is such reasonable assurance, it shall allow operation during an interim period under the combined license.

(iv)

The Commission, in its discretion, shall determine appropriate hearing procedures, whether informal or formal adjudicatory, for any hearing under clause (i), and shall state its reasons therefor.

(v)

The Commission shall, to the maximum possible extent, render a decision on issues raised by the hearing request within 180 days of the publication of the notice provided by clause (i) or the anticipated date for initial loading of fuel into the reactor, whichever is later. Commencement of operation under a combined license is not subject to subparagraph (A).

(2)
(A)

The Commission may issue and make immediately effective any amendment to an operating license or any amendment to a combined construction and operating license, upon a determination by the Commission that such amendment involves no significant hazards consideration, notwithstanding the pendency before the Commission of a request for a hearing from any person. Such amendment may be issued and made immediately effective in advance of the holding and completion of any required hearing. In determining under this section whether such amendment involves no significant hazards consideration, the Commission shall consult with the State in which the facility involved is located. In all other respects such amendment shall meet the requirements of this chapter.

(B)

The Commission shall periodically (but not less frequently than once every thirty days) publish notice of any amendments issued, or proposed to be issued, as provided in subparagraph (A). Each such notice shall include all amendments issued, or proposed to be issued, since the date of publication of the last such periodic notice. Such notice shall, with respect to each amendment or proposed amendment (i) identify the facility involved; and (ii) provide a brief description of such amendment. Nothing in this subsection shall be construed to delay the effective date of any amendment.

(C)

The Commission shall, during the ninety-day period following the effective date of this paragraph, promulgate regulations establishing (i) standards for determining whether any amendment to an operating license or any amendment to a combined construction and operating license involves no significant hazards consideration; (ii) criteria for providing or, in emergency situations, dispensing with prior notice and reasonable opportunity for public comment on any such determination, which criteria shall take into account the exigency of the need for the amendment involved; and (iii) procedures for consultation on any such determination with the State in which the facility involved is located.

(b)

The following Commission actions shall be subject to judicial review in the manner prescribed in chapter 158 of title 28 and chapter 7 of title 5:

(1)

Any final order entered in any proceeding of the kind specified in subsection (a).

(2)

Any final order allowing or prohibiting a facility to begin operating under a combined construction and operating license.

(3)

Any final order establishing by regulation standards to govern the Department of Energy’s gaseous diffusion uranium enrichment plants, including any such facilities leased to a corporation established under the USEC Privatization Act [42 U.S.C. 2297h et seq.].

(4)

Any final determination under section 2297f(c) of this title relating to whether the gaseous diffusion plants, including any such facilities leased to a corporation established under the USEC Privatization Act [42 U.S.C. 2297h et seq.], are in compliance with the Commission’s standards governing the gaseous diffusion plants and all applicable laws.

Footnotes

  1. 1 So in original. Probably should be “section”.

Legislative history

Reconstructed from this section’s Code source credit and amendment notes, resolved against the local Statutes at Large. Editorial notes are evidence, not the law that made the change.

  1. Pub. L. 83–724 · 68 Stat. 998

    Enacted · 42 U.S.C. § 2239

    Aug. 1, 1946, ch. 724, title I, § 189, as added Aug. 30, 1954, ch. 1073, § 1, 68 Stat. 955

    Source evidence

    Code source credit
    Aug. 1, 1946, ch. 724, title I, § 189, as added Aug. 30, 1954, ch. 1073, § 1, 68 Stat. 955

  2. Pub. L. 85–256 § 7 · 71 Stat. 576

    Changed · 42 U.S.C. § 2239(a)

    Pub. L. 85–256 required the Commission to hold a hearing after 30 days notice and publication once in the Federal Register on an application for a license for a facility or a testing facility

    Source evidence

    Code amendment note
    Subsec. (a). Pub. L. 85–256 required the Commission to hold a hearing after 30 days notice and publication once in the Federal Register on an application for a license for a facility or a testing facility.

    Enacted provision · exact public law section
    Sec. 7. Section 189 a. of the Atomic Energy Act of 1954, as 42 USC 2239. amended, is amended by adding the following sentence at the end thereof: “The Commission shall hold a hearing after thirty days Hearing. Publication in F.R. 42 USC 2133, 2134. notice and publication once in the Federal Register on each application under section 103 or 104 b. for a license for a facility, and on any application under section 104 c. for a license for a testing facility.”

  3. Pub. L. 87–615 § 2 · 76 Stat. 409

    Substituted · 42 U.S.C. § 2239(a)

    Pub. L. 87–615 substituted “construction permit for a facility” and “construction permit for a testing facility” for “license for a facility” and “license for a testing facility” respectively, and authorized the commission in cases where a permit has been issued following a hearing, and in the absence of a request therefor by anyone whose interest may be affected, to issue an operating license or an amendment to a construction permit or an operating license without a hearing upon thirty days’ notice and publication once in the Federal Register of its intent to do so, and to dispense with such notice and publication with respect to any application for an amendment to a construction permit or to an operating license upon its determination that the amendment involves no significant hazards consideration

    Source evidence

    Code amendment note
    Subsec. (a). Pub. L. 87–615 substituted “construction permit for a facility” and “construction permit for a testing facility” for “license for a facility” and “license for a testing facility” respectively, and authorized the commission in cases where a permit has been issued following a hearing, and in the absence of a request therefor by anyone whose interest may be affected, to issue an operating license or an amendment to a construction permit or an operating license without a hearing upon thirty days’ notice and publication once in the Federal Register of its intent to do so, and to dispense with such notice and publication with respect to any application for an amendment to a construction permit or to an operating license upon its determination that the amendment involves no significant hazards consideration.

    Enacted provision · exact public law section
    Sec. 2. The second sentence of subsection 189a. of the Atomic Energy Act of 1954, as amended, is deleted and the following is inserted in 68 Stat. 955. 42 USC 2239. lieu thereof: “The Commission shall hold a hearing after thirty days’ notice and publication once in the Federal Register, on each application under section 103 or 104b. for a construction permit for a facility, and on any application Publication in F. R. under section 104c. for a construction permit for a testing facility. In cases where such a construction permit has 68 Stat. 936. 937. 42 USC 2133, 2134. been issued following the holding of such a hearing, the Commission may, in the absence of a request therefor by any person whose interest may be affected, issue an operating license or an amendment to a construction permit or an amendment to an operating license without a hearing, but upon thirty days’ notice and publication once in the Federal Register of its intent to do so. The Commission may dispense with such thirty days’ notice and publication with respect to any application for an amendment to a construction permit or an amendment to an operating license upon a determination by the Commission that the amendment involves no significant hazards consideration.”

  4. Pub. L. 97–415 § 12(a) · 96 Stat. 2067

    1. Amended · 42 U.S.C. § 2239(a)

      Pub. L. 97–415 designated existing provisions as par. (1)

    2. Added · 42 U.S.C. § 2239(a)

      Pub. L. 97–415 added par. (2)

    Source evidence

    Code amendment note
    Subsec. (a). Pub. L. 97–415 designated existing provisions as par. (1) and added par. (2).

    Enacted provision · exact public law section
    (a) Section 189 a. of the Atomic Energy Act of 1954 (42 U.S.C. 2239(a)) is amended— (1) by inserting “(1)” after the subsection designation; and (2) by adding at the end thereof the following new paragraph: “(2) (A) The Commission may issue and make immediately effective any amendment to an operating license, upon a determination by the Commission that such amendment involves no significant hazards consideration, notwithstanding the pendency before the Commission of a request for a hearing from any person. Such amendment may be issued and made immediately effective in advance of the holding and completion of any required hearing. In determining under this section whether such amendment involves no significant hazards consideration, the Commission shall consult with the State in which the facility involved is located. In all other respects such amendment shall meet the requirements of this Act. “(B) The Commission shall periodically (but not less frequently Notice of publication. than once every thirty days) publish notice of any amendments issued, or proposed to be issued, as provided in subparagraph (A). Each such notice shall include all amendments issued, or proposed to be issued, since the date of publication of the last such periodic notice. Such notice shall, with respect to each amendment or proposed amendment (i) identify the facility involved; and (ii) provide a brief description of such amendment. Nothing in this subsection shall be construed to delay the effective date of any amendment. “(C) The Commission shall, during the ninety-day period following Regulations establishing standards, criteria, and procedures. the effective date of this paragraph, promulgate regulations establishing (i) standards for determining whether any amendment to an operating license involves no significant hazards consideration; (ii) criteria for providing or, in emergency situations, dispensing with prior notice and reasonable opportunity for public comment on any such determination, which criteria shall take into account the exigency of the need for the amendment involved; and (iii) procedures for consultation on any such determination with the State in which the facility involved is located.”.

  5. Energy Policy Act of 1992

    Pub. L. 102–486 § 2802 · 106 Stat. 2776

    1. Amended · 42 U.S.C. § 2239(a)(1)

      Pub. L. 102–486, § 2802, designated existing provisions as subpar. (A)

    2. Added · 42 U.S.C. § 2239(a)(1)

      Pub. L. 102–486, § 2802, added subpar. (B)

    Source evidence

    Code amendment note
    Subsec. (a)(1). Pub. L. 102–486, § 2802, designated existing provisions as subpar. (A) and added subpar. (B).

    Enacted provision · exact public law section
    SEC. 2802. POST-CONSTRUCTION HEARINGS ON COMBINED LICENSES. Section 189 a. (1) of the Atomic Energy Act of 1954 (42 U.S.C. 2239(a)(1)) is amended— (1) by adding a subparagraph designator “(A)” before “In any proceeding under this Act,”; and (2) by adding after subparagraph (A) the following new subparagraph: “(B) (i) Not less than 180 days before the date scheduled for initial loading of fuel into a plant by a licensee that has been issued a combined construction permit and operating license under section 185 b., the Commission snail publish in the Federal Register notice of intended operation. That notice shall provide that any person whose interest may be affected by operation of the plant, may within 60 days request the Commission to hold a hearing on whether the facility as constructed complies, or on completion will comply, with the acceptance criteria of the license. “(ii) A request for hearing under clause (i) shall show, prima facie, that one or more of the acceptance criteria in the combined license have not been, or will not be met, and the specific operational consequences of nonconformance that would be contrary to providing reasonable assurance of adequate protection of the public health and safety. “(iii) After receiving a request for a hearing under clause (i), the Commission expeditiously shall either deny or grant the request. If the request is granted, the Commission shall determine, after considering petitioners’ prima facie showing and any answers there-to, whether during a period of interim operation, there will be reasonable assurance of adequate protection of the public health and safety. If the Commission determines that there is such reasonable assurance, it shall allow operation during an interim period under the combined license. “(iv) The Commission, in its discretion, shall determine appropriate hearing procedures, whether informal or formal adjudicatory, for any hearing under clause (i), and shall state its reasons therefor. “(v) The Commission shall, to the maximum possible extent, render a decision on issues raised by the hearing request within 180 days of the publication of the notice provided by clause (i) or the anticipated date for initial loading of fuel into the reactor, whichever is later. Commencement of operation under a combined license is not subject to subparagraph (A).”.

    Effective date note
    Subsec. (a)(1)(B) of this section, as added by section 2802 of Pub. L. 102–486, applicable to all proceedings involving combined license for which application was filed after May 8, 1991, see section 2806 of Pub. L. 102–486, set out as a note under section 2235 of this title.

  6. Energy Policy Act of 1992

    Pub. L. 102–486 § 2804 · 106 Stat. 2776

    Inserted · 42 U.S.C. § 2239(a)(2)(A); 42 U.S.C. § 2239(a)(2)(C)

    Pub. L. 102–486, § 2804, inserted “or any amendment to a combined construction and operating license” after “any amendment to an operating license”

    Source evidence

    Code amendment note
    Subsec. (a)(2)(A), (C). Pub. L. 102–486, § 2804, inserted “or any amendment to a combined construction and operating license” after “any amendment to an operating license”.

    Enacted provision · exact public law section
    SEC. 2804. AMENDMENT OF A COMBINED LICENSE PENDING A HEARING. Section 189 a. (2) of the Atomic Energy Act of 1954 (42 U.S.C. 2239(a)(2)) is amended by inserting “or any amendment to a combined construction and operating license” after “any amendment to an operating license” each time it occurs.

    Effective date note
    Subsec. (a)(1)(B) of this section, as added by section 2802 of Pub. L. 102–486, applicable to all proceedings involving combined license for which application was filed after May 8, 1991, see section 2806 of Pub. L. 102–486, set out as a note under section 2235 of this title.

  7. Energy Policy Act of 1992

    Pub. L. 102–486 § 2805 · 106 Stat. 2776

    Inserted · 42 U.S.C. § 2239(b)

    Pub. L. 102–486, § 2805, inserted “or any final order allowing or prohibiting a facility to begin operating under a combined construction and operating license” before “shall be subject to judicial review”

    Source evidence

    Code amendment note
    Subsec. (b). Pub. L. 102–486, § 2805, inserted “or any final order allowing or prohibiting a facility to begin operating under a combined construction and operating license” before “shall be subject to judicial review”.

    Enacted provision · exact public law section
    SEC. 2805. JUDICIAL REVIEW. Section 189 b. of the Atomic Energy Act of 1954 (42 U.S.C. 2239(b)) is amended by inserting “or any final order allowing or prohibiting a facility to begin operating under a combined construction and operating license” before “shall be subject to judicial review”.

    Effective date note
    Subsec. (a)(1)(B) of this section, as added by section 2802 of Pub. L. 102–486, applicable to all proceedings involving combined license for which application was filed after May 8, 1991, see section 2806 of Pub. L. 102–486, set out as a note under section 2235 of this title.

  8. USEC Privatization Act

    Pub. L. 104–134 title III § 3116(c) · 110 Stat. 1321

    Amended · 42 U.S.C. § 2239(b)

    Pub. L. 104–134 amended subsec. (b) generally. Prior to amendment, subsec. (b) read as follows: “Any final order entered in any proceeding of the kind specified in subsection (a) of this section or any final order allowing or prohibiting a facility to begin operating under a combined construction and operating license shall be subject to judicial review in the manner prescribed in the Act of December 29, 1950, as amended (ch. 1189, 64 Stat. 1129), and to the provisions of section 10 of the Administrative Procedure Act, as amended.”

    Source evidence

    Code amendment note
    Subsec. (b). Pub. L. 104–134 amended subsec. (b) generally. Prior to amendment, subsec. (b) read as follows: “Any final order entered in any proceeding of the kind specified in subsection (a) of this section or any final order allowing or prohibiting a facility to begin operating under a combined construction and operating license shall be subject to judicial review in the manner prescribed in the Act of December 29, 1950, as amended (ch. 1189, 64 Stat. 1129), and to the provisions of section 10 of the Administrative Procedure Act, as amended.”

    Enacted provision · exact public law section
    (c) Judicial Review of NRC Actions.— Section 189b. of the Atomic Energy Act of 1954 (42 U.S.C. 2239(b)) is amended to read as follows: “b. The following Commission actions shall be subject to judicial review in the manner prescribed in chapter 158 of title 28, United States Code, and chapter 7 of title 5, United States Code: “(1) Any final order entered in any proceeding of the kind specified in subsection (a). “(2) Any final order allowing or prohibiting a facility to begin operating under a combined construction and operating license. “(3) Any final order establishing by regulation standards to govern the Department of Energy’s gaseous diffusion uranium enrichment plants, including any such facilities leased to a corporation established under the USEC Privatization Act. “(4) Any final determination under section 1701(c) relating to whether the gaseous diffusion plants, including any such facilities leased to a corporation established under the USEC Privatization Act, are in compliance with the Commission’s standards governing the gaseous diffusion plants and all applicable laws.”.

9 of 10 references resolved to an enrolled provision · 1 partial

Editorial Notes

References in Text

This chapter, referred to in subsec. (a)(1)(A), (2)(A), was in the original “this Act”, meaning act Aug. 1, 1946, ch. 724, as added by act Aug. 30, 1954, ch. 1073, § 1, 68 Stat. 919, known as the Atomic Energy Act of 1954, which is classified principally to this chapter. For complete classification of this Act to the Code, see Short Title note set out under section 2011 of this title and Tables.

The effective date of this paragraph, referred to in subsec. (a)(2)(C), probably means the date of enactment of Pub. L. 97–415, which was approved .

The USEC Privatization Act, referred to in subsec. (b)(3), (4), is subchapter A (§§ 3101–3117) of chapter 1 of title III of Pub. L. 104–134, , 110 Stat. 1321–335, which is classified principally to subchapter VIII (§ 2297h et seq.) of this chapter. For complete classification of this Act to the Code, see Short Title of 1996 Amendment note set out under section 2011 of this title and Tables.

Amendments1957–1996 · 5 rounds

1996

Subsec. (b). Pub. L. 104–134 amended subsec. (b) generally. Prior to amendment, subsec. (b) read as follows: “Any final order entered in any proceeding of the kind specified in subsection (a) of this section or any final order allowing or prohibiting a facility to begin operating under a combined construction and operating license shall be subject to judicial review in the manner prescribed in the Act of , as amended (ch. 1189, 64 Stat. 1129), and to the provisions of section 10 of the Administrative Procedure Act, as amended.”

1992

Subsec. (a)(1). Pub. L. 102–486, § 2802, designated existing provisions as subpar. (A) and added subpar. (B).

Subsec. (a)(2)(A), (C). Pub. L. 102–486, § 2804, inserted “or any amendment to a combined construction and operating license” after “any amendment to an operating license”.

Subsec. (b). Pub. L. 102–486, § 2805, inserted “or any final order allowing or prohibiting a facility to begin operating under a combined construction and operating license” before “shall be subject to judicial review”.

1983

Subsec. (a). Pub. L. 97–415 designated existing provisions as par. (1) and added par. (2).

1962

Subsec. (a). Pub. L. 87–615 substituted “construction permit for a facility” and “construction permit for a testing facility” for “license for a facility” and “license for a testing facility” respectively, and authorized the commission in cases where a permit has been issued following a hearing, and in the absence of a request therefor by anyone whose interest may be affected, to issue an operating license or an amendment to a construction permit or an operating license without a hearing upon thirty days’ notice and publication once in the Federal Register of its intent to do so, and to dispense with such notice and publication with respect to any application for an amendment to a construction permit or to an operating license upon its determination that the amendment involves no significant hazards consideration.

1957

Subsec. (a). Pub. L. 85–256 required the Commission to hold a hearing after 30 days notice and publication once in the Federal Register on an application for a license for a facility or a testing facility.

Statutory Notes and Related Subsidiaries

Effective Date of 1992 Amendment

Subsec. (a)(1)(B) of this section, as added by section 2802 of Pub. L. 102–486, applicable to all proceedings involving combined license for which application was filed after , see section 2806 of Pub. L. 102–486, set out as a note under section 2235 of this title.

Authority To Effectuate Amendments to Operating Licenses

Pub. L. 97–415, § 12(b), , 96 Stat. 2073, provided that: “The authority of the Nuclear Regulatory Commission, under the provisions of the amendment made by subsection (a) [amending this section], to issue and to make immediately effective any amendment to an operating license shall take effect upon the promulgation by the Commission of the regulations required in such provisions.”

Review of Nuclear Proliferation Assessment Statements

No court or regulatory body to have jurisdiction to compel performance of or to review adequacy of performance of any Nuclear Proliferation Assessment Statement called for by the Atomic Energy Act of 1954 [this chapter] or by the Nuclear Non-Proliferation Act of 1978, Pub. L. 95–242, , 92 Stat. 120, see section 2160a of this title.

Administrative Orders Review Act

Court of appeals exclusive jurisdiction respecting final orders of Atomic Energy Commission, now the Nuclear Regulatory Commission and the Secretary of Energy, made reviewable by this section, see section 2342 of Title 28, Judiciary and Judicial Procedure.

Credits

1946–1996 · 6 acts
  1. 1946Aug. 1, 1946, ch. 724, title I, § 189, as added Aug. 30, 1954, ch. 1073, § 1, 68 Stat. 955
  2. 1957amended Pub. L. 85–256, § 7, , 71 Stat. 579
  3. 1962Pub. L. 87–615, § 2, , 76 Stat. 409
  4. 1983Pub. L. 97–415, § 12(a), , 96 Stat. 2073
  5. 1992renumbered title I and amended Pub. L. 102–486, title IX, § 902(a)(8), title XXVIII, §§ 2802, 2804, 2805, , 106 Stat. 2944, 3120, 3121
  6. 1996Pub. L. 104–134, title III, § 3116(c), , 110 Stat. 1321–349.
Show as published

(Aug. 1, 1946, ch. 724, title I, § 189, as added Aug. 30, 1954, ch. 1073, § 1, 68 Stat. 955; amended Pub. L. 85–256, § 7, , 71 Stat. 579; Pub. L. 87–615, § 2, , 76 Stat. 409; Pub. L. 97–415, § 12(a), , 96 Stat. 2073; renumbered title I and amended Pub. L. 102–486, title IX, § 902(a)(8), title XXVIII, §§ 2802, 2804, 2805, , 106 Stat. 2944, 3120, 3121; Pub. L. 104–134, title III, § 3116(c), , 110 Stat. 1321–349.)

Parsed from the official OLRC USLM XML in data/usc_all/usc42.xml · release point 119-108 · OLRC build 2026-09-09

USLM identifier /us/usc/t42/s2239