Skip to content

Title 42 — The Public Health and Welfare

Part B · Chapter 92 — Powerplant and Industrial Fuel Use

§ 8321. Temporary exemptions

Statutory text

(a)

General exemption due to lack of alternate fuel supply, site limitations, or environmental requirements

After consideration of a petition (and comments thereon) for an exemption for a powerplant from the prohibitions of part A, the Secretary shall, by order, grant an exemption under this subsection for the use of natural gas or petroleum, if he finds that the petitioner has demonstrated that for the period of the proposed exemption, despite diligent good faith efforts—

(1)

it is likely that an adequate and reliable supply of coal or other alternate fuel of the quality necessary to conform with design and operational requirements for use as a primary energy source will not be available to such powerplant at a cost (taking into account associated facilities for the transportation and use of such fuel) which, based upon the best practicable estimates, does not substantially exceed the cost, as determined by rule by the Secretary, of the fuel that would be used as a primary energy source;

(2)

one or more site limitations exist which would ot 1 permit the location or operation of such a powerplant using coal or any other alternate fuel as a primary energy source; or

(3)

the prohibitions of section 8311 of this title could not be satisfied without violating applicable environmental requirements.

(b)

Temporary exemption based upon future use of synthetic fuels

After consideration of a petition (and comments thereon) for an exemption for a powerplant from the prohibitions of part A, the Secretary shall, by order, grant an exemption under this subsection for the use of natural gas or petroleum, if he finds that the petitioner has demonstrated that—

(1)

the petitioner will comply with the prohibitions of part A by the end of the proposed exemption by the use of a synthetic fuel derived from coal or another alternate fuel; and

(2)

the petitioner is not able to comply with such prohibitions by the use of such synthetic fuel until the end of the proposed exemption.

The effectiveness of an exemption under this subsection is conditioned on the petitioner filing and maintaining a compliance plan meeting the requirements of section 8324(b) of this title.

(c)

, (d) Repealed. Pub. L. 100–42, § 1(c)(5)(E), , 101 Stat. 312

(e)

Duration of temporary exemptions

(1)

Except as provided in paragraph (2), exemptions under this section for any powerplant may not exceed, taking into account any extension or renewal, 5 years.

(2)
(A)

An exemption under subsection (a)(1) may be granted for a period of more than 5 years, but may not exceed, taking into account any extension or renewal, 10 years.

(B)

An exemption under subsection (b) may be extended beyond the 5-year limit under paragraph (1), but such exemption, so extended, may not exceed 10 years.

(3)

If an exemption is granted for any powerplant before the powerplant is placed in service, the period before it is placed in service shall not be taken into account in computing the 5-year and the 10-year limitations of paragraphs (1) and (2).

Footnotes

  1. 1 So in original. Probably should be “not”.

Legislative history

Reconstructed from this section’s Code source credit and amendment notes, resolved against the local Statutes at Large. Editorial notes are evidence, not the law that made the change.

  1. Pub. L. 95–620 title II § 211 · 92 Stat. 3289

    Enacted · 42 U.S.C. § 8321

    Pub. L. 95–620, title II, § 211, Nov. 9, 1978, 92 Stat. 3299

    Source evidence

    Code source credit
    Pub. L. 95–620, title II, § 211, Nov. 9, 1978, 92 Stat. 3299

    Enacted provision · exact public law section
    SEC. 211. TEMPORARY EXEMPTIONS. (a) General Exemption Due to Lack of Alternate Fuel Supply, Site Limitations, or Environmental Requirements.— After consideration of a petition (and comments thereon) for an exemption for a powerplant or installation from one or more of the prohibitions of subtitle A, the Secretary shall, by order, grant an exemption under this subsection for the use of natural gas or petroleum, if he finds that the petitioner has demonstrated that for the period of the proposed exemption, despite diligent good faith efforts— (1) it is likely that an adequate and reliable supply of coal or other alternate fuel of the quality necessary to conform with design and operational requirements for use as a primary energy source will not be available to such powerplant or installation at a cost (taking into account associated facilities for the transportation and use of such fuel) which, based upon the best practicable estimates, does not substantially exceed the cost, as determined by rule by the Secretary, of using imported petroleum as a primary energy source; (2) one or more site limitations exist which would of permit the location or operation of such a powerplant or installation using coal or any other alternate fuel as a primary energy source; or (3) the prohibitions of section 201 or 202 could not be satisfied without violating applicable environmental requirements. (b) Temporary Exemption Based Upon Future Use of Synthetic Fuels.— After consideration of a petition (and comments thereon) for an exemption for a powerplant or installation from one or more of the prohibitions of subtitle A, the Secretary shall, by order, grant an exemption under this subsection for the use of natural gas or petroleum, if he finds that the petitioner has demonstrated that— (1) the petitioner will comply with the prohibitions of subtitle A by the end of the proposed exemption by the use of a synthetic fuel derived from coal or another alternate fuel; and (2) the petitioner is not able to comply with such prohibitions by the use of such synthetic fuel until the end of the proposed exemption. Compliance plan, filing and maintenance. The effectiveness of an exemption under this subsection is conditioned on the petitioner filing and maintaining a compliance plan meeting the requirements of section 214(b). (c) Temporary Public Interest Exemption.— After consideration of a petition (and comments thereon) for an exemption for a powerplant or installation from one or more of the prohibitions of subtitle A, the Secretary may, by order, grant an exemption under this subsection for the use of natural gas or petroleum, if he finds that the petitioner has demonstrated that for the period of the proposed exemption the issuance of such exemption would be in the public interest and would be consistent with the purposes of this Act (d) Temporary Exemption for the Use of Petroleum by Certain Installations.— After consideration of a petition (and comments thereon) for an exemption from the prohibition of the use of petroleum under section 202 for an installation with a design capacity of consuming any fuel (or any mixture thereof) at a fuel heat input rate which does not exceed 300 million Btu’s per hour, the Secretary may, by order, grant an exemption under this subsection for the use of petroleum if lie finds that the petitioner has demonstrated, by the existence of binding contracts or other evidence, including appropriate State construction permits, that he will use coal or another alternate fuel for at least 75 percent of the annual fuel heat input rate upon the expiration of such Post, p. 3349. exemption. For provisions relating to authority to receive, consider and granting (or denying) certain petitons for an exemption under this subsection, see section 902(b). (e) Duration of Temporary Exemptions.— (1) Except as provided in paragraph (2), exemptions under this section for any powerplant or installation may not exceed, taking into account any extension or renewal, 5 years. (2) (A) An exemption under subsection (a)(1) may be granted for a period of more than 5 years, but may not exceed, taking into account any extension or renewal. 10 years. (B) An exemption under subsection (b) may be extended beyond the 5-year limit under paragraph (1), but such exemption, so extended, may not exceed 10 years. (3) If an exemption is granted for any powerplant or installation before the powerplant or installation is placed in service, the period before it is placed in service, shall not be taken into account in computing the 5-year and the 10-year limitations of paragraphs (1) and (2).

  2. Pub. L. 100–42 § 1(c)(5)(A) · 101 Stat. 310

    1. Substituted · 42 U.S.C. § 8321(a)

      Pub. L. 100–42, § 1(c)(5)(A)–(D), substituted “from” for “or installation from one or more of” in introductory provisions

    2. Substituted · 42 U.S.C. § 8321(a)

      Pub. L. 100–42, § 1(c)(5)(A)–(D), substituted “the fuel that would be used” for “using imported petroleum”

    3. Struck · 42 U.S.C. § 8321(a)

      Pub. L. 100–42, § 1(c)(5)(A)–(D), struck out “or installation” after “powerplant” in par. (1)

    4. Struck · 42 U.S.C. § 8321(a)

      Pub. L. 100–42, § 1(c)(5)(A)–(D), struck out “or installation” after “powerplant” in par. (2)

    5. Struck · 42 U.S.C. § 8321(a)

      Pub. L. 100–42, § 1(c)(5)(A)–(D), struck out “or 8312” after “8311” in par. (3)

    Source evidence

    Code amendment note
    Subsec. (a). Pub. L. 100–42, § 1(c)(5)(A)–(D), substituted “from” for “or installation from one or more of” in introductory provisions, substituted “the fuel that would be used” for “using imported petroleum” and struck out “or installation” after “powerplant” in par. (1), struck out “or installation” after “powerplant” in par. (2), and struck out “or 8312” after “8311” in par. (3).

    Enacted provision · exact public law section
    (A) by striking “or installation from one or more of” and inserting “from” each place it appears;

  3. Pub. L. 100–42 § 1(c)(5)(A) · 101 Stat. 310

    Substituted · 42 U.S.C. § 8321(b)

    Pub. L. 100–42, § 1(c)(5)(A), substituted “from” for “or installation from one or more of”

    Source evidence

    Code amendment note
    Subsec. (b). Pub. L. 100–42, § 1(c)(5)(A), substituted “from” for “or installation from one or more of”.

    Enacted provision · exact public law section
    (A) by striking “or installation from one or more of” and inserting “from” each place it appears;

  4. Pub. L. 100–42 § 1(c)(5)(E) · 101 Stat. 310

    Struck · 42 U.S.C. § 8321(c)

    Pub. L. 100–42, § 1(c)(5)(E), struck out subsec. (c) which read as follows: “After consideration of a petition (and comments thereon) for an exemption for a powerplant or installation from one or more of the prohibitions of part A, the Secretary may, by order, grant an exemption under this subsection for the use of natural gas or petroleum, if he finds that the petitioner has demonstrated that for the period of the proposed exemption the issuance of such exemption would be in the public interest and would be consistent with the purposes of this chapter.”

    Source evidence

    Code amendment note
    Subsec. (c). Pub. L. 100–42, § 1(c)(5)(E), struck out subsec. (c) which read as follows: “After consideration of a petition (and comments thereon) for an exemption for a powerplant or installation from one or more of the prohibitions of part A, the Secretary may, by order, grant an exemption under this subsection for the use of natural gas or petroleum, if he finds that the petitioner has demonstrated that for the period of the proposed exemption the issuance of such exemption would be in the public interest and would be consistent with the purposes of this chapter.”

    Enacted provision · exact public law section
    (E) by striking subsections (c) and (d).

  5. Pub. L. 100–42 § 1(c)(5)(E) · 101 Stat. 310

    Struck · 42 U.S.C. § 8321(d)

    Pub. L. 100–42, § 1(c)(5)(E), struck out subsec. (d) which read as follows: “After consideration of a petition (and comments thereon) for an exemption from the prohibition of the use of petroleum under section 8312 of this title for an installation with a design capacity of consuming any fuel (or any mixture thereof) at a fuel heat input rate which does not exceed 300 million Btu’s per hour, the Secretary may, by order, grant an exemption under this subsection for the use of petroleum if he finds that the petitioner has demonstrated, by the existence of binding contracts or other evidence, including appropriate State construction permits, that he will use coal or another alternate fuel for at least 75 percent of the annual fuel heat input rate upon the expiration of such exemption. For provisions relating to authority to receive, consider and granting (or denying) certain petitons [sic] for an exemption under this subsection, see section 902(b).”

    Source evidence

    Code amendment note
    Subsec. (d). Pub. L. 100–42, § 1(c)(5)(E), struck out subsec. (d) which read as follows: “After consideration of a petition (and comments thereon) for an exemption from the prohibition of the use of petroleum under section 8312 of this title for an installation with a design capacity of consuming any fuel (or any mixture thereof) at a fuel heat input rate which does not exceed 300 million Btu’s per hour, the Secretary may, by order, grant an exemption under this subsection for the use of petroleum if he finds that the petitioner has demonstrated, by the existence of binding contracts or other evidence, including appropriate State construction permits, that he will use coal or another alternate fuel for at least 75 percent of the annual fuel heat input rate upon the expiration of such exemption. For provisions relating to authority to receive, consider and granting (or denying) certain petitons [sic] for an exemption under this subsection, see section 902(b).”

    Enacted provision · exact public law section
    (E) by striking subsections (c) and (d).

  6. Pub. L. 100–42 § 1(c)(5)(B) · 101 Stat. 310

    Struck · 42 U.S.C. § 8321(e)(1); 42 U.S.C. § 8321(e)(3)

    Pub. L. 100–42, § 1(c)(5)(B), struck out “or installation” after “powerplant” wherever appearing

    Source evidence

    Code amendment note
    Subsec. (e)(1), (3). Pub. L. 100–42, § 1(c)(5)(B), struck out “or installation” after “powerplant” wherever appearing.

    Enacted provision · exact public law section
    (B) by striking “or installation” wherever it appears;

10 of 10 references resolved to an enrolled provision

Editorial Notes

Amendments

1987—Subsec. (a). Pub. L. 100–42, § 1(c)(5)(A)–(D), substituted “from” for “or installation from one or more of” in introductory provisions, substituted “the fuel that would be used” for “using imported petroleum” and struck out “or installation” after “powerplant” in par. (1), struck out “or installation” after “powerplant” in par. (2), and struck out “or 8312” after “8311” in par. (3).

Subsec. (b). Pub. L. 100–42, § 1(c)(5)(A), substituted “from” for “or installation from one or more of”.

Subsec. (c). Pub. L. 100–42, § 1(c)(5)(E), struck out subsec. (c) which read as follows: “After consideration of a petition (and comments thereon) for an exemption for a powerplant or installation from one or more of the prohibitions of part A, the Secretary may, by order, grant an exemption under this subsection for the use of natural gas or petroleum, if he finds that the petitioner has demonstrated that for the period of the proposed exemption the issuance of such exemption would be in the public interest and would be consistent with the purposes of this chapter.”

Subsec. (d). Pub. L. 100–42, § 1(c)(5)(E), struck out subsec. (d) which read as follows: “After consideration of a petition (and comments thereon) for an exemption from the prohibition of the use of petroleum under section 8312 of this title for an installation with a design capacity of consuming any fuel (or any mixture thereof) at a fuel heat input rate which does not exceed 300 million Btu’s per hour, the Secretary may, by order, grant an exemption under this subsection for the use of petroleum if he finds that the petitioner has demonstrated, by the existence of binding contracts or other evidence, including appropriate State construction permits, that he will use coal or another alternate fuel for at least 75 percent of the annual fuel heat input rate upon the expiration of such exemption. For provisions relating to authority to receive, consider and granting (or denying) certain petitons [sic] for an exemption under this subsection, see section 902(b).”

Subsec. (e)(1), (3). Pub. L. 100–42, § 1(c)(5)(B), struck out “or installation” after “powerplant” wherever appearing.

Statutory Notes and Related Subsidiaries

Exemption for Certain Electric Powerplants and Temporary Exemption Issued Under Subsection (d) as Effective Prior to 180 Days After November 9, 1978

For effectiveness of exemption for certain electric powerplants and the temporary exemption issued under subsec. (d) of this section as prior to 180 days after , see section 902 of Pub. L. 95–620, set out as a note under section 8301 of this title.

Credits

1978–1987 · 2 acts
  1. 1978Pub. L. 95–620, title II, § 211, , 92 Stat. 3299
  2. 1987Pub. L. 100–42, § 1(c)(5), , 101 Stat. 312.
Show as published

(Pub. L. 95–620, title II, § 211, , 92 Stat. 3299; Pub. L. 100–42, § 1(c)(5), , 101 Stat. 312.)

Parsed from the official OLRC USLM XML in data/usc_all/usc42.xml · release point 119-108 · OLRC build 2026-09-09

USLM identifier /us/usc/t42/s8321