Skip to content

Title 42 — The Public Health and Welfare

Part B · Chapter 92 — Powerplant and Industrial Fuel Use

§ 8323. General requirements for exemptions

Statutory text

(a)

Use of mixtures or fluidized bed combustion not feasible

Except in the case of an exemption under section 8322(d) of this title, the Secretary may grant a permanent exemption for a powerplant under this part only—

(1)

if the applicant has demonstrated that the use of a mixture of natural gas or petroleum and coal or another alternate fuel, for which an exemption under section 8322(d) of this title would be available, is not economically or technically feasible; and

(2)

if the Secretary has not made a finding that the use of a method of fluidized bed combustion of coal or another alternate fuel is economically and technically feasible.

(b)

State approval required for powerplant

If the appropriate State regulatory authority has not approved a powerplant for which a petition has been filed, such exemption, to the extent it applies to the prohibition under section 8311 of this title against construction without the capability of using coal or another alternate fuel, shall not take effect until all approvals required by such State regulatory authority which relate to construction have been obtained.

(c)

No alternative power supply in the case of a powerplant

(1)

Except in the case of an exemption under section 8322(c) of this title, the Secretary may not grant an exemption for a new powerplant unless he finds that the petitioner has demonstrated that there is no alternative supply of electric power which is available within a reasonable distance at a reasonable cost without impairing short-run or long-run reliability of service and which can be obtained by the petitioner, despite reasonable good faith efforts.

(2)

The Secretary shall forward a copy of any such petition to the Federal Energy Regulatory Commission promptly after it is filed with the Secretary and shall consult with such Commission before making any finding on such petition under paragraph (1).

Legislative history

Reconstructed from this section’s Code source credit and amendment notes, resolved against the local Statutes at Large. Editorial notes are evidence, not the law that made the change.

  1. Pub. L. 95–620 title II § 213 · 92 Stat. 3289

    Enacted · 42 U.S.C. § 8323

    Pub. L. 95–620, title II, § 213, Nov. 9, 1978, 92 Stat. 3304

    Source evidence

    Code source credit
    Pub. L. 95–620, title II, § 213, Nov. 9, 1978, 92 Stat. 3304

    Enacted provision · exact public law section
    SEC. 213. GENERAL REQUIREMENTS FOR EXEMPTIONS. (a) 42 USC 8323. Use of Mixtures or Fluidized Bed Combustion Not Feasible.— Except in the case of an exemption under section 212 (d) or (g), the Secretary may grant a permanent exemption for a powerplant or installation under this subtitle only— (1) if the applicant has demonstrated that the use of a mixture of natural gas or petroleum and coal or another alternate fuel, for which an exemption under section 212(d) would be available, is not economically or technically feasible; and (2) if the Secretary has not made a finding that the use of a method of fluidized bed combustion of coal or another alternate fuel is economically and technically feasible. (b) State Approval Required for Powerplant.— If the appropriate State regulatory authority has not approved a powerplant for which a petition has been filed, such exemption— (1) to the extent it applies to the prohibition under section 201 (2) against construction without the capability of using coal or another alternate fuel, shall not take effect until all approvals required by such State regulatory authority which relate to construction have been obtained; ana (3) to the extent it applies to the prohibition under section 201 (1) against the use of natural gas or petroleum as a primary energy source, shall not take effect until all approvals required by such State regulatory authority which relate to construction or operation have been obtained. (c) No Alternative Power Supply in the Case of a Powerplant.— (1) Except in the case of an exemption under section 212 (c) or (g), the Secretary may not grant an exemption for a new powerplant unless he finds that the petitioner has demonstrated that there is no alternative supply of electric power which is available within a reasonable distance at a reasonable cost without impairing short-run or long-run reliability of service and which can be obtained by the petitioner, despite reasonable good faith efforts. (2) Petition and consultation. The Secretary shall forward a copy of any such petition to the consultation. Federal Energy Regulatory Commission promptly after it is filed with the Secretary and shall consult with such Commission before making any finding on such petition under paragraph (1).

  2. Pub. L. 100–42 § 1(c)(7)(A) · 101 Stat. 310

    Struck · 42 U.S.C. § 8323(a)

    Pub. L. 100–42, § 1(c)(7)(A), (B), in introductory provisions struck out “or (g)” after “8322(d)” and “or installation” after “powerplant”

    Source evidence

    Code amendment note
    Subsec. (a). Pub. L. 100–42, § 1(c)(7)(A), (B), in introductory provisions struck out “or (g)” after “8322(d)” and “or installation” after “powerplant”.

    Enacted provision · exact public law section
    (A) in subsections (a) and (c)(1), by striking “or (g)”;

  3. Pub. L. 100–42 § 1(c)(7)(C) · 101 Stat. 310

    Amended · 42 U.S.C. § 8323(b)

    Pub. L. 100–42, § 1(c)(7)(C), amended subsec. (b) generally. Prior to amendment, subsec. (b) read as follows: “If the appropriate State regulatory authority has not approved a powerplant for which a petition has been filed, such exemption—

    Source evidence

    Code amendment note
    Subsec. (b). Pub. L. 100–42, § 1(c)(7)(C), amended subsec. (b) generally. Prior to amendment, subsec. (b) read as follows: “If the appropriate State regulatory authority has not approved a powerplant for which a petition has been filed, such exemption—

    “(1) to the extent it applies to the prohibition under section 8311(2) of this title against construction without the capability of using coal or another alternate fuel, shall not take effect until all approvals required by such State regulatory authority which relate to construction have been obtained; and “(2) to the extent it applies to the prohibition under section 8311(1) of this title against the use of natural gas or petroleum as a primary energy source, shall not take effect until all approvals required by such State regulatory authority which relate to construction or operation have been obtained.”

    Enacted provision · exact public law section
    (C) by amending subsection (b) to read as follows: “(b) State Approval Required for Powerplant.— If the appropriate State regulatory authority has not approved a powerplant for which a petition has been filed, such exemption, to the extent it applies to the prohibition under section 201 against construction without the capability of using coal or another alternate fuel, shall not take effect until all approvals required by such State regulatory authority which relate to construction have been obtained.”.

  4. Pub. L. 100–42 § 1(c)(7)(A) · 101 Stat. 310

    Struck · 42 U.S.C. § 8323(c)(1)

    Pub. L. 100–42, § 1(c)(7)(A), in introductory provisions struck out “or (g)” after “section 8322(c)”

    Source evidence

    Code amendment note
    Subsec. (c)(1). Pub. L. 100–42, § 1(c)(7)(A), in introductory provisions struck out “or (g)” after “section 8322(c)”.

    Enacted provision · exact public law section
    (A) in subsections (a) and (c)(1), by striking “or (g)”;

4 of 4 references resolved to an enrolled provision

Editorial Notes

Amendments

1987—Subsec. (a). Pub. L. 100–42, § 1(c)(7)(A), (B), in introductory provisions struck out “or (g)” after “8322(d)” and “or installation” after “powerplant”.

Subsec. (b). Pub. L. 100–42, § 1(c)(7)(C), amended subsec. (b) generally. Prior to amendment, subsec. (b) read as follows: “If the appropriate State regulatory authority has not approved a powerplant for which a petition has been filed, such exemption—

“(1) to the extent it applies to the prohibition under section 8311(2) of this title against construction without the capability of using coal or another alternate fuel, shall not take effect until all approvals required by such State regulatory authority which relate to construction have been obtained; and

“(2) to the extent it applies to the prohibition under section 8311(1) of this title against the use of natural gas or petroleum as a primary energy source, shall not take effect until all approvals required by such State regulatory authority which relate to construction or operation have been obtained.”

Subsec. (c)(1). Pub. L. 100–42, § 1(c)(7)(A), in introductory provisions struck out “or (g)” after “section 8322(c)”.

Statutory Notes and Related Subsidiaries

Exemption for Certain Electric Powerplants as Effective Prior to 180 Days After November 9, 1978

For effectiveness of exemption for certain electric powerplants as prior to 180 days after , see section 902(a) of Pub. L. 95–620, set out as a note under section 8301 of this title.

Credits

1978–1987 · 2 acts
  1. 1978Pub. L. 95–620, title II, § 213, , 92 Stat. 3304
  2. 1987Pub. L. 100–42, § 1(c)(7), , 101 Stat. 312.
Show as published

(Pub. L. 95–620, title II, § 213, , 92 Stat. 3304; Pub. L. 100–42, § 1(c)(7), , 101 Stat. 312.)

Parsed from the official OLRC USLM XML in data/usc_all/usc42.xml · release point 119-108 · OLRC build 2026-09-09

USLM identifier /us/usc/t42/s8323