Title 43 — Public Lands
Chapter 38 — Crude Oil Transportation Systems
§ 2009. Expedited procedures for issuance of permits: enforcement of rights-of-way
Statutory text
Expedited procedures for approved systems
After issuance of a decision by the President approving any crude oil transportation system, all Federal officers and agencies shall expedite, to the maximum extent practicable, consistent with applicable provisions of law, all actions necessary to determine whether to issue, administer, or enforce rights-of-way across Federal lands and to issue Federal permits in connection with, or otherwise to authorize, construction and operation of such system. Any such action shall be consistent with applicable provisions of law. After taking any such action, such officer or agency shall publish notification of the taking of such action in the Federal Register.
Expedited procedures for Long Beach-Midland project
All decisions regarding issuance of Federal permits, rights-of-way, and leases and other Federal authorizations necessary for construction and operation of the Long Beach-Midland project shall be consistent with applicable provisions of Federal law, except that such decisions shall be made within 30 days after the date this chapter becomes effective. The President may extend the date by which such decisions, under the preceding sentence, are to be made to a date not later than 90 days after the effective date of this chapter. Notification of the making of such decisions shall be published in the Federal Register. Nothing in this section affects any decision made before .
Law governing rights-of-way
Rights-of-way over any Federal land with respect to an approved crude oil transportation system or the Long Beach-Midland project shall be governed by the provisions of section 185 of title 30, other than subsection (w)(2) of such section.
Legislative history
Reconstructed from this section’s Code source credit and amendment notes, resolved against the local Statutes at Large. Editorial notes are evidence, not the law that made the change.
Public Utility Regulatory Policies Act of 1978
Pub. L. 95–617 title V § 509 · 92 Stat. 3117
Enacted · 43 U.S.C. § 2009
(Pub. L. 95–617, title V, § 509, Nov. 9, 1978, 92 Stat. 3162.)
Source evidence
Code source credit
(Pub. L. 95–617, title V, § 509, Nov. 9, 1978, 92 Stat. 3162.)Enacted provision · exact public law section
SEC. 509. EXPEDITED PROCEDURES FOR ISSUANCE OF PERMITS: ENFORCEMENT OF RIGHTS-OF-WAY. (a) Expedited Procedures for Approved Systems.— After issuance of a decision by the President approving any crude oil transportation system, all Federal officers and agencies shall expedite, to the maximum extent practicable, consistent with applicable provisions of law, all actions necessary to determine whether to issue, administer, or enforce rights-of-way across Federal lands and to issue Federal permits in connection with, or otherwise to authorize, construction and operation of such system. Any such action shall be consistent with applicable provisions of law. After taking any such Publication in Federal Register. action, such officer or agency shall publish notification of the taking of such action in the Federal Register. (b) Expedited Procedures for Long Beach-Midland Project.— All decisions regarding issuance of Federal permits, rights-of-way, and leases and other Federal authorizations necessary for construction and operation of the Long Beach-Midland project shall be consistent with applicable provisions of Federal law. except that such decisions shall be. made within 30 days after the date this title becomes effective. The President may extend the date by which such decisions, under the preceding sentence, are to lie made to a date not later than 90 days after the effective date of this title. Notification Publication in Federal Register. of the making of such decisions shall be published in the Federal Register. Nothing in this section affects any decision made before the date of the enactment of this title. (c) Law Governing Rights-of-Way.— Rights-of-way over any Federal land with respect to an approved crude oil transportation system or the Long Beach-Midland project shall be governed by the provisions of section 28 of the Act of February 25, 1920, commonly referred to as the Mineral Leasing Act of 1920 (30 U.S.C. 185), other than subsection (w) (2) of such section.