Skip to content

Title 43 — Public Lands

Chapter 12 — Reclamation and Irrigation of Lands by Federal Government

§ 510a. Guidelines and inspection of project facilities and technical assistance to transferred works operating entities

Statutory text

(a)

Guidelines and inspections

(1)

Development of guidelines

Not later than 1 year after , the Secretary in consultation with transferred works operating entities shall develop, consistent with existing transfer contracts, specific inspection guidelines for project facilities which are in proximity to urbanized areas and which could pose a risk to public safety or property damage if such project facilities were to fail.

(2)

Conduct of inspections

Not later than 3 years after , the Secretary shall conduct inspections of those project facilities, which are in proximity to urbanized areas and which could pose a risk to public safety or property damage if such facilities were to fail, using such specific inspection guidelines and criteria developed pursuant to paragraph (1). In selecting project facilities to inspect, the Secretary shall take into account the potential magnitude of public safety and economic damage posed by each project facility.

(3)

Treatment of costs

The costs incurred by the Secretary in conducting these inspections shall be nonreimbursable.

(b)

Use of inspection data

The Secretary shall use the data collected through the conduct of the inspections under subsection (a)(2) to—

(1)

provide recommendations to the transferred works operating entities for improvement of operation and maintenance processes, operating procedures including operation guidelines consistent with existing transfer contracts, and structural modifications to those transferred works;

(2)

determine an appropriate inspection frequency for such nondam project facilities which shall not exceed 6 years; and

(3)

provide, upon request of transferred work operating entities, local governments, or State agencies, information regarding potential hazards posed by existing or proposed residential, commercial, industrial or public-use development adjacent to project facilities.

(c)

Technical assistance to transferred works operating entities

(1)

Authority of Secretary to provide technical assistance

The Secretary is authorized, at the request of a transferred works operating entity in proximity to an urbanized area, to provide technical assistance to accomplish the following, if consistent with existing transfer contracts:

(A)

Development of documented operating procedures for a project facility.

(B)

Development of documented emergency notification and response procedures for a project facility.

(C)

Development of facility inspection criteria for a project facility.

(D)

Development of a training program on operation and maintenance requirements and practices for a project facility for a transferred works operating entity’s workforce.

(E)

Development of a public outreach plan on the operation and risks associated with a project facility.

(F)

Development of any other plans or documentation which, in the judgment of the Secretary, will contribute to public safety and the sage operation of a project facility.

(2)

Costs

The Secretary is authorized to provide, on a non-reimbursable basis, up to 50 percent of the cost of such technical assistance, with the balance of such costs being advanced by the transferred works operating entity or other non-Federal source. The non-Federal 50 percent minimum cost share for such technical assistance may be in the form of in-lieu contributions of resources by the transferred works operating entity or other non-Federal source.

Legislative history

Reconstructed from this section’s Code source credit and amendment notes, resolved against the local Statutes at Large. Editorial notes are evidence, not the law that made the change.

  1. Omnibus Public Land Management Act of 2009

    Pub. L. 111–11 title IX § 9602 · 123 Stat. 991

    Enacted · 43 U.S.C. § 510a

    (Pub. L. 111–11, title IX, § 9602, Mar. 30, 2009, 123 Stat. 1347.)

    Source evidence

    Code source credit
    (Pub. L. 111–11, title IX, § 9602, Mar. 30, 2009, 123 Stat. 1347.)

    Enacted provision · exact public law section
    SEC. 9602. GUIDELINES AND INSPECTION OF PROJECT FACILITIES AND TECHNICAL ASSISTANCE TO TRANSFERRED WORKS OPERATING ENTITIES. (a) Guidelines and Inspections.— (1) Development of guidelines.— Not later than 1 year after the date of enactment of this Act, the Secretary in consultation with transferred works operating entities shall develop, consistent with existing transfer contracts, specific inspection guidelines for project facilities which are in proximity to urbanized areas and which could pose a risk to public safety or property damage if such project facilities were to fail. (2) Conduct of inspections.— Not later than 3 years after the date of enactment of this Act, the Secretary shall conduct inspections of those project facilities, which are in proximity to urbanized areas and which could pose a risk to public safety or property damage if such facilities were to fail, using such specific inspection guidelines and criteria developed pursuant to paragraph (1). In selecting project facilities to inspect, the Secretary shall take into account the potential magnitude of public safety and economic damage posed by each project facility. (3) Treatment of costs.— The costs incurred by the Secretary in conducting these inspections shall be nonreimbursable. (b) Use of Inspection Data.— The Secretary shall use the data collected through the conduct of the inspections under subsection (a)(2) to— (1) provide recommendations to the transferred works operating entities for improvement of operation and maintenance processes, operating procedures including operation guidelines consistent with existing transfer contracts, and structural modifications to those transferred works; (2) determine an appropriate inspection frequency for such nondam project facilities which shall not exceed 6 years; and (3) provide, upon request of transferred work operating entities, local governments, or State agencies, information regarding potential hazards posed by existing or proposed residential, commercial, industrial or public-use development adjacent to project facilities. (c) Technical Assistance to Transferred Works Operating Entities.— (1) Authority of secretary to provide technical assistance.— The Secretary is authorized, at the request of a transferred works operating entity in proximity to an urbanized area, to provide technical assistance to accomplish the following, if consistent with existing transfer contracts: (A) Development of documented operating procedures for a project facility. (B) Development of documented emergency notification and response procedures for a project facility. (C) Development of facility inspection criteria for a project facility. (D) Development of a training program on operation and maintenance requirements and practices for a project facility for a transferred works operating entity’s workforce. (E) Development of a public outreach plan on the operation and risks associated with a project facility. (F) Development of any other plans or documentation which, in the judgment of the Secretary, will contribute to public safety and the sage operation of a project facility. (2) Costs.— The Secretary is authorized to provide, on a non-reimbursable basis, up to 50 percent of the cost of such technical assistance, with the balance of such costs being advanced by the transferred works operating entity or other non-Federal source. The non-Federal 50 percent minimum cost share for such technical assistance may be in the form of in-lieu contributions of resources by the transferred works operating entity or other non-Federal source.

1 of 1 references resolved to an enrolled provision

Credits

(Pub. L. 111–11, title IX, § 9602, , 123 Stat. 1347.)

Parsed from the official OLRC USLM XML in data/usc_all/usc43.xml · release point 119-108 · OLRC build 2026-04-17

USLM identifier /us/usc/t43/s510a