§ 618j. Effect of refusal to modify existing contracts
Statutory text
Any contractor for energy from the project failing or refusing to execute a contract modifying its existing contract to conform to this subchapter shall continue to pay the rates and charges provided for in its existing contract, subject to such periodic readjustments as are therein provided, in all respects as if this subchapter had not been passed, and so far as necessary to support such existing contract all of the provisions of the Project Act [43 U.S.C. 617 et seq.] shall remain in effect, anything in this subchapter inconsistent therewith notwithstanding.
Legislative history
Reconstructed from this section’s Code source credit and amendment notes, resolved against the local Statutes at Large. Editorial notes are evidence, not the law that made the change.
Pub. L. 76–643 § 11 · 54 Stat. 774
Enacted · 43 U.S.C. § 618j
(July 19, 1940, ch. 643, § 11, 54 Stat. 778.)
Source evidence
Code source credit
(July 19, 1940, ch. 643, § 11, 54 Stat. 778.)Enacted provision · exact public law section
Sec. 11. Any contractor for energy from the project failing or refusing to execute a contract modifying its existing contract to conform to this Act. shall continue to pay the rates and charges provided for in its existing contract, subject to such periodic readjustments as are therein provided, in all respects as if this Act had not been passed, and so far as necessary to support such existing contract all of the 45 Stat. 1057. 43 U. S. C. §§ 617–617t. Definitions. provisions of the Project Act shall remain in effect, anything in this Act inconsistent therewith notwithstanding.
1 of 1 references resolved to an enrolled provision
Editorial Notes
References in Text
The Project Act, referred to in text, is defined in section 618k of this title.
Credits