Title 49 — Transportation
Chapter 53 — Public Transportation
§ 5327. Project management oversight
Statutory text
Project Management Plan Requirements.—
To receive Federal financial assistance for a major capital project for public transportation under this chapter or any other provision of Federal law, a recipient must prepare a project management plan approved by the Secretary and carry out the project in accordance with the project management plan. The plan shall provide for—
adequate recipient staff organization with well-defined reporting relationships, statements of functional responsibilities, job descriptions, and job qualifications;
a budget covering the project management organization, appropriate consultants, property acquisition, utility relocation, systems demonstration staff, audits, and miscellaneous payments the recipient may be prepared to justify;
a construction schedule for the project;
a document control procedure and recordkeeping system;
a change order procedure that includes a documented, systematic approach to the handling of construction change orders;
organizational structures, management skills, and staffing levels required throughout the construction phase;
quality control and quality assurance functions, procedures, and responsibilities for construction, system installation, and integration of system components;
material testing policies and procedures;
internal plan implementation and reporting requirements;
criteria and procedures to be used for testing the operational system or its major components;
periodic updates of the plan, especially related to project budget and project schedule, financing, ridership estimates, and the status of local efforts to enhance ridership where ridership estimates partly depend on the success of those efforts;
the recipient’s commitment to submit a project budget and project schedule to the Secretary quarterly; and
safety and security management.
Plan Approval.—
The Secretary shall approve a plan not later than 60 days after it is submitted. If the approval cannot be completed within 60 days, the Secretary shall notify the recipient, explain the reasons for the delay, and estimate the additional time that will be required.
The Secretary shall inform the recipient of the reasons when a plan is disapproved.
Access to Sites and Records.—
Each recipient of Federal financial assistance for public transportation under this chapter or any other provision of Federal law shall provide the Secretary and a contractor the Secretary chooses under section 5338(f) 1 with access to the construction sites and records of the recipient when reasonably necessary.
Regulations.—
The Secretary shall prescribe regulations necessary to carry out this section. The regulations shall include—
a definition of “major capital project” for section 5338(f) 1 that excludes a project to acquire rolling stock or to maintain or rehabilitate a vehicle;
a requirement that oversight—
begin during the project development phase of a project, unless the Secretary finds it more appropriate to begin the oversight during another phase of the project, to maximize the transportation benefits and cost savings associated with project management oversight; and
be limited to quarterly reviews of compliance by the recipient with the project management plan approved under subsection (b) unless the Secretary finds that the recipient requires more frequent oversight because the recipient has failed to meet the requirements of such plan and the project may be at risk of going over budget or becoming behind schedule; and
a process for recipients that the Secretary has found require more frequent oversight to return to quarterly reviews for purposes of paragraph (2)(B).
Footnotes
- 1 See References in Text note below.
Legislative history
Reconstructed from this section’s Code source credit and amendment notes, resolved against the local Statutes at Large. Editorial notes are evidence, not the law that made the change.
Pub. L. 103–272 § 1(d) · 108 Stat. 745
Enacted · 49 U.S.C. § 5327
Pub. L. 103–272, § 1(d), July 5, 1994, 108 Stat. 826
Source evidence
Code source credit
Pub. L. 103–272, § 1(d), July 5, 1994, 108 Stat. 826Enacted provision · exact public law section
(d) Title 49, United States Code, is amended by adding the following immediately after subtitle I:Pub. L. 103–429 § 6(12) · 108 Stat. 4377
Substituted · 49 U.S.C. § 5327(c)(1)
Pub. L. 103–429 substituted “section 5307, 5309, 5311, or 103(e)(4) or that Act” for “section 5307, 5309, 5311, or 103(e)(4) of that Act”
Source evidence
Code amendment note
Subsec. (c)(1). Pub. L. 103–429 substituted “section 5307, 5309, 5311, or 103(e)(4) or that Act” for “section 5307, 5309, 5311, or 103(e)(4) of that Act”.Enacted provision · exact public law section
(12) In section 5327(c)(1), strike “of that Act” and substitute “or that Act”.Pub. L. 104–287 § 5(17) · 110 Stat. 3388
Substituted · 49 U.S.C. § 5327(c)(1)
Pub. L. 104–287 substituted “to carry out a major project under section 5309” for “to carry out a major project under section 5307”
Source evidence
Code amendment note
Subsec. (c)(1). Pub. L. 104–287 substituted “to carry out a major project under section 5309” for “to carry out a major project under section 5307”.Enacted provision · exact public law section
(17) Section 5327(c) is amended by striking “to carry out a major project under section 5307” and substituting “to carry out a major project under section 5309”.Federal Transit Act of 1998
Pub. L. 105–178 § 3024(a) · 112 Stat. 107
Substituted · 49 U.S.C. § 5327(c)(2)
Pub. L. 105–178, § 3024(a), substituted “enter into contracts” for “make contracts”
Inserted · 49 U.S.C. § 5327(c)(2)
Pub. L. 105–178, § 3024(a), inserted “and to provide technical assistance to correct deficiencies identified in compliance reviews and audits carried out under this section” before period at end of first sentence
Source evidence
Code amendment note
Subsec. (c)(2). Pub. L. 105–178, § 3024(a), substituted “enter into contracts” for “make contracts” and inserted “and to provide technical assistance to correct deficiencies identified in compliance reviews and audits carried out under this section” before period at end of first sentence.Enacted provision · exact public law section
(a) Limitation on Use of Available Amounts.— Section 5327(c)(2) is amended— (1) by striking “make contracts” and inserting “enter into contracts”; and (2) by inserting before the period at the end of the first sentence the following: “and to provide technical assistance to correct deficiencies identified in compliance reviews and audits carried out under this section”.Federal Transit Act of 1998
Pub. L. 105–178 § 3024(b) · 112 Stat. 107
Added · 49 U.S.C. § 5327(f)
Pub. L. 105–178, § 3024(b), added subsec. (f)
Source evidence
Code amendment note
Subsec. (f). Pub. L. 105–178, § 3024(b), added subsec. (f).Enacted provision · exact public law section
(b) Financial Plan.— Section 5327 is amended by adding at the end the following: “(f) Financial Plan.— A recipient of financial assistance for a project under this chapter with an estimated total cost of $1,000,000,000 or more shall submit to the Secretary an annual financial plan for the project. The plan shall be based on detailed annual estimates of the cost to complete the remaining elements of the project and on reasonable assumptions, as determined by the Secretary, of future increases in the cost to complete the project.”.Federal Public Transportation Act of 2005
Pub. L. 109–59 § 3026(a) · 119 Stat. 1144
Added · 49 U.S.C. § 5327(a)(13)
Pub. L. 109–59, § 3026(a), added par. (13)
Source evidence
Code amendment note
Subsec. (a)(13). Pub. L. 109–59, § 3026(a), added par. (13).Enacted provision · exact public law section
(a) Project Management Plan Requirements.— Section 5327(a) is amended— (1) in paragraph (11) by striking “and” at the end; (2) in paragraph (12) by striking the period at the end and inserting “; and”; and (3) by adding at the end the following: “(13) safety and security management.” .Federal Public Transportation Act of 2005
Pub. L. 109–59 § 3026(b) · 119 Stat. 1144
Amended · 49 U.S.C. § 5327(c)
Pub. L. 109–59, § 3026(b), amended subsec. (c) generally. Prior to amendment, subsec. (c) specified limitations on use of available amounts for certain purposes
Source evidence
Code amendment note
Subsec. (c). Pub. L. 109–59, § 3026(b), amended subsec. (c) generally. Prior to amendment, subsec. (c) specified limitations on use of available amounts for certain purposes.Enacted provision · exact public law section
(b) Limitations.— Section 5327(c) is amended to read as follows: “(c) Limitations.— “(1) Limitations on use of available amounts.— Of the amounts made available to carry out this chapter for a fiscal year, the Secretary may use not more than the following amounts to make contracts for the activities described in paragraph (2): “(A) 0.5 percent of amounts made available to carry out section 5305. “(B) 0.75 percent of amounts made available to carry out section 5307. “(C) 1 percent of amounts made available to carry out section 5309. “(D) 0.5 percent of amounts made available to carry out section 5310. “(E) 0.5 percent of amounts made available to carry out section 5311. “(F) 0.5 percent of amounts made available to carry out section 5320. “(2) Activities.— Paragraph (1) shall apply to the following: “(A) Activities to oversee the construction of a major project. “(B) Activities to review and audit the safety and security, procurement, management, and financial compliance of a recipient or subrecipient of funds under sections 5305, 5307, 5309, 5310, 5311, and 5320. “(C) Activities to provide technical assistance to correct deficiencies identified in compliance reviews and audits carried out under this section. “(3) Limitations on applicability.— Subsections (a), (b), and (e) do not apply to contracts under this section for activities described in paragraphs (2)(B) and (2)(C). “(4) Government’s share of costs.— The Government shall pay the entire cost of carrying out a contract under this subsection. “(5) Availability of certain funds.— Beginning in fiscal year 2006, funds available under paragraph (1)(C) shall be made available to the Secretary before allocating the funds appropriated to carry out any project under a full funding grant agreement or project construction grant agreement.” .Federal Public Transportation Act of 2012
Pub. L. 112–141 § 20020(1)(A) · 126 Stat. 405
Substituted · 49 U.S.C. § 5327(a)
Pub. L. 112–141, § 20020(1)(A), in introductory provisions, substituted “Federal financial assistance for a major capital project for public transportation under this chapter or any other provision of Federal law, a recipient must prepare a project management plan approved by the Secretary and carry out the project in accordance with the project management plan” for “United States Government financial assistance for a major capital project under this chapter or the National Capital Transportation Act of 1969 (Public Law 91–143, 83 Stat. 320), a recipient must prepare and carry out a project management plan approved by the Secretary of Transportation”
Source evidence
Code amendment note
Subsec. (a). Pub. L. 112–141, § 20020(1)(A), in introductory provisions, substituted “Federal financial assistance for a major capital project for public transportation under this chapter or any other provision of Federal law, a recipient must prepare a project management plan approved by the Secretary and carry out the project in accordance with the project management plan” for “United States Government financial assistance for a major capital project under this chapter or the National Capital Transportation Act of 1969 (Public Law 91–143, 83 Stat. 320), a recipient must prepare and carry out a project management plan approved by the Secretary of Transportation”.Enacted provision · exact public law section
(A) in the matter preceding paragraph (1), by striking “United States” and all that follows through “Secretary of Transportation” and inserting the following: “Federal financial assistance for a major capital project for public transportation under this chapter or any other provision of Federal law, a recipient must prepare a project management plan approved by the Secretary and carry out the project in accordance with the project management plan”; andFederal Public Transportation Act of 2012
Pub. L. 112–141 § 20020(1)(B) · 126 Stat. 405
Substituted · 49 U.S.C. § 5327(a)(12)
Pub. L. 112–141, § 20020(1)(B), substituted “quarterly” for “each month”
Source evidence
Code amendment note
Subsec. (a)(12). Pub. L. 112–141, § 20020(1)(B), substituted “quarterly” for “each month”.Enacted provision · exact public law section
(B) in paragraph (12), by striking “each month” and inserting “quarterly”;Federal Public Transportation Act of 2012
Pub. L. 112–141 § 20020(2) · 126 Stat. 405
Added · 49 U.S.C. § 5327(c)
Pub. L. 112–141, § 20020(2), (3), added subsec. (c)
Struck · 49 U.S.C. § 5327(c)
Pub. L. 112–141, § 20020(2), (3), struck out former subsec. (c) which related to limitations
Source evidence
Code amendment note
Subsec. (c). Pub. L. 112–141, § 20020(2), (3), added subsec. (c) and struck out former subsec. (c) which related to limitations.Enacted provision · exact public law section
(2) by striking subsections (c), (d), and (f);Federal Public Transportation Act of 2012
Pub. L. 112–141 § 20020(2) · 126 Stat. 405
Redesignated · 49 U.S.C. § 5327(d)
Pub. L. 112–141, § 20020(2), (4), redesignated subsec. (e) as (d)
Struck · 49 U.S.C. § 5327(d)
Pub. L. 112–141, § 20020(2), (4), struck out former subsec. (d) which related to access to sites and records
Source evidence
Code amendment note
Subsec. (d). Pub. L. 112–141, § 20020(2), (4), redesignated subsec. (e) as (d) and struck out former subsec. (d) which related to access to sites and records.Enacted provision · exact public law section
(2) by striking subsections (c), (d), and (f);Federal Public Transportation Act of 2012
Pub. L. 112–141 § 20020(5)(A) · 126 Stat. 405
Substituted · 49 U.S.C. § 5327(d)(1)
Pub. L. 112–141, § 20020(5)(A), substituted “section 5338(i)” for “subsection (c) of this section”
Source evidence
Code amendment note
Subsec. (d)(1). Pub. L. 112–141, § 20020(5)(A), substituted “section 5338(i)” for “subsection (c) of this section”.Enacted provision · exact public law section
(A) in paragraph (1), by striking “subsection (c) of this section” and inserting “section 5338(i)”; andFederal Public Transportation Act of 2012
Pub. L. 112–141 § 20020(5)(B) · 126 Stat. 405
Substituted · 49 U.S.C. § 5327(d)(2)
Pub. L. 112–141, § 20020(5)(B), substituted “project development phase” for “preliminary engineering stage”
Substituted · 49 U.S.C. § 5327(d)(2)
Pub. L. 112–141, § 20020(5)(B), substituted “another phase” for “another stage”
Source evidence
Code amendment note
Subsec. (d)(2). Pub. L. 112–141, § 20020(5)(B), substituted “project development phase” for “preliminary engineering stage” and “another phase” for “another stage”.Enacted provision · exact public law section
(B) in paragraph (2)— (i) by striking “preliminary engineering stage” and inserting “project development phase”; and (ii) by striking “another stage” and inserting “another phase”.Federal Public Transportation Act of 2012
Pub. L. 112–141 § 20020(4) · 126 Stat. 405
Redesignated · 49 U.S.C. § 5327(e)
Pub. L. 112–141, § 20020(4), redesignated subsec. (e) as (d)
Source evidence
Code amendment note
Subsec. (e). Pub. L. 112–141, § 20020(4), redesignated subsec. (e) as (d).Enacted provision · exact public law section
(4) by redesignating subsection (e) as subsection (d); andFederal Public Transportation Act of 2012
Pub. L. 112–141 § 20020(2) · 126 Stat. 405
Struck · 49 U.S.C. § 5327(f)
Pub. L. 112–141, § 20020(2), struck out subsec. (f). Text read as follows: “A recipient of financial assistance for a project under this chapter with an estimated total cost of $1,000,000,000 or more shall submit to the Secretary an annual financial plan for the project. The plan shall be based on detailed annual estimates of the cost to complete the remaining elements of the project and on reasonable assumptions, as determined by the Secretary, of future increases in the cost to complete the project.”
Source evidence
Code amendment note
Subsec. (f). Pub. L. 112–141, § 20020(2), struck out subsec. (f). Text read as follows: “A recipient of financial assistance for a project under this chapter with an estimated total cost of $1,000,000,000 or more shall submit to the Secretary an annual financial plan for the project. The plan shall be based on detailed annual estimates of the cost to complete the remaining elements of the project and on reasonable assumptions, as determined by the Secretary, of future increases in the cost to complete the project.”Enacted provision · exact public law section
(2) by striking subsections (c), (d), and (f);Federal Public Transportation Act of 2015
Pub. L. 114–94 § 3012(1) · 129 Stat. 1312
Substituted · 49 U.S.C. § 5327(c)
Pub. L. 114–94, § 3012(1), which directed substitution of section “5338(f)” for “section 5338(i)” to reflect the probable intent of Congress
Substituted · 49 U.S.C. § 5327(c)
Pub. L. 114–94, § 3012(1), which directed substitution of section “section 5338(f)” for “section 5338(i)” to reflect the probable intent of Congress
Source evidence
Code amendment note
Subsec. (c). Pub. L. 114–94, § 3012(1), which directed substitution of section “5338(f)” for “section 5338(i)”, was executed by substituting “section 5338(f)” for “section 5338(i)”, to reflect the probable intent of Congress.Enacted provision · exact public law section
(1) in subsection (c) by striking “section 5338(i)” and inserting section “5338(f)” ; andEffective date note
Amendment by Pub. L. 114–94 effective Oct. 1, 2015, see section 1003 of Pub. L. 114–94, set out as a note under section 5313 of Title 5, Government Organization and Employees.Federal Public Transportation Act of 2015
Pub. L. 114–94 § 3012(2)(A)(i) · 129 Stat. 1312
Substituted · 49 U.S.C. § 5327(d)(1)
Pub. L. 114–94, § 3012(2)(A)(i), which directed substitution of section 5338(f) for “section 5338(i)” without placing quotation marks around the language to be substituted, was executed by substituting “section 5338(f)” for “section 5338(i)”, to reflect the probable intent of Congress
Source evidence
Code amendment note
Subsec. (d)(1). Pub. L. 114–94, § 3012(2)(A)(i), which directed substitution of section 5338(f) for “section 5338(i)” without placing quotation marks around the language to be substituted, was executed by substituting “section 5338(f)” for “section 5338(i)”, to reflect the probable intent of Congress.Enacted provision · exact public law section
(i) by striking “section 5338(i)” and inserting section 5338(f); andEffective date note
Amendment by Pub. L. 114–94 effective Oct. 1, 2015, see section 1003 of Pub. L. 114–94, set out as a note under section 5313 of Title 5, Government Organization and Employees.Federal Public Transportation Act of 2015
Pub. L. 114–94 § 3012(2)(A)(ii) · 129 Stat. 1312
Added · 49 U.S.C. § 5327(d)(2); 49 U.S.C. § 5327(d)(3)
Pub. L. 114–94, § 3012(2)(A)(ii), (B), added pars. (2) and (3)
Struck · 49 U.S.C. § 5327(d)(2); 49 U.S.C. § 5327(d)(3)
Pub. L. 114–94, § 3012(2)(A)(ii), (B), struck out former par. (2), which read as follows: “a requirement that oversight begin during the project development phase of a project, unless the Secretary finds it more appropriate to begin the oversight during another phase of the project, to maximize the transportation benefits and cost savings associated with project management oversight.”
Source evidence
Code amendment note
Subsec. (d)(2), (3). Pub. L. 114–94, § 3012(2)(A)(ii), (B), added pars. (2) and (3) and struck out former par. (2), which read as follows: “a requirement that oversight begin during the project development phase of a project, unless the Secretary finds it more appropriate to begin the oversight during another phase of the project, to maximize the transportation benefits and cost savings associated with project management oversight.”Enacted provision · exact public law section
(ii) by striking “and” at the end; andEffective date note
Amendment by Pub. L. 114–94 effective Oct. 1, 2015, see section 1003 of Pub. L. 114–94, set out as a note under section 5313 of Title 5, Government Organization and Employees.
24 of 24 references resolved to an enrolled provision
Notes
historicalAndRevision
| Historical and Revision Notes | ||
|---|---|---|
| Pub. L. 103–272 | ||
| RevisedSection | Source (U.S. Code) | Source (Statutes at Large) |
| 5327(a) | 49 App.:1619(d), (e). | July 9, 1964, Pub. L. 88–365, 78 Stat. 302, § 23(b)–(g); added Apr. 2, 1987, Pub. L. 100–17, § 324, 101 Stat. 236. |
| 5327(b) | 49 App.:1619(g). | |
| 5327(c)(1) | 49 App.:1619(a). | July 9, 1964, Pub. L. 88–365, 78 Stat. 302, § 23(a); added Apr. 2, 1987, Pub. L. 100–17, § 324, 101 Stat. 235; Dec. 18, 1991, Pub. L. 102–240, § 3027, 105 Stat. 2115. |
| 5327(c)(2) | 49 App.:1619(h). | July 9, 1964, Pub. L. 88–365, 78 Stat. 302, § 23(h); added Nov. 21, 1989, Pub. L. 101–164, § 340, 103 Stat. 1099. |
| 5327(c)(3) | 49 App.:1619(b). | |
| 5327(d) | 49 App.:1619(c). | |
| 5327(e) | 49 App.:1619(f). | |
In subsection (a), before clause (1), the words “as required in each case by the Secretary” are omitted as surplus. In clause (11), the words “such items as” and “where applicable” are omitted as surplus.
In subsection (c)(1), the words “Beginning ” are omitted as executed. The words “with any person” are omitted as surplus.
In subsection (c)(2), the words “In addition to the purposes provided for under subsection (a) of this section” and “with any person” are omitted as surplus. The cross-reference to paragraph (1) is not changed. The cross-reference in 49 App.:1619(h), the source provision being restated in this subsection, is no longer correct, but is apparently still meant to apply to funds made available under 49 App.:1619(a).
In subsection (e), before clause (1), the text of 49 App.:1619(f) (2d sentence) is omitted as executed. In clause (1), The words “vehicles or other” and “the performance of” are omitted as surplus.
Pub. L. 103–429
This amends 49:5327(c)(1) to correct an erroneous cross-reference.
Pub. L. 104–287
This amends 49:5327(c) to correct an erroneous cross-reference.
Editorial Notes
References in Text
Section 5338, referred to in subsecs. (c) and (d)(1), was amended generally by Pub. L. 117–58, div. C, § 30017, , 135 Stat. 912. As amended, section 5338 no longer contains a subsec. (f). Provisions relating to oversight, formerly contained in section 5338(f), can be found elsewhere in section 5338.
Amendments1994–2015 · 6 rounds
2015
Subsec. (c). Pub. L. 114–94, § 3012(1), which directed substitution of section “5338(f)” for “section 5338(i)”, was executed by substituting “section 5338(f)” for “section 5338(i)”, to reflect the probable intent of Congress.
Subsec. (d)(1). Pub. L. 114–94, § 3012(2)(A)(i), which directed substitution of section 5338(f) for “section 5338(i)” without placing quotation marks around the language to be substituted, was executed by substituting “section 5338(f)” for “section 5338(i)”, to reflect the probable intent of Congress.
Subsec. (d)(2), (3). Pub. L. 114–94, § 3012(2)(A)(ii), (B), added pars. (2) and (3) and struck out former par. (2), which read as follows: “a requirement that oversight begin during the project development phase of a project, unless the Secretary finds it more appropriate to begin the oversight during another phase of the project, to maximize the transportation benefits and cost savings associated with project management oversight.”
2012
Subsec. (a). Pub. L. 112–141, § 20020(1)(A), in introductory provisions, substituted “Federal financial assistance for a major capital project for public transportation under this chapter or any other provision of Federal law, a recipient must prepare a project management plan approved by the Secretary and carry out the project in accordance with the project management plan” for “United States Government financial assistance for a major capital project under this chapter or the National Capital Transportation Act of 1969 (Public Law 91–143, 83 Stat. 320), a recipient must prepare and carry out a project management plan approved by the Secretary of Transportation”.
Subsec. (a)(12). Pub. L. 112–141, § 20020(1)(B), substituted “quarterly” for “each month”.
Subsec. (c). Pub. L. 112–141, § 20020(2), (3), added subsec. (c) and struck out former subsec. (c) which related to limitations.
Subsec. (d). Pub. L. 112–141, § 20020(2), (4), redesignated subsec. (e) as (d) and struck out former subsec. (d) which related to access to sites and records.
Subsec. (d)(1). Pub. L. 112–141, § 20020(5)(A), substituted “section 5338(i)” for “subsection (c) of this section”.
Subsec. (d)(2). Pub. L. 112–141, § 20020(5)(B), substituted “project development phase” for “preliminary engineering stage” and “another phase” for “another stage”.
Subsec. (e). Pub. L. 112–141, § 20020(4), redesignated subsec. (e) as (d).
Subsec. (f). Pub. L. 112–141, § 20020(2), struck out subsec. (f). Text read as follows: “A recipient of financial assistance for a project under this chapter with an estimated total cost of $1,000,000,000 or more shall submit to the Secretary an annual financial plan for the project. The plan shall be based on detailed annual estimates of the cost to complete the remaining elements of the project and on reasonable assumptions, as determined by the Secretary, of future increases in the cost to complete the project.”
2005
Subsec. (a)(13). Pub. L. 109–59, § 3026(a), added par. (13).
Subsec. (c). Pub. L. 109–59, § 3026(b), amended subsec. (c) generally. Prior to amendment, subsec. (c) specified limitations on use of available amounts for certain purposes.
1998
Subsec. (c)(2). Pub. L. 105–178, § 3024(a), substituted “enter into contracts” for “make contracts” and inserted “and to provide technical assistance to correct deficiencies identified in compliance reviews and audits carried out under this section” before period at end of first sentence.
Subsec. (f). Pub. L. 105–178, § 3024(b), added subsec. (f).
1996
Subsec. (c)(1). Pub. L. 104–287 substituted “to carry out a major project under section 5309” for “to carry out a major project under section 5307”.
1994
Subsec. (c)(1). Pub. L. 103–429 substituted “section 5307, 5309, 5311, or 103(e)(4) or that Act” for “section 5307, 5309, 5311, or 103(e)(4) of that Act”.
Statutory Notes and Related Subsidiaries
Effective Date of 2015 Amendment
Amendment by Pub. L. 114–94 effective , see section 1003 of Pub. L. 114–94, set out as a note under section 5313 of Title 5, Government Organization and Employees.
Effective Date of 2012 Amendment
Amendment by Pub. L. 112–141 effective , see section 3(a) of Pub. L. 112–141, set out as an Effective and Termination Dates of 2012 Amendment note under section 101 of Title 23, Highways.
Effective Date of 1996 Amendment
Amendment by Pub. L. 104–287 effective , see section 8(1) of Pub. L. 104–287, set out as a note under section 5303 of this title.
Effective Date of 1994 Amendment
Amendment by Pub. L. 103–429 effective , see section 9 of Pub. L. 103–429, set out as a note under section 321 of this title.
Financing of Oversight Activities
Pub. L. 107–87, title III, § 319, , 115 Stat. 858, provided that: “Beginning in fiscal year 2002 and thereafter, the Secretary may use up to 1 percent of the amounts made available to carry out 49 U.S.C. 5309 for oversight activities under 49 U.S.C. 5327.”
Credits
1994–2015 · 7 acts
- 1994Pub. L. 103–272, § 1(d), , 108 Stat. 826
- 1994Pub. L. 103–429, § 6(12), , 108 Stat. 4379
- 1996Pub. L. 104–287, § 5(17), , 110 Stat. 3390
- 1998Pub. L. 105–178, title III, § 3024, , 112 Stat. 364
- 2005Pub. L. 109–59, title III, § 3026, , 119 Stat. 1622
- 2012Pub. L. 112–141, div. B, § 20020, , 126 Stat. 708
- 2015Pub. L. 114–94, div. A, title III, § 3012, , 129 Stat. 1475.
Show as published
(Pub. L. 103–272, § 1(d), , 108 Stat. 826; Pub. L. 103–429, § 6(12), , 108 Stat. 4379; Pub. L. 104–287, § 5(17), , 110 Stat. 3390; Pub. L. 105–178, title III, § 3024, , 112 Stat. 364; Pub. L. 109–59, title III, § 3026, , 119 Stat. 1622; Pub. L. 112–141, div. B, § 20020, , 126 Stat. 708; Pub. L. 114–94, div. A, title III, § 3012, , 129 Stat. 1475.)